Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD13-02772
StatusFinaled
Name TK CONSTRUCTION
Site Address 5118 W OVERLAND RD
Project NameMAY NAILS & SPA SALON
Customer Number 
ePlanReviewYes
Description
(MAY NAILS & SPA SALON) Permit to improve a 1,000 s.f. previously completed vanilla tenant improvement (BLD13-01681) into a nail salon. Prior to vanilla shell the space was part of a restaurant. The demising walls, suspended acoustical tile ceiling and lighting are existing. New work includes mechanical ventilation, plumbing to the pedicure stations, electrical convenience outlets and floor and wall finishes. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department.**ajs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 2/8/20142/3/2014 DONE
This permit finaled on the web by Todd Kurns
Second Notice 1/9/20142/3/2014 DONE
First Notice 12/13/201312/30/2013 DONE
DetailsChristina Prado
mailed 12-30-13
FIRE-Final Inspection12/2/201312/3/201312/3/2013APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final12/2/201312/3/201312/3/2013APASS
DetailsTom Arcoraci
Phone #: ###-#### >> Inspection requested via web by Todd Kurns
BLD-Final12/2/201312/3/201312/3/2013APASS
DetailsTom Arcoraci
Phone #: ###-#### >> Inspection requested via web by Todd Kurns
Permanent Occupancy  12/3/2013 DONE
DetailsTisha Gallop
OVERRIDE  10/23/2013  
Print Occupancy Form  10/23/2013 DONE
Issue PAID IN FULL permit  10/23/2013 DONE
Case Summary (BLD)  10/23/2013 DONE
Permit Ready to Issue  10/23/2013  
Plan assigned to (AJS)10/9/201310/9/201310/21/2013 PASS
DetailsAdele J Schaffeld-Griffin
Due 10/22Level 2 e plan
Routing - PLAN CHECK10/9/2013 10/21/2013 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed  10/21/2013 DONE
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  10/21/2013 DONE
Routing - PLUMBING10/9/2013 10/15/2013 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - MECHANICAL10/9/2013 10/15/2013 PASS
DetailsTroy James
Routing - Erosion and Sediment10/9/2013 10/10/2013 PASS
DetailsEvan Jenkins
Payment Received  10/9/2013 DONE
Payment received via Govolutions
Intake Approval  10/9/2013 PASS
DetailsAdele J Schaffeld-Griffin
Routing - Addressing10/9/2013 10/9/2013 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS10/9/2013 10/9/2013 PASS
DetailsBeverly Mountain
Routing PW Sewer Rating10/9/2013 10/9/2013 PASS
DetailsConnie Baumgartner
Application received  10/8/2013 DONE
Application submitted via PDS Online on Oct 8 2013 9:08AM
Intake Approval  10/8/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Please re upload the the drawings individually with conventional naming.

Thank you

Adele