Letter of compliance/Occupancy | | | 7/18/2014 | | DONE |
Barbara Stitt
|
|
|
|
DOC - L/C Approved | | | 7/18/2014 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 7/10/2014 | 7/11/2014 | 7/11/2014 | A | PASS |
Dave Hannah
|
|
|
Daryl Phone #: ###-####
|
FIRE-Final Inspection | 7/7/2014 | 7/8/2014 | 7/8/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety completed satisfactory. Inspection passed.
|
FIRE-Conference | 7/7/2014 | 7/7/2014 | 7/7/2014 | P | DONE |
Forrest France
|
|
|
Regarding project finals.
|
BLD-Final | 3/18/2014 | 3/19/2014 | 3/20/2014 | A | PEND |
Dave Hannah
|
|
|
for temp // daryl Phone #: ###-#### ok for temp occ ok for perm occ after fire gos perm
|
FIRE-Final Inspection | 3/17/2014 | 3/18/2014 | 3/18/2014 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is approved until the issues with the project related fire alarm permit have been resolved.
|
BLD-Ceiling Grid Inspection | 2/21/2014 | 2/24/2014 | 2/24/2014 | A | PASS |
Dave Hannah
|
|
|
Daryl Phone #: ###-####
|
BLD-Framing/Rough-in | 1/27/2014 | 1/27/2014 | 1/27/2014 | P | PASS |
Dave Hannah
|
|
|
daryl - before 3 if possible Phone #: ###-####
|
BLD-Conference | 1/3/2014 | 1/6/2014 | 1/7/2014 | A | PART |
Dave Hannah
|
|
|
daryl - walk through prior to the final Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 12/2/2013 | | DONE |
Christina Prado
|
|
|
|
Fees Due Hold | 11/13/2013 | | 12/2/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Framing/Rough-in | 11/15/2013 | 11/18/2013 | 11/18/2013 | A | PART |
Dave Hannah
|
|
|
daryl Phone #: ###-#### ok to cover walls phase one of two
|
Issue & PRINT to be Invoiced | | | 11/12/2013 | | DONE |
|
|
|
Curtis is mailing in the payment
|
Inspection Record Card- Bld | | | 11/12/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 10/2/2013 | 10/2/2013 | 10/14/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Due 10/15 Level 2 E plan
|
Routing - PLAN CHECK | 10/3/2013 | | 10/14/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 10/14/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/14/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/14/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 10/2/2013 | 10/2/2013 | 10/3/2013 | | PASS |
Scott Arellano
|
|
|
|
Routing PW Sewer Rating | 10/2/2013 | | 10/2/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 10/2/2013 | | 10/2/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/2/2013 | | 10/2/2013 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 10/2/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 10/1/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 1 2013 8:31AM
|
Intake Approval | | | 10/1/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1. Please provide the required stamping areas on the sheets that do not meet the requirment.
Cover sheet 4"x4" space 3" from right sheet edge
Additional sheet 4"x2" space located 3" from right of sheet edge
2. Please have the contractor sign the contractor decloration. This can be done prior to final.
|