Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD13-02585
StatusFinaled
Name ESI
Site Address 800 W MAIN ST Unit: 210
Project NameZenergy Athletic Club
Customer Number 
ePlanReviewYes
Description
(ZENERGY ATHLETIC CLUB)(8TH & MAIN BLDG - SUITE 210)(PLAN MODIFICATION includes...) This permit includes the gym and group fitness area in suite 220 and the office/mercantile/locker room located in suite 210. Tenant improvement plans include nonbearing noncombustible walls to create the 2,793 sq ft gym, 1,116 sq ft group fitness, 318 sq ft boutique, 5 offices 2 locker room and a family assist restroom. The non-rated corridor construction is included in this tenant improvement. Scope of work includes associated plumbing, mechanical and electrical work. New suspended ceilings and hard ceilings in the rest room and locker rooms will be constructed. There is access to the parking garage between the two suites however this is not an exit. The drinking fountain and floor sink are fixtures are utilized from the core area. Special inspection required for Aspen Tree Wall as per plans and documents. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. All high-rise fire and life safety systems must also be installed and operational before occupancy. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **AJS**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 9/3/201410/9/2014 DONE
This permit finaled on the web by Adam Johnson
Third Notice 6/14/20148/29/2014 DONE
e-mailed to Adam Johnson
Third Notice 5/10/20146/9/2014 DONE
e-mailed to Adam Johnson
Second Notice 4/10/20145/5/2014 DONE
e-mailed to Adam Johnson
First Notice 3/9/20143/31/2014 DONE
BLD-Final2/27/20142/27/20142/27/2014PPASS
DetailsDave Hannah
Adam - call for access Phone #: ###-####
Permanent Occupancy  2/27/2014 DONE
DetailsTisha Gallop
BLD-Final2/24/20142/26/20142/26/2014PPART
DetailsDave Hannah
Final BLD inspection request, coordinate with Korey or Adam for walk. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok for temp occ
FIRE-Final Inspection2/24/20142/26/20142/26/2014APASS
DetailsTroy Cobbley
Life safety passed
Temporary Occupancy2/26/20145/27/20142/26/2014 DONE
DetailsAlexandra L. DeYoung
BLD-Ceiling Grid Inspection2/19/20142/19/20142/20/2014PPASS
DetailsDave Hannah
Ceiling grid inspection. 2nd half requested by Kory, second floor Zenergy t.i. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Ceiling Grid Inspection2/14/20142/14/20142/19/2014PPART
DetailsDave Hannah
Ceiling inspection walk of Zenergy, 2nd floor. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover hallways
BLD-Ceiling Grid Inspection2/6/20142/7/20142/7/2014APASS
DetailsDave Hannah
Follow up to on site ceiling grid inspection, follow up of added wires requested by Dave Hannah. Thanks. AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Conference1/7/20141/7/20141/9/2014PPART
DetailsDave Hannah
adam Phone #: ###-#### fire proofing ok ok to cover all walls
Plan assigned to (AJS)12/20/201312/20/20131/7/2014 PASS
DetailsAdele J Schaffeld-Griffin
1st review comments Plan Mod - Zenergy Athletic Club
Plan Reviewer's activity  1/7/2014 DONE
DetailsAdele J Schaffeld-Griffin
recieved email from Nicole withdrawing the plan modification. 1/7/14
PLANS/APPL TAKEN TO FRONT DESK  1/7/2014 DONE
CHANGE STATUS TO (ISS)  1/7/2014 DONE
DID NOT DO MOD
BLD-Framing/Rough-in12/27/20131/2/20141/3/2014APASS
DetailsDave Hannah
Adam @ ###-####
Plan Reviewer's activity  1/3/2014 DONE
DetailsAdele J Schaffeld-Griffin
Recieved email from Nicole. I called and spoke with her. She will have to get back to me on the door as it does not meet code requirements to open into the cooridor. She is working through issues with their door hardware supplier and will get back to me. 1/3/14
Routing - PLAN CHECK12/20/2013 12/26/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE12/20/201312/20/201312/24/2013 PASS
DetailsScott Arellano
No comments.
Plan Modification Accepted  12/18/2013 DONE
started workflow
Telephone call  12/5/2013 DONE
DetailsAdele J Schaffeld-Griffin
returned Nicole's phone call. she sais she contacted her local building offical and got the answeres she needed for ADA so she said she did not have any questions for me. 12/5/13 ajs
Print Occupancy Form  11/19/2013 DONE
DetailsBarbara Stitt
Permit Ready to Issue  11/19/2013 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  11/19/2013 DONE
DetailsBarbara Stitt
Plan assigned to (AJS)9/30/20139/30/201310/17/2013 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Green Tag - ePlanReview - Zenergy Athletic Club
Routing - PLAN CHECK10/17/2013 10/17/2013 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  10/17/2013 DONE
Routing - PLAN CHECK9/30/2013 10/3/2013 FAIL
DetailsAdele J Schaffeld-Griffin
see change marks in e plan
Routing - PLUMBING9/30/2013 10/3/2013 PASS
DetailsBill VanDegrift
must have double wall with leak detection at potable to heating water.
1st review completed  10/3/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE9/30/20139/30/201310/1/2013 PASS
DetailsCraig D. Hanson
Routing PW Sewer Rating9/30/2013 10/1/2013 PASS
DetailsConnie Baumgartner
Routing - Addressing9/30/2013 10/1/2013 PASS
DetailsEmily Dixon
Suites being used are 210 & 220. Others shown are wrong. Jason Talyor ###-####
Routing - PUBLIC WORKS9/30/2013 9/30/2013 PASS
DetailsBeverly Mountain
Intake Approval  9/30/2013 PASS
DetailsJason Blais
Prescreen approved and plan review fees paid.
Pending Assignment by JCB9/30/2013 9/30/2013 DONE
DetailsJason Blais
Intake Approval  9/24/2013 FAIL
DetailsTim L. Woodard
Nicole,

Please see marked up checklist for additional requirements still needed.

Best regards,

Tim Woodard
Plans Examiner II / City of Boise
###-####
twoodard@cityofboise.org
Intake Approval  9/23/2013 FAIL
DetailsTim L. Woodard
Nicole,

Please upload plans into the drawings folder and have only small documents in the "Documents" folder. Also please scan and upload the #520 submittal checklist.

Best regards,
Tim Woodard
twoodard@cityofboise.org
Payment Received  9/20/2013 DONE
Payment received via Govolutions
Application received  9/20/2013 DONE
Application submitted via PDS Online on Sep 20 2013 9:46AM