BLD-Final | 2/13/2015 | 2/17/2015 | 2/17/2015 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper
|
DOC - Permit Finaled | 2/17/2015 | 2/17/2015 | 2/17/2015 | P | PASS |
Tony Young
|
|
|
c of o issued
|
PubWorks Occupancy Approval | 2/17/2015 | 2/17/2015 | 2/17/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 5/30/2014 | 6/2/2014 | 6/2/2014 | P | PASS |
Tony Young
|
|
|
plans in trash bag at fireplce Phone #: ###-#### >> Inspection requested via web by David Wipper
|
BLD-Framing/Rough-in | 5/29/2014 | 5/29/2014 | 5/29/2014 | P | PASS |
Tony Young
|
|
|
plans in trash bag at fireplace Phone #: ###-#### >> Inspection requested via web by David Wipper
|
BLD-Wall cover | 5/27/2014 | 5/28/2014 | 5/28/2014 | A | PASS |
Tony Young
|
|
|
fire rated drywall soffit request to cover. Plans are in trash bag at fireplace. Phone #: ###-#### >> Inspection requested via web by David Wipper
|
BLD-Wall Bracing | 5/15/2014 | 5/16/2014 | 5/16/2014 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by David Wipper,, ext shear ok to cover
|
BLD-Foundation | 4/22/2014 | 4/23/2014 | 4/23/2014 | P | PART |
Tony Young
|
|
|
Adam-Pour at 4 Phone #: ###-####,, work in progress
|
BLD-Footing | 4/22/2014 | 4/22/2014 | 4/22/2014 | P | PART |
Tony Young
|
|
|
Adam-Pour at 4 Phone #: ###-####,, work in progress,, ok
|
PubWorks Subgrade Approval | 4/18/2014 | 4/18/2014 | 4/18/2014 | | DONE |
Jason C. Taylor
|
|
|
*FOOTINGS ONLY _ NO COLUMNS*A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 4/15/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 4/15/2014 | | DONE |
Christina Prado
|
|
|
|
Extend Review Timeline | | | 3/27/2014 | | DONE |
Christina Prado
|
|
|
180day extension granted 3/25/14
|
Expiration Notice | 3/17/2014 | 4/7/2014 | 3/17/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 11/26/2013 | | |
|
|
|
|
Permit Ready to Issue | | | 11/26/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 10/14/2013 | 10/14/2013 | 11/15/2013 | | PASS |
Carl D Madsen
|
|
|
eplan First review completed
|
Routing - PLAN CHECK | 11/15/2013 | | 11/15/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Grading-Hillside | 11/15/2013 | | 11/15/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/15/2013 | | DONE |
|
|
|
|
Routing - FIRE | 10/14/2013 | 10/14/2013 | 11/1/2013 | | PASS |
Scott Arellano
|
|
|
No comments.
|
1st review completed | | | 10/23/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/14/2013 | | 10/23/2013 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 10/14/2013 | | 10/17/2013 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 10/14/2013 | | 10/16/2013 | | PASS |
Evan Jenkins
|
|
|
ESC Inspections to be performed within 24hrs of a Rain Event of a .25"
|
Routing PW Grading-Hillside | 10/14/2013 | | 10/16/2013 | | FAIL |
Jason C. Taylor
|
|
|
Grading plan needs to be signed and srtamped by a licenced professional engineer. Jason Taylor ###-####.
|
Route to Impact Fee Review | 10/14/2013 | 10/17/2013 | 10/15/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 10/14/2013 | | 10/15/2013 | | PASS |
Joshua Johnson
|
|
|
|
Routing - Addressing | 10/14/2013 | | 10/15/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/14/2013 | | 10/15/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Payment Received | | | 10/14/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 10/14/2013 | | PASS |
Christina Prado
|
|
|
|
Intake Approval | | | 10/10/2013 | | FAIL |
|
|
|
Needs to turn the drawings to landscape
|
Application received | | | 10/7/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 7 2013 10:52AM
|