Second Notice | | 2/7/2014 | 2/10/2014 | | DONE |
|
|
|
This permit finaled on the web by Tony O'Neil
|
First Notice | 12/30/2013 | 12/30/2013 | 1/28/2014 | | DONE |
Jim Sly
|
|
|
|
BLD-Final | 12/30/2013 | 12/30/2013 | 12/30/2013 | P | PASS |
Jim Sly
|
|
|
I have been told that all other inspections have been passed. Thanks Phone #: ###-#### >> Inspection requested via web by Scott Stimpson
|
DOC - Permit Finaled | 12/30/2013 | 12/30/2013 | 12/30/2013 | P | PASS |
Jim Sly
|
|
|
|
BLD-Conference | 12/30/2013 | 12/30/2013 | 12/30/2013 | P | CANC |
Jim Sly
|
|
|
I have been told that all inspections have been completed finally. Just need Building now. Let me know if this is right.
Thanks Phone #: ###-#### >> Inspection requested via web by Scott Stimpson Inspection cancelled from web by: Scott Stimpson
|
FIRE-Final Inspection | 11/17/2013 | 11/18/2013 | 11/18/2013 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 11/17/2013 | 11/18/2013 | 11/18/2013 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Stimpson Need Fire and Mech (Hood) final inspections.
|
BLD-Final | 11/15/2013 | 11/15/2013 | 11/15/2013 | P | CANC |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Stimpson Inspection cancelled from web by: Scott Stimpson
|
FIRE-Final Inspection | 11/15/2013 | 11/15/2013 | 11/15/2013 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Stimpson Inspection cancelled from web by: Scott Stimpson
|
Issue PAID IN FULL permit | | | 10/28/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/28/2013 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/28/2013 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 10/21/2013 | | DONE |
Darla L Downs
|
|
|
|
Routing - PLAN CHECK | 10/18/2013 | | 10/21/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/21/2013 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 10/3/2013 | 10/3/2013 | 10/11/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 10/3/2013 | | 10/11/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - C.D.H | 10/3/2013 | | 10/11/2013 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 10/11/2013 | | DONE |
|
|
|
Pending CDHC
|
Routing - MECHANICAL | 10/3/2013 | | 10/10/2013 | | PASS |
Troy James
|
|
|
Approval pending make-up air design does not create a discomfort to the employee. See letter from mechanical engineer.
|
Routing PW Sewer Rating | 10/7/2013 | | 10/8/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 10/7/2013 | | 10/8/2013 | | PASS |
Walt Baumgartner
|
|
|
Facility has existing in ground 1000 gal grease interceptor
|
Routing - PUBLIC WORKS | 10/7/2013 | | 10/7/2013 | | PASS |
Beverly Mountain
|
|
|
|
Payment Received | | | 10/3/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 10/3/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 3 2013 10:51AM
|
Intake Approval | | | 10/3/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|