Permanent Occupancy | | | 12/13/2013 | | DONE |
|
|
|
|
BLD-Final | 12/12/2013 | 12/12/2013 | 12/12/2013 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 12/12/2013 | 12/12/2013 | 12/12/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Jim is going to address the door/common use restroom issue.
|
BLD-Final | 12/11/2013 | 12/12/2013 | 12/12/2013 | A | DEFR |
Jim Storey
|
|
|
|
BLD-Final | 12/11/2013 | 12/11/2013 | 12/11/2013 | P | DEFR |
Jim Storey
|
|
|
hvac fail
|
BLD-Final | 12/10/2013 | 12/11/2013 | 12/11/2013 | A | DEFR |
Jim Storey
|
|
|
Jim, I will be there at 8:30 tomorrow am, hope to see you as early as possible, if not til later give me a call 30 minutes out thanks Phone #: ###-#### >> Inspection requested via web by rodger smith
|
BLD-Final | 12/9/2013 | 12/9/2013 | 12/9/2013 | P | NR |
Jim Storey
|
|
|
final plumbing being done this am Phone #: ###-#### >> Inspection requested via web by rodger smith
|
BLD-Framing/Rough-in | 11/19/2013 | 11/19/2013 | 11/19/2013 | P | PART |
Jim Storey
|
|
|
call half hour ahead so I can meet you there Phone #: ###-#### >> Inspection requested via web by rodger smith bathrm ok
|
Issue PAID IN FULL permit | | | 10/10/2013 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 10/9/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/9/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/9/2013 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 10/9/2013 | | DONE |
Barbara Stitt
|
|
|
Left a voice message for Robin Gates that permit is ready and need GC info on 10-9-13 @ 8:45am//BAS
|
Routing - PLAN CHECK | 10/7/2013 | | 10/8/2013 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 10/8/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 10/8/2013 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 10/1/2013 | | 10/8/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 10/1/2013 | | 10/8/2013 | | PASS |
Connie Baumgartner
|
|
|
Approved on Routing Slip. TLW
|
Routing - PLAN CHECK | | | 10/8/2013 | | PASS |
Tim L. Woodard
|
|
|
Tim Woodard
|
Routing - PLUMBING | 10/4/2013 | | 10/7/2013 | | PASS |
Daryl Spivey
|
|
|
per plans and ISPC
|
Routing - PLANNING | 10/3/2013 | | 10/4/2013 | | PASS |
Josh Wilson
|
|
|
Ok per CZC13-000208
|
Routing PW Environmental | 10/2/2013 | | 10/3/2013 | | PASS |
Walt Baumgartner
|
|
|
Per applicant, 2 grease traps existing on site from previous tenant, OK
|
Routing PW Sewer Rating | 10/1/2013 | | 10/2/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 10/1/2013 | 10/1/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/1/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 10/1/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/1/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Addressing | 10/1/2013 | | 10/1/2013 | | PASS |
Jason C. Taylor
|
|
|
|