BLD-Final | 8/29/2014 | 9/2/2014 | 9/2/2014 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 9/2/2014 | 9/2/2014 | 9/2/2014 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Blower Door Test Results | 9/2/2014 | 9/2/2014 | 9/2/2014 | A | PASS |
Phil Shearer
|
|
|
3.4
|
PubWorks Occupancy Approval | 8/29/2014 | 8/29/2014 | 8/29/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 5/23/2014 | 5/23/2014 | 5/27/2014 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 5/20/2014 | 5/22/2014 | 5/22/2014 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall c/n fire blk and air seal.
|
BLD-Final | 5/15/2014 | 5/15/2014 | 5/16/2014 | P | PART |
Jim Sly
|
|
|
Clint-fire soffit Phone #: ###-#### Fire Soffit.....OK
|
Plan Modification Accepted | | | 5/7/2014 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 5/7/2014 | | 5/7/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 4/23/2014 | 4/24/2014 | 4/24/2014 | A | PASS |
Jim Storey
|
|
|
Rudy Phone #: ###-####
|
BLD-Foundation | 3/28/2014 | 3/28/2014 | 3/29/2014 | P | PASS |
Dave Hannah
|
|
|
wes
|
BLD-Footing | 3/24/2014 | 3/25/2014 | 3/25/2014 | P | PASS |
Jim Sly
|
|
|
pour at 2:30 Phone #: ###-####
|
PubWorks Subgrade Approval | 3/24/2014 | 3/24/2014 | 3/24/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 10/21/2013 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/21/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 10/21/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/21/2013 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 10/21/2013 | | DONE |
Christina Prado
|
|
|
called Tahoe to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 10/21/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (PEP) | 10/17/2013 | 10/17/2013 | 10/18/2013 | | PASS |
Perry Paine
|
|
|
|
1st review completed | | | 10/18/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/10/2013 | | 10/18/2013 | | PASS |
Perry Paine
|
|
|
|
Plan assigned to (JG) | 10/1/2013 | 10/1/2013 | 10/17/2013 | | DEFR |
Javier Guzman
|
|
|
Due 10/18 L2-
|
Routing - PLAN CHECK | | | 10/17/2013 | | PASS |
Perry Paine
|
|
|
|
Routing - Erosion and Sediment | 10/8/2013 | | 10/10/2013 | | PASS |
Evan Jenkins
|
|
|
|
Routing - FIRE | 10/10/2013 | | 10/10/2013 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - MECHANICAL | 10/2/2013 | | 10/8/2013 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/2/2013 | 10/5/2013 | 10/3/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 10/1/2013 | 10/4/2013 | 10/3/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 10/3/2013 | | 10/3/2013 | | PASS |
Joshua Johnson
|
|
|
|
Routing - PUBLIC WORKS | 10/2/2013 | | 10/3/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 10/1/2013 | 10/2/2013 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 10/2/2013 | | 10/2/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - Addressing | 10/2/2013 | | 10/2/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/1/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/1/2013 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 10/1/2013 | | PASS |
Tisha Gallop
|
|
|
|