BLD-Final | 2/11/2015 | 2/13/2015 | 2/13/2015 | A | PASS |
Phil Shearer
|
|
|
Clint Phone #: ###-####
|
BLD-Blower Door Test Results | 2/13/2015 | 2/13/2015 | 2/13/2015 | P | PASS |
Phil Shearer
|
|
|
4.6
|
DOC - Permit Finaled | 2/13/2015 | 2/13/2015 | 2/13/2015 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 2/10/2015 | 2/11/2015 | 2/11/2015 | A | NR |
Phil Shearer
|
|
|
Clint Phone #: ###-####
|
BLD-Energy code compliance | 11/14/2014 | 11/17/2014 | 11/17/2014 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 11/11/2014 | 11/13/2014 | 11/13/2014 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 10/24/2014 | 10/24/2014 | 10/24/2014 | P | PASS |
Jim Storey
|
|
|
Joey Phone #: ###-####
|
Plan Reviewer's activity | | | 2/14/2014 | | DONE |
Jason Blais
|
|
|
Materials Testing & Inspection (MTI) has provided an engineered report on adequacy for the compressive strength of the foundation. Test methods included a combination of collecting core specimens and use of the rebound hammer method for actual and correlated strength results. Report also noted a visible inspection of the foundation indicating no visible evidence of freezing bleedwater and the opinion the foundation possesses adequate strength and hardness for the intended use. The MTI report is attached to this case.
|
BLD-Foundation | 12/4/2013 | 12/5/2013 | 12/5/2013 | P | FAIL |
Dave Hannah
|
|
|
antone - around 2 if possible please Phone #: ###-#### outside air temps are 23deg forms rebar ect same temp footing was not protected to aci 306 standerds and will need to be tested.avg temps are below 20deg crew is not using any type of heat insulated blankets only .ground temps are below 32deg talked with wes and jake I will not ok this as is they are pouring at thier own risk.
|
BLD-Footing | 12/3/2013 | 12/3/2013 | 12/4/2013 | P | PART |
Dave Hannah
|
|
|
anton - after 3 please Phone #: ###-####
|
BLD-Foundation | 12/4/2013 | 12/4/2013 | 12/4/2013 | P | CANC |
Dave Hannah
|
|
|
Around 4 if possible please-Anton Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/21/2013 | | |
|
|
|
|
OVERRIDE | | | 10/11/2013 | | |
|
|
|
|
Telephone call | | | 10/11/2013 | | DONE |
Tisha Gallop
|
|
|
called Tahoe Homes and left vm permit is ready and fee.
|
Inspection Record Card- Bld | | | 10/11/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 10/11/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (JG) | 10/2/2013 | 10/2/2013 | 10/10/2013 | | PASS |
Javier Guzman
|
|
|
Due 10/15 L1-
|
Routing - PLAN CHECK | 10/9/2013 | | 10/10/2013 | | PASS |
Javier Guzman
|
|
|
Javier
|
1st review completed | | | 10/10/2013 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 10/10/2013 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2013 | | DONE |
|
|
|
|
Routing - MECHANICAL | | | 10/9/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 10/7/2013 | | 10/7/2013 | | PASS |
Leon Letson
|
|
|
|
Routing - PUBLIC WORKS | 10/3/2013 | | 10/7/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Route to Impact Fee Review | 10/2/2013 | 10/7/2013 | 10/3/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 10/2/2013 | 10/5/2013 | 10/3/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 10/2/2013 | | 10/3/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Application received | | 10/2/2013 | 10/2/2013 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/2/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 10/2/2013 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/2/2013 | | DONE |
Christina Prado
|
|
|
|