Second Notice | | 1/9/2014 | 1/9/2014 | | DONE |
Christina Prado
|
|
|
completed 1-9-14
|
First Notice | | 12/22/2013 | 12/30/2013 | | DONE |
Christina Prado
|
|
|
mailed 12-30-13
|
BLD-Final | 12/11/2013 | 12/12/2013 | 12/12/2013 | A | PASS |
Tom Arcoraci
|
|
|
Morgan-PLease call prior to inspection Phone #: ###-####
|
Permanent Occupancy | | | 12/12/2013 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/10/2013 | 12/11/2013 | 12/11/2013 | A | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
FIRE-Final Inspection | 12/9/2013 | 12/10/2013 | 12/10/2013 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans on site and no contact on site.
|
CHANGE STATUS TO (ISS) | | | 11/14/2013 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 11/14/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Framing/Rough-in | 11/6/2013 | 11/7/2013 | 11/7/2013 | P | PASS |
Tom Arcoraci
|
|
|
Brad @ ###-####
|
CHANGE STATUS TO (ISS) | | | 11/1/2013 | | DONE |
Tisha Gallop
|
|
|
changed status to ISS so electrical contractor could pull permit online.
|
CHANGE STATUS TO (RDY) | | | 11/1/2013 | | DONE |
Tisha Gallop
|
|
|
change back to RDY status
|
Routing - PLAN CHECK | 10/23/2013 | | 10/30/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Design Review | 10/28/2013 | | 10/28/2013 | | PASS |
Josh Wilson
|
|
|
Modifications ok
|
Permit Ready to Issue | | | 10/22/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 10/22/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/22/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 9/19/2013 | 9/19/2013 | 10/2/2013 | | PASS |
Carl D Madsen
|
|
|
Due 10/2 E plan Level II
|
Routing PW Environmental | 9/20/2013 | | 10/2/2013 | | PASS |
Walt Baumgartner
|
|
|
|
Routing - PLAN CHECK | 10/2/2013 | | 10/2/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/1/2013 | | 10/1/2013 | | FAIL |
Carl D Madsen
|
|
|
Original items were not adequately addressed.
|
1st review completed | | | 9/27/2013 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 9/19/2013 | | 9/27/2013 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - Design Review | 9/19/2013 | | 9/27/2013 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PUBLIC WORKS | 9/19/2013 | | 9/20/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 9/19/2013 | | 9/20/2013 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 9/19/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 9/18/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 18 2013 10:20AM
|
Intake Approval | | | 9/18/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
The 518 check list in the documents is not completed. Please complete the 518 check list.
|