Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD13-02770
StatusFinaled
Name ST LUKES REG MED CNTR
Site Address 190 E BANNOCK ST
Project NameSLRMC - 2ND FLOOR
Customer Number 
ePlanReviewYes
Description
(SAINT LUKES REGIONAL MEDICAL CENTER - 2ND FLOOR - CENTRAL TOWER) The fire sprinkler system is used for high-rise and for occupancy. To remodel an existing 7,430 square foot patient sleeping suite located on the 2nd story of an existing hospital. Work is to include upgrading an existing patient sleeping room to comply as an “Accessible Unit” for the disabled, upgrading an existing patient sleeping room for bariatric patients, constructing new interior walls, and installing new finishes. An existing patient sleeping room will be converted to an employee break room, an existing patient sleeping room will be converted to an office, and an existing patient sleeping room will be converted to a clean supply room. The existing corridor enclosure is not being altered. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 9/7/20149/5/2014 DONE
This permit finaled on the web by Curtis Weedop
Third Notice 7/14/20149/2/2014 DONE
e-mailed Curtis and Virna
Third Notice 6/14/20147/9/2014 DONE
e-mailed to Curtis
Third Notice 5/10/20146/9/2014 DONE
e-mailed to Curtis Weedop
Second Notice 4/10/20145/5/2014 DONE
e-mailed to Curtis Weedop
First Notice 3/30/20143/31/2014 DONE
Permanent Occupancy  3/20/2014 DONE
DetailsBarbara Stitt
BLD-Final3/10/20143/10/20143/10/2014PPASS
DetailsTom Arcoraci
if no answer please call ###-#### Phone #: ###-#### >> Inspection requested via web by Rock Self
FIRE-Final Inspection3/10/20143/10/20143/10/2014PPASS
DetailsTroy Cobbley
life safety passed
BLD-Final2/28/20143/4/20143/4/2014ACANC
DetailsDave Hannah
if no answer please try my desk phone ###-#### Thanks Phone #: ###-#### >> Inspection requested via web by Rock Self Inspection cancelled from web by: Rock Self
FIRE-Final Inspection2/28/20143/3/20143/3/2014AFAIL
DetailsForrest France
Missing exit signs per plan review annotations at three locations, missing occupant notification at the break room and office areas, project related fire alarm permit final pending.
BLD-Ceiling Grid Inspection12/26/201312/27/201312/27/2013APASS
DetailsDave Hannah
if no answer on my cell phone please call my desk phone ###-#### Thanks Phone #: ###-#### >> Inspection requested via web by Rock Self
BLD-Wall cover12/11/201312/11/201312/11/2013APASS
DetailsDave Hannah
if no answer try my desk phone ###-#### Phone #: ###-#### >> Inspection requested via web by Rock Self
Plan assigned to (CJW)10/9/201310/9/201311/21/2013 PASS
DetailsCarl Westfall
ST. LUKE'S HOSPITAL - 2ND STORY - TOWER ePlanReview - Level 3 TI (20 days - Nov 4)
Routing - PLAN CHECK11/20/2013 11/21/2013 PASS
DetailsCarl Westfall
Architect Emailed a revised sheet. Uploaded the revised drawing into ePlanReview. Drawings approved.
PLANS/APPL TAKEN TO FRONT DESK  11/21/2013 DONE
Permit Ready to Issue  11/21/2013 DONE
DetailsTisha Gallop
Issue PAID IN FULL permit  11/21/2013 DONE
DetailsChristina Prado
Print Occupancy Form  11/21/2013 DONE
DetailsChristina Prado
Print Occupancy Form  11/21/2013 DONE
DetailsTisha Gallop
Routing - FIRE11/20/201311/20/201311/20/2013 PASS
DetailsCraig D. Hanson
See report revision 1
Routing - PLAN CHECK11/19/2013 11/20/2013 FAIL
DetailsCarl Westfall
Revisions made to the drawings by the Architect made the accessible shower no longer accessible to the disabled. Correction was required.
Plan resubmittals received  11/19/2013 DONE
1st review completed  11/8/2013 DONE
Plan resubmittals requested  11/8/2013 DONE
Routing - FIRE10/9/201310/9/201311/7/2013 FAIL
DetailsCraig D. Hanson
Refer to report
Routing - PLAN CHECK10/9/2013 11/6/2013 FAIL
DetailsCarl Westfall
Revised drawings required.
Routing - PLUMBING10/9/2013 10/16/2013 PASS
DetailsBill VanDegrift
Routing - Addressing10/9/2013 10/11/2013 PASS
DetailsEmily Dixon
Routing PW Sewer Rating10/9/2013 10/11/2013 PASS
DetailsConnie Baumgartner
Routing - PUBLIC WORKS10/9/2013 10/9/2013 PASS
DetailsBeverly Mountain
Intake Approval  10/9/2013 PASS
DetailsJason Blais
Prescreen approved by Adele Schaffeld-Griffin and Plan Review Fees paid.
Pending Assignment by JCB10/9/2013 10/9/2013 DONE
DetailsJason Blais
Payment Received  10/8/2013 DONE
Payment received via Govolutions
Intake Approval  10/8/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Please upload the completed check list
Please upload the 304 design professional form
All plan sheet must be signed by a design professional of record. The finish plans need to be stamped and signed.

Once the pre screen is accepted this project will be routed as a majot TI. There will not be a need to change any of the forms we will take care of that on our end. If you have any questions please let me know.

Adele Schaffeld-Griffin

###-####
Intake Approval  10/8/2013 FAIL
DetailsAdele J Schaffeld-Griffin
All plan sheet must be signed by a design professional of record. The finish plans need to be stamped and signed.

Once the pre screen is accepted this project will be routed as a majot TI. There will not be a need to change any of the forms we will take care of that on our end. If you have any questions please let me know.

Adele Schaffeld-Griffin

###-####
Application received  10/7/2013 DONE
Application submitted via PDS Online on Oct 7 2013 4:57PM