BLD-Final | 12/10/2014 | 12/10/2014 | 12/10/2014 | P | PASS |
Dave Hannah
|
|
|
Final Building Inspection has been completed. Final sign off was pending until zoning approval. Zoning approved this am by Sarah Shafer. Phone #: ###-#### Inspection requested via web by Gary Beck
|
DOC - Permit Finaled | 12/10/2014 | 12/10/2014 | 12/10/2014 | P | PASS |
Dave Hannah
|
|
|
|
Zoning Approval | 12/10/2014 | 12/10/2014 | 12/10/2014 | | PASS |
Sarah Schafer
|
|
|
|
BLD-Final | 12/1/2014 | 12/1/2014 | 12/1/2014 | P | PEND |
Dave Hannah
|
|
|
For access, please call Gary 30-40 min prior to inspection. Thanks. Phone #: ###-#### Inspection requested via web by Gary Beck needs zoning final ok after that
|
BLD-Framing/Rough-in | 6/18/2014 | 6/18/2014 | 6/18/2014 | P | PASS |
Tom Arcoraci
|
|
|
Request is for framing inspection on the detached garage Phone #: ###-#### >> Inspection requested via web by Gary Beck garage ok for cover 408
|
BLD-Energy code compliance | 5/22/2014 | 5/23/2014 | 5/23/2014 | A | PASS |
Dave Hannah
|
|
|
>> Inspection requested via web by Gary Beck
|
BLD-Wall cover | 5/22/2014 | 5/23/2014 | 5/23/2014 | A | PASS |
Dave Hannah
|
|
|
>> Inspection requested via web by Gary Beck
|
BLD-Framing/Rough-in | 5/18/2014 | 5/19/2014 | 5/19/2014 | P | PART |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Gary Beck needs mec rough in needs windows removed and screens installed on back porch.
|
Plan Modification Accepted | | | 5/19/2014 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 5/19/2014 | | 5/19/2014 | | PASS |
Troy James
|
|
|
manual j report
|
BLD-Foundation | 4/23/2014 | 4/24/2014 | 4/24/2014 | A | PASS |
Dave Hannah
|
|
|
Jay Phone #: ###-####
|
BLD-Footing | 4/22/2014 | 4/22/2014 | 4/23/2014 | P | PASS |
Dave Hannah
|
|
|
Ben Phone #: ###-####
|
BLD-Foundation | 2/6/2014 | 2/6/2014 | 2/6/2014 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ben Sears
|
BLD-Footing | 2/4/2014 | 2/4/2014 | 2/5/2014 | P | PART |
Dave Hannah
|
|
|
Jay Phone #: ###-#### basement ftgs crew will tent and heat
|
Issue PAID IN FULL permit | | | 12/10/2013 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 11/13/2013 | | |
|
|
|
|
Telephone call | | | 11/13/2013 | | DONE |
Christina Prado
|
|
|
Gave Catherine fees due and advised GC form is required prior to issuance
|
Permit Ready to Issue | | | 11/13/2013 | | DONE |
Christina Prado
|
|
|
|
Routing Walk-In (BLD) | 11/12/2013 | 11/12/2013 | 11/12/2013 | P | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/12/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/12/2013 | | DONE |
|
|
|
|
Application received | | 9/24/2013 | 9/24/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing Walk-In (Zoning) | 9/24/2013 | 9/24/2013 | 9/24/2013 | P | PASS |
Sarah Schafer
|
|
|
Approved per DRH13-00066.
|
Routing Walk-In (BLD) | 9/24/2013 | 9/24/2013 | 9/24/2013 | P | FAIL |
Perry Paine
|
|
|
Need existing structure eng analysis, engineered foundation design and helicle pier design and proceedure for helical pier installation. pep 9-24-2013 3:34 p.m.
|
1st review completed | | | 9/24/2013 | | DONE |
|
|
|
|