BLD-Final | 6/26/2014 | 6/27/2014 | 6/27/2014 | A | PASS |
Mike Jordan
|
|
|
nick - 11:30 please Phone #: ###-####
|
DOC - Permit Finaled | 6/27/2014 | 6/27/2014 | 6/27/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Conference | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Dave Hannah
|
|
|
Nick Phone #: ###-####
|
PubWorks Occupancy Approval | 6/25/2014 | 6/25/2014 | 6/25/2014 | | DONE |
Jason C. Taylor
|
|
|
*BOND IN PLACE FOR FINAL SITE RESTORATION, REVEGETATION, & DRIVEWAY * A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 3/4/2014 | 3/4/2014 | 3/4/2014 | P | PASS |
Jim Storey
|
|
|
Nick Phone #: ###-####
|
BLD-Framing/Rough-in | 3/4/2014 | 3/4/2014 | 3/4/2014 | P | PASS |
Jim Storey
|
|
|
Nick Phone #: ###-#### c/n made ok
|
BLD-Framing/Rough-in | 2/27/2014 | 2/28/2014 | 2/28/2014 | A | PART |
Jim Storey
|
|
|
1st thing please - Nick Phone #: ###-#### mlb support to bearing thru floor behind stairs/ 3 ply needs cluster nails or sds screws.//ok to insulate.
|
Routing - MECHANICAL | 2/20/2014 | | 2/20/2014 | | PASS |
Troy James
|
|
|
resubmitted another manual j for review
|
BLD-Wall Bracing | 2/11/2014 | 2/11/2014 | 2/11/2014 | P | PASS |
Jim Storey
|
|
|
Nick Phone #: ###-####
|
BLD-Other | 2/11/2014 | 2/11/2014 | 2/11/2014 | P | PASS |
Jim Storey
|
|
|
fire rated soffit // Nick Phone #: ###-####
|
Plan Modification Accepted | | | 2/3/2014 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 2/3/2014 | | 2/3/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Foundation | 12/26/2013 | 12/30/2013 | 12/31/2013 | A | PASS |
Dave Hannah
|
|
|
jard Phone #: ###-####
|
BLD-Footing | 12/20/2013 | 12/23/2013 | 12/23/2013 | A | PASS |
Dave Hannah
|
|
|
request 11:30 // Jared ###-####
|
BLD-Footing | 12/19/2013 | 12/20/2013 | 12/20/2013 | A | CANC |
Dave Hannah
|
|
|
jared- 11:30 please Phone #: ###-#### // cancelled and rescheduled for monday am
|
PubWorks Subgrade Approval | 12/20/2013 | 12/20/2013 | 12/20/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the garage footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Foundation | 11/26/2013 | 11/26/2013 | 11/26/2013 | A | PART |
Jim Sly
|
|
|
nick Phone #: ###-#### PLEASE EARLY AM IF POSSIBLE Daylight Bsmnt. walls only.....OK
|
BLD-Footing | 11/18/2013 | 11/20/2013 | 11/20/2013 | P | PASS |
Jim Sly
|
|
|
Jared Phone #: ###-####
|
PubWorks Subgrade Approval | 11/18/2013 | 11/18/2013 | 11/18/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade (daylight basement only) is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 11/14/2013 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 11/12/2013 | | |
|
|
|
|
Routing - FIRE | 11/5/2013 | 11/5/2013 | 11/12/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Plan assigned to (AJS) | 10/28/2013 | 10/28/2013 | 11/12/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 10/30 hillside 10,000
|
Routing - PLAN CHECK | 11/5/2013 | | 11/12/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 11/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing PW Grading-Hillside | 11/5/2013 | | 11/5/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - FIRE | 10/25/2013 | 10/25/2013 | 10/29/2013 | | FAIL |
Scott Arellano
|
|
|
Emailed resubmittal items to the applicant.
|
1st review completed | | | 10/29/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Erosion and Sediment | 10/29/2013 | | 10/29/2013 | | PASS |
Evan Jenkins
|
|
|
|
Routing PW Grading-Hillside | 10/29/2013 | | 10/29/2013 | | FAIL |
Jason C. Taylor
|
|
|
Need to upload correct geotechnical report and hillside report. Jason Taylor ###-####
|
Routing - PLAN CHECK | 10/18/2013 | | 10/29/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
ePlan review
|
Plan assigned to (JG) | 10/18/2013 | 10/18/2013 | 10/28/2013 | | DEFR |
Javier Guzman
|
|
|
Due 10/30 L2 ePlan
|
Route to Impact Fee Review | 10/18/2013 | 10/21/2013 | 10/25/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 10/18/2013 | | 10/21/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 10/18/2013 | | 10/18/2013 | | PASS |
Susan Riggs
|
|
|
Note on plan that a 3' side yard setback is required for the turn around.
|
Routing - Addressing | 10/18/2013 | | 10/18/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/18/2013 | | 10/18/2013 | | PASS |
Beverly Mountain
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/18/2013 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/18/2013 | | DONE |
Christina Prado
|
|
|
|
Payment Received | | | 10/17/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 10/17/2013 | | PASS |
Christina Prado
|
|
|
|
Intake Approval | | | 10/14/2013 | | FAIL |
Barbara Stitt
|
|
|
Sheets turned to landscape, needs manual J, needs RES Check
|
Application received | | | 10/10/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 10 2013 2:22PM
|