Permit Information
Permit NumberBLD13-02610
StatusFinaled
Name RETAIL CONSTRUCTION SERVICES
Site Address 675 N MILWAUKEE ST
Project NameMattress Firm
Customer Number 
ePlanReviewYes
Description
(Mattress Firm) This permit is for the tenant improvement that are being made by the tenant. The scope of work included in the Major TI under BLD13-02226 is the scope of work the owner is permitting for this project. This permit is for the Interior finishes (paint, flooring), low voltage lighting control module, sales desk, electrical conduit in slab, platform. All interior finishe shall meet the requirment of chapter 8 IBC. This building is NOT fire sprinklered per the alternate attached to BLD13-02226. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 4/11/20144/2/2014 DONE
DetailsChristina Prado
completed 4-2-14
First Notice 3/9/20144/1/2014 DONE
Faxed 4-1-14
BLD-Final2/27/20142/27/20142/27/2014PPASS
DetailsMike Jordan
Layton Phone #: ###-####. Ok for perm occ.
FIRE-Final Inspection2/27/20142/27/20142/27/2014PPASS
DetailsTroy Cobbley
Life safety passed
Permanent Occupancy  2/27/2014 DONE
DetailsChristina Prado
BLD-Final2/25/20142/26/20142/26/2014PNR
DetailsMike Jordan
Layton Phone #: ###-####. Life/safety failed.
FIRE-Final Inspection2/25/20142/26/20142/26/2014AFAIL
DetailsTroy Cobbley
No city approved documents/plans on site.
Print Occupancy Form  2/10/2014 DONE
DetailsTisha Gallop
Issue PAID IN FULL permit  2/10/2014 DONE
DetailsTisha Gallop
OVERRIDE  2/7/2014  
Permit Ready to Issue  2/7/2014 DONE
DetailsTisha Gallop
Plan assigned to (AJS)10/1/201310/1/201312/26/2013 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Due 10/7 Level I
Routing - PLAN CHECK12/26/2013 12/26/2013 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  12/26/2013 DONE
Telephone call  11/22/2013 DONE
DetailsAdele J Schaffeld-Griffin
Called and left message for Rob on status of revisons
1st review completed  10/7/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK10/1/2013 10/6/2013 FAIL
DetailsAdele J Schaffeld-Griffin
see change marks in e plan
Routing - Erosion and Sediment10/1/2013 10/2/2013 PASS
DetailsEvan Jenkins
Intake Approval  10/1/2013 PASS
DetailsAdele J Schaffeld-Griffin
Intake Approval  9/30/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Please re upload the ESC permit. When you open the document it is not there. Thank you
Intake Approval  9/26/2013 FAIL
DetailsAdele J Schaffeld-Griffin
need esc permit and com check for new lighting
Intake Approval  9/25/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Please up load the completed 518 checklist. The per screen will be started after this is recieved.
Please up load the 304 design professional of record form.
Intake Approval  9/25/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Please up load the completed 518 checklist. The per screen will be started after this is recieved.
Intake Approval  9/25/2013 FAIL
DetailsAdele J Schaffeld-Griffin
need com check for lighting, esc permit for saw cutting, signed m sheets
See change marks on check list
Payment Received  9/24/2013 DONE
Payment received via Govolutions
Application received  9/24/2013 DONE
Application submitted via PDS Online on Sep 24 2013 2:41PM