Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD13-02645
StatusFinaled
Name TAHOE HOMES LLC
Site Address 2775 S HONEYCOMB WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
WUI Zone B, Class A Roof, Permit for the construction of a new 2595 sq. ft., two story (first story 993 sq. ft., second story 1602 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 140 sq. ft. of covered patio/porch and a 769 sq. ft. attached garage per the approved plans, Rescheck, plan review report and any notations. SP-01 zoning and setbacks per planning. JG
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/15/20151/16/20151/16/2015APASS
DetailsPhil Shearer
Clint Phone #: ###-####
DOC - Permit Finaled1/16/20151/16/20151/16/2015PPASS
DetailsPhil Shearer
BLD-Blower Door Test Results1/16/20151/16/20151/16/2015PPASS
DetailsPhil Shearer
3.5
BLD-Energy code compliance11/6/201411/10/201411/10/2014PPASS
DetailsPhil Shearer
Phone #: ###-#### Inspection requested via web by Clint Wall
BLD-Framing/Rough-in11/6/201411/7/201411/7/2014APASS
DetailsPhil Shearer
Phone #: ###-#### Inspection requested via web by Clint Wall
BLD-Wall Bracing10/15/201410/16/201410/16/2014APASS
DetailsPhil Shearer
Rudy Phone #: ###-####
BLD-Foundation8/1/20148/1/20148/1/2014PPASS
DetailsPhil Shearer
Pouring at 2 - Wes Phone #: ###-#### or Juan ###-####
BLD-Footing7/31/20147/31/20147/31/2014PPASS
DetailsPhil Shearer
Wes-pour time 2:00 Phone #: ###-####
Issue PAID IN FULL permit  7/23/2014 DONE
DetailsChristina Prado
Extend Review Timeline  3/18/2014 DONE
DetailsChristina Prado
180 day extension 3/18/14
Expiration Notice3/5/20143/26/20143/5/2014 DONE
DetailsChristina Prado
OVERRIDE  10/7/2013  
Application received 9/26/201310/7/2013 DONE
Telephone call  10/7/2013 DONE
DetailsTisha Gallop
called Tahoe Homes and left vm permit is ready and fee due.
Permit Ready to Issue  10/7/2013 DONE
DetailsTisha Gallop
Plan assigned to (JG) 9/26/201310/4/2013 PASS
DetailsJavier Guzman
Due 10/9 L1-
Routing - PLAN CHECK10/3/2013 10/4/2013 PASS
DetailsJavier Guzman
1st review completed  10/4/2013 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  10/4/2013 DONE
Case Summary (BLD)  10/4/2013 DONE
DetailsJavier Guzman
Inspection Record Card- Bld  10/4/2013 DONE
Routing - MECHANICAL  10/3/2013 PASS
DetailsTroy James
Routing - PLANNING9/30/2013 9/30/2013 PASS
DetailsLeon Letson
Routing - PUBLIC WORKS9/27/2013 9/30/2013 PASS
DetailsConnie Baumgartner
Route to Impact Fee Review9/26/201310/1/20139/27/2013 PASS
DetailsCindy M. Gould
Route to Impact Fee Review9/26/20139/29/20139/27/2013 PASS
DetailsCindy M. Gould
Routing - Addressing9/26/2013 9/27/2013 PASS
DetailsJason C. Taylor
Plans ACCEPTED BY PLAN TECH  9/26/2013 DONE
DetailsChristina Prado
Intake Approval  9/26/2013 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  9/26/2013 DONE
DetailsChristina Prado