BLD-Final | 4/22/2014 | 4/23/2014 | 4/23/2014 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by Austin Wagner
|
DOC - Permit Finaled | 4/23/2014 | 4/23/2014 | 4/23/2014 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 2/14/2014 | 2/18/2014 | 2/18/2014 | A | PASS |
Mike Jordan
|
|
|
Austin Phone #: ###-####. Framing issues resolved.
|
BLD-Framing/Rough-in | 2/13/2014 | 2/13/2014 | 2/14/2014 | P | PART |
Dave Hannah
|
|
|
austin Phone #: ###-#### ok to insulate c/n on site
|
BLD-Wall Bracing | 2/4/2014 | 2/5/2014 | 2/5/2014 | A | PASS |
Dave Hannah
|
|
|
austin Phone #: ###-####
|
BLD-Wall Bracing | 2/3/2014 | 2/4/2014 | 2/4/2014 | A | FAIL |
Mike Jordan
|
|
|
austin Phone #: ###-####. 1st floor exterior wall bracing ok, except for missing holdowns at east wall, front entry. Also missing blocking and several areas at 2nd floor floor not attached. Also told framer not to install exterior weaTHER MEMBRANE until wall bracing inspection has been completed.
|
BLD-Foundation | 1/9/2014 | 1/10/2014 | 1/10/2014 | A | PASS |
Dave Hannah
|
|
|
Heron Phone #: ###-####
|
BLD-Footing | 1/7/2014 | 1/8/2014 | 1/8/2014 | A | PASS |
Jim Storey
|
|
|
Heron Phone #: ###-####
|
BLD-Footing | 1/6/2014 | 1/7/2014 | 1/7/2014 | P | NR |
Jim Sly
|
|
|
heron Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 12/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 12/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 12/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (JG) | 12/17/2013 | 12/17/2013 | 12/19/2013 | | PASS |
Javier Guzman
|
|
|
1st review completed, pending Mech, ePlan mod
|
Routing - MECHANICAL | 12/18/2013 | | 12/19/2013 | | PASS |
Troy James
|
|
|
Plan Mod
|
1st review completed | | | 12/19/2013 | | DONE |
|
|
|
Plan Mod
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/19/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/18/2013 | | 12/18/2013 | | PASS |
Javier Guzman
|
|
|
Pending Mech, Plan Mod
|
Plan Modification Accepted | | | 12/17/2013 | | |
|
|
|
started workflow
|
Routing - PLANNING | 12/17/2013 | | 12/17/2013 | | PASS |
Leon Letson
|
|
|
|
OVERRIDE | | | 10/28/2013 | | |
|
|
|
|
Plan assigned to (JG) | 10/16/2013 | 10/16/2013 | 10/28/2013 | | PASS |
Javier Guzman
|
|
|
1st review completed, Due 10/29 L1 ePlan
|
Inspection Record Card- Bld | | | 10/28/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 10/28/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 10/25/2013 | | 10/28/2013 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/28/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 10/16/2013 | | 10/25/2013 | | FAIL |
Javier Guzman
|
|
|
PRJ DOX CASE
|
1st review completed | | | 10/25/2013 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLANNING | 10/16/2013 | | 10/24/2013 | | PASS |
Leon Letson
|
|
|
|
Route to Impact Fee Review | 10/16/2013 | 10/21/2013 | 10/18/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 10/16/2013 | 10/19/2013 | 10/18/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 10/16/2013 | | 10/18/2013 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 10/16/2013 | | 10/17/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Payment Received | | | 10/16/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Routing - Addressing | 10/16/2013 | | 10/16/2013 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 9/27/2013 | | PASS |
|
|
|
|
Intake Approval | | | 9/27/2013 | | FAIL |
|
|
|
Need building cross section , Stair section detail (other is que what is this sheet TS 1-12 Denali)
|
Application received | | | 9/26/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 26 2013 3:52PM
|