Third Notice | | 9/7/2014 | 9/5/2014 | | DONE |
|
|
|
This permit finaled on the web by Curtis Weedop
|
Third Notice | | 7/14/2014 | 9/2/2014 | | DONE |
|
|
|
e-mailed Curtis and Virna
|
Third Notice | | 6/14/2014 | 7/9/2014 | | DONE |
|
|
|
e-mailed to Curtis
|
Third Notice | | 5/10/2014 | 6/9/2014 | | DONE |
|
|
|
e-mailed to Curtis Weedop
|
Second Notice | | 4/10/2014 | 5/5/2014 | | DONE |
|
|
|
e-mailed to Curtis Weedop
|
First Notice | | 3/30/2014 | 3/31/2014 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/20/2014 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 3/10/2014 | 3/10/2014 | 3/10/2014 | P | PASS |
Tom Arcoraci
|
|
|
if no answer please call ###-#### Phone #: ###-#### >> Inspection requested via web by Rock Self
|
FIRE-Final Inspection | 3/10/2014 | 3/10/2014 | 3/10/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 2/28/2014 | 3/4/2014 | 3/4/2014 | A | CANC |
Dave Hannah
|
|
|
if no answer please try my desk phone ###-#### Thanks Phone #: ###-#### >> Inspection requested via web by Rock Self Inspection cancelled from web by: Rock Self
|
FIRE-Final Inspection | 2/28/2014 | 3/3/2014 | 3/3/2014 | A | FAIL |
Forrest France
|
|
|
Missing exit signs per plan review annotations at three locations, missing occupant notification at the break room and office areas, project related fire alarm permit final pending.
|
BLD-Ceiling Grid Inspection | 12/26/2013 | 12/27/2013 | 12/27/2013 | A | PASS |
Dave Hannah
|
|
|
if no answer on my cell phone please call my desk phone ###-#### Thanks Phone #: ###-#### >> Inspection requested via web by Rock Self
|
BLD-Wall cover | 12/11/2013 | 12/11/2013 | 12/11/2013 | A | PASS |
Dave Hannah
|
|
|
if no answer try my desk phone ###-#### Phone #: ###-#### >> Inspection requested via web by Rock Self
|
Plan assigned to (CJW) | 10/9/2013 | 10/9/2013 | 11/21/2013 | | PASS |
Carl Westfall
|
|
|
ST. LUKE'S HOSPITAL - 2ND STORY - TOWER ePlanReview - Level 3 TI (20 days - Nov 4)
|
Routing - PLAN CHECK | 11/20/2013 | | 11/21/2013 | | PASS |
Carl Westfall
|
|
|
Architect Emailed a revised sheet. Uploaded the revised drawing into ePlanReview. Drawings approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/21/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/21/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 11/21/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 11/21/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 11/21/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 11/20/2013 | 11/20/2013 | 11/20/2013 | | PASS |
Craig D. Hanson
|
|
|
See report revision 1
|
Routing - PLAN CHECK | 11/19/2013 | | 11/20/2013 | | FAIL |
Carl Westfall
|
|
|
Revisions made to the drawings by the Architect made the accessible shower no longer accessible to the disabled. Correction was required.
|
Plan resubmittals received | | | 11/19/2013 | | DONE |
|
|
|
|
1st review completed | | | 11/8/2013 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 11/8/2013 | | DONE |
|
|
|
|
Routing - FIRE | 10/9/2013 | 10/9/2013 | 11/7/2013 | | FAIL |
Craig D. Hanson
|
|
|
Refer to report
|
Routing - PLAN CHECK | 10/9/2013 | | 11/6/2013 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required.
|
Routing - PLUMBING | 10/9/2013 | | 10/16/2013 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - Addressing | 10/9/2013 | | 10/11/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing PW Sewer Rating | 10/9/2013 | | 10/11/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 10/9/2013 | | 10/9/2013 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 10/9/2013 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and Plan Review Fees paid.
|
Pending Assignment by JCB | 10/9/2013 | | 10/9/2013 | | DONE |
Jason Blais
|
|
|
|
Payment Received | | | 10/8/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 10/8/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please upload the completed check list
Please upload the 304 design professional form
All plan sheet must be signed by a design professional of record. The finish plans need to be stamped and signed.
Once the pre screen is accepted this project will be routed as a majot TI. There will not be a need to change any of the forms we will take care of that on our end. If you have any questions please let me know.
Adele Schaffeld-Griffin
###-####
|
Intake Approval | | | 10/8/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
All plan sheet must be signed by a design professional of record. The finish plans need to be stamped and signed.
Once the pre screen is accepted this project will be routed as a majot TI. There will not be a need to change any of the forms we will take care of that on our end. If you have any questions please let me know.
Adele Schaffeld-Griffin
###-####
|
Application received | | | 10/7/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 7 2013 4:57PM
|