First Notice | | 2/28/2014 | 4/1/2014 | | DONE |
|
|
|
Faxed 4-1-14
|
BLD-Final | 2/18/2014 | 2/18/2014 | 2/18/2014 | P | PASS |
Tom Arcoraci
|
|
|
|
Permanent Occupancy | | | 2/18/2014 | | DONE |
|
|
|
|
Temporary Occupancy | 2/14/2014 | 5/15/2014 | 2/14/2014 | | DONE |
Tisha Gallop
|
|
|
pending plumbing and structural (after plumbing perms)
|
PubWorks Occupancy Approval | 2/14/2014 | 2/14/2014 | 2/14/2014 | | DONE |
Tiffany Lowery
|
|
|
This project did not require Public Works inspection per Brian Murphy.
|
BLD-Final | 2/12/2014 | 2/13/2014 | 2/13/2014 | P | PART |
Jim Sly
|
|
|
ivey Phone #: ###-#### OK for Temp Occ. OK for perm occ. when Plumbing perms.
|
FIRE-Final Inspection | 2/13/2014 | 2/13/2014 | 2/13/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide the missing exit sign and the ADA hardware for the pocket door prior to a building inspection. I also noted that per the plans the door to the Gas Room is to be self closing.
|
FIRE-Final Inspection | 2/12/2014 | 2/13/2014 | 2/13/2014 | A | FAIL |
Troy Cobbley
|
|
|
No small documents provided. No inspection performed. Rescheduled for this afternoon.
|
BLD-Ceiling Grid Inspection | 1/23/2014 | 1/23/2014 | 1/23/2014 | P | PASS |
Tom Arcoraci
|
|
|
izey Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 1/22/2014 | | DONE |
Tisha Gallop
|
|
|
plan mod issued
|
Print Occupancy Form | | | 1/22/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (SRZ) | 12/10/2013 | | 12/19/2013 | | PASS |
Sam Zahorka
|
|
|
Plan Modification
|
Routing - PLAN CHECK | 12/10/2013 | | 12/19/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/19/2013 | | DONE |
|
|
|
|
Routing - FIRE | 12/10/2013 | | 12/12/2013 | | PASS |
Craig D. Hanson
|
|
|
|
Routing - MECHANICAL | 12/10/2013 | | 12/12/2013 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 12/9/2013 | | DONE |
|
|
|
started worflow
|
BLD-Framing/Rough-in | 12/4/2013 | 12/5/2013 | 12/5/2013 | A | PART |
Tom Arcoraci
|
|
|
Call for access - Scott Phone #: ###-#### cn posted ok to continue needs approval from plan review
|
Telephone call | | | 11/15/2013 | | DONE |
|
|
|
Jason Hoskins with Advantage Architecture called to add the name of the business for this dentist's pracice. Dustin Connaughton is the dentist and the business name is Tree City Family Dental.
|
Print Occupancy Form | | | 11/12/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/12/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/12/2013 | | DONE |
|
|
|
|
Routing - FIRE | 11/8/2013 | 11/8/2013 | 11/8/2013 | | PASS |
Craig D. Hanson
|
|
|
See report
|
Plan assigned to (SRZ) | 10/9/2013 | 10/9/2013 | 11/8/2013 | | PASS |
Sam Zahorka
|
|
|
ePlanReview - Level 3 TI - Duston Connaughton DDS
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing PW Environmental | 11/8/2013 | | 11/8/2013 | | PASS |
Walt Baumgartner
|
|
|
Hg5 Amalgam Separator to be installed, ok
|
Routing - PLAN CHECK | 11/8/2013 | | 11/8/2013 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 10/30/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 10/9/2013 | | 10/30/2013 | | FAIL |
Sam Zahorka
|
|
|
|
Routing PW Sewer Rating | 10/9/2013 | | 10/30/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Telephone call | | | 10/17/2013 | | DONE |
|
|
|
Spoke with architect on 10/17. he is says he going to add a head in the gas room off the plumbing system, show the door schedule and specify the tennant space. CDH
|
Routing - FIRE | 10/9/2013 | 10/9/2013 | 10/15/2013 | | FAIL |
Craig D. Hanson
|
|
|
See attached letter
|
Routing - PLUMBING | 10/9/2013 | | 10/15/2013 | | PASS |
Bill VanDegrift
|
|
|
May require additional backflow protection on equipment.
Provide tempered water at public lavs.
Install plumbing per ISPC and med gas per NFPA 99C.
|
Plan Reviewer's activity | | | 10/11/2013 | | DONE |
Jason Blais
|
|
|
Received email from Christy Little at ACHD. No impact fees or inspection required.
|
Routing - Erosion and Sediment | 10/9/2013 | | 10/10/2013 | | PASS |
Evan Jenkins
|
|
|
|
Pending Assignment by JCB | 10/9/2013 | | 10/9/2013 | | DONE |
Jason Blais
|
|
|
|
Routing PW Environmental | 10/9/2013 | | 10/9/2013 | | FAIL |
Walt Baumgartner
|
|
|
ISO certified amalgam separator required for vacuum system prior to sewer discharge.
|
Plan Reviewer's activity | | | 10/9/2013 | | DONE |
Jason Blais
|
|
|
Emailed architect to have him contact ACHD for evaluation of any impact fees due. Written verification from ACHD needs to be provided to our Permit Counter prior to the building permit being issued.
|
Routing - Addressing | 10/9/2013 | | 10/9/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/9/2013 | | 10/9/2013 | | PASS |
Beverly Mountain
|
|
|
|
Payment Received | | | 10/8/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 10/8/2013 | | PASS |
Jason Blais
|
|
|
Prescreen passed on 10/8/13 by Adele Schaffeld-Grifffin. Plan Review Fees paid on 10/8/13.
|
Intake Approval | | | 10/7/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Jay, I sent you this email this morning. I have not heard back so I am sending the task back to you to upload the ESC permit application.
Jay, I received the revised plan submittal. The only item left from the check list is the ESC permit application as noted on the 520 check list. I have attached the permit. The waiver letter only waives the requirement to submit plans. You still have to apply for the permit. If you can complete it and send it back I will upload it and approve the prescreen.
Thanks
Adele J. Schaffeld-Griffin
City of Boise
Plans Examiner II
###-####
|
Intake Approval | | | 10/3/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Thank you for re submitting you plans for pre screen review. The scope of the project places it into the Major plan review classification. There is no need to complete another application or check list. I have completed and uploaded the Major TI check list for you and changed the minor application to Major.
Please see the additional information that is required for this submittal on the 520 check list.
If you have any questions please feel free to contact me.
Thank you
Adele Schaffeld Griffin
###-####
|
Intake Approval | | | 9/26/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Before the pre screen can begin please re upload the drawing sheets individually with conventional naming such as A1.0 Floor Plan.
Please revise plans to have the required stamping area's required. The cover sheets needs a 4 inch by 4 inch space located 3 inches off the right sheet edge and each additional drawing needs a 4 inch by 2 inch space located 3 inches off the right sheet edge to allow for city stamps.
Once the plans are uploaded correctly and returned I will begin the pre screen.
Please refer to the required electronic plan submittal standards.
Thank you
|
Application received | | | 9/19/2013 | | PASS |
Jim Sly
|
|
|
per temp occupancy notes ok for final when plumbing signs off . ///signed of building final for Jim Sly ///dld
|