BLD-Final | 5/18/2015 | 5/19/2015 | 5/19/2015 | P | PASS |
Phil Shearer
|
|
|
Clint Phone #: ###-####
|
DOC - Permit Finaled | 5/19/2015 | 5/19/2015 | 5/19/2015 | P | PASS |
Phil Shearer
|
|
|
|
PubWorks Occupancy Approval | 5/13/2015 | 5/13/2015 | 5/13/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 3/25/2015 | 3/27/2015 | 3/27/2015 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Other | 3/20/2015 | 3/23/2015 | 3/23/2015 | A | PASS |
Phil Shearer
|
|
|
Clint-offit Phone #: ###-####
|
BLD-Wall Bracing | 3/4/2015 | 3/5/2015 | 3/5/2015 | A | PASS |
Phil Shearer
|
|
|
Shear // Rudy Phone #: ###-####
|
BLD-Foundation | 12/17/2014 | 12/17/2014 | 12/17/2014 | P | PASS |
Phil Shearer
|
|
|
Juan ###-#### pour time 1:00 Phone #: ###-#### Inspection requested via web by tony L
|
BLD-Footing | 12/15/2014 | 12/15/2014 | 12/15/2014 | P | PASS |
Phil Shearer
|
|
|
3:30 pour time - Juan Phone #: ###-####
|
PubWorks Subgrade Approval | 12/15/2014 | 12/15/2014 | 12/15/2014 | | DONE |
Jason C. Taylor
|
|
|
* INTERIOR FOOTINGS ONLY - NO EXTERIOR COLUMNS**A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 12/12/2014 | 12/12/2014 | 12/12/2014 | P | CANC |
Phil Shearer
|
|
|
pour time 4:00 Phone #: ###-#### Inspection requested via web by tony L
|
Issue PAID IN FULL permit | | | 10/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Extend Review Timeline | | | 9/12/2014 | | DONE |
Christina Prado
|
|
|
final extension approved
|
Expiration Notice | 9/8/2014 | 9/29/2014 | 9/8/2014 | | DONE |
Christina Prado
|
|
|
|
Extend Review Timeline | | | 3/18/2014 | | DONE |
Christina Prado
|
|
|
180 day extension 3/18/14
|
Expiration Notice | 3/10/2014 | 3/31/2014 | 3/10/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 10/16/2013 | | |
|
|
|
|
Telephone call | | | 10/16/2013 | | |
|
|
|
10-16-13 called Tahoe Homes permit ready and fee given ///dld
|
Plan assigned to (JG) | 10/2/2013 | 10/2/2013 | 10/15/2013 | | PASS |
Javier Guzman
|
|
|
Due 10/21 L2-
|
Routing - PLAN CHECK | 10/10/2013 | | 10/15/2013 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 10/15/2013 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 10/15/2013 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Erosion and Sediment | 10/9/2013 | | 10/10/2013 | | PASS |
Evan Jenkins
|
|
|
Waiver Approved
|
Routing - FIRE | 10/10/2013 | | 10/10/2013 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - MECHANICAL | | | 10/9/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 10/7/2013 | | 10/7/2013 | | PASS |
Leon Letson
|
|
|
|
Routing - PUBLIC WORKS | 10/3/2013 | | 10/7/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Route to Impact Fee Review | 10/2/2013 | 10/7/2013 | 10/3/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 10/2/2013 | 10/5/2013 | 10/3/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 10/2/2013 | | 10/3/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing PW Grading-Hillside | 10/2/2013 | | 10/3/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Application received | | 10/2/2013 | 10/2/2013 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/2/2013 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 10/2/2013 | | PASS |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/2/2013 | | DONE |
Tisha Gallop
|
|
|
|