Second Notice | | 3/13/2014 | 3/20/2014 | | DONE |
|
|
|
|
First Notice | | 2/3/2014 | 3/3/2014 | | DONE |
Christina Prado
|
|
|
mailed 3-4-14
|
Permanent Occupancy | | | 1/24/2014 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 1/9/2014 | 1/10/2014 | 1/13/2014 | P | PASS |
Jim Storey
|
|
|
jason Phone #: ###-#### PLEASE CALL BEFORE GOING OUT
|
FIRE-Final Inspection | 1/9/2014 | 1/10/2014 | 1/10/2014 | A | PASS |
Forrest France
|
|
|
Noted correction items are finished. Fire life safety finaled.
|
FIRE-Final Inspection | 12/23/2013 | 12/23/2013 | 12/27/2013 | P | PART |
Forrest France
|
|
|
Final pending repairs for the existing fire alarm system.
|
BLD-Final | 12/5/2013 | 12/6/2013 | 12/6/2013 | A | PART |
Jim Storey
|
|
|
andy Phone #: ###-#### handrail ends/ada signage/ mirrior height/temp ok
|
FIRE-Final Inspection | 12/4/2013 | 12/4/2013 | 12/5/2013 | P | PART |
Forrest France
|
|
|
Items noted include; repair EM light at the north hall, reverse door hardware at one location, existing non-required fire alarm system must remain operational or be removed as discussed.
|
Zoning Approval | 12/3/2013 | 12/3/2013 | 12/3/2013 | | PASS |
Josh Wilson
|
|
|
|
BLD-Framing/Rough-in | 11/15/2013 | 11/15/2013 | 11/15/2013 | P | PASS |
Tom Arcoraci
|
|
|
andy PLEASE CALL FOR ACCESS Phone #: ###-####
|
Permit Ready to Issue | | | 11/14/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 11/14/2013 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 11/14/2013 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 10/7/2013 | | 11/12/2013 | | PASS |
Tim L. Woodard
|
|
|
ePlanReview - Level 3 TI - River's Edge Church
|
Routing - FIRE | 11/7/2013 | | 11/8/2013 | | PASS |
Craig D. Hanson
|
|
|
Refer to Fire report revision 1
|
Routing - PLAN CHECK | 11/7/2013 | | 11/7/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 10/7/2013 | 10/7/2013 | 10/28/2013 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Review Report
|
1st review completed | | | 10/24/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 10/7/2013 | | 10/24/2013 | | FAIL |
Tim L. Woodard
|
|
|
Refer to change marks on the drawings. TLW
|
Routing - PLANNING | 10/7/2013 | | 10/24/2013 | | PASS |
Sue Cummings
|
|
|
Sue Cummings - CUP13-00027 Approved in E-plan by Sue. TLW
|
Routing - Addressing | 10/7/2013 | | 10/7/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/7/2013 | | 10/7/2013 | | PASS |
Beverly Mountain
|
|
|
|
Plan Reviewer's activity | | | 10/7/2013 | | DONE |
Jason Blais
|
|
|
Emailed architect to have her contact ACHD for evaluation of any impact fees. Written verification from ACHD is required to be provided to our Permit Counter prior to the building permit being issued.
|
Routing PW Sewer Rating | 10/7/2013 | | 10/7/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 10/7/2013 | | PASS |
Jason Blais
|
|
|
Prescreen passed by Tim Woodard on 10/4/13. Plan Review Fees paid on 10/7/13.
|
Pending Assignment by JCB | 10/7/2013 | | 10/7/2013 | | DONE |
Jason Blais
|
|
|
|
Payment Received | | | 10/5/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/2/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 2 2013 3:18PM
|