FIRE-Final Inspection | 10/28/2013 | 10/28/2013 | 10/28/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 10/28/2013 | 10/28/2013 | 10/28/2013 | A | PART |
Tom Arcoraci
|
|
|
ok for temp exit sign near wharehouse door to be changed
|
FIRE-Hydro test above ground | 10/25/2013 | 10/25/2013 | 10/25/2013 | P | PART |
Craig D. Hanson
|
|
|
Fire alarm system working and monitored by Alarm Star. Fire sprinklers being inspected and back flow flush by Shilo. Life safety issues OK for temporay CO.
|
FIRE-Final Inspection | 10/24/2013 | 10/25/2013 | 10/25/2013 | A | FAIL |
Craig D. Hanson
|
|
|
met with Chris on site. Fire Alarm and Fire Sprinkler system still needs certification. No apparent modifications to either sstem has been made. Other items: area around all breaker box's need to be cleared. Some exit signs need batteries replaced. HazMat dimond on oil storage tank. Class D extinguisher (1) for welding area. Fuel pump permits being maintaned by other tenant on property. No stotage above wood built structure in bay unless an enginer evaluates. Cooler room being used for boat storage.
|
FIRE-Final Inspection | 10/24/2013 | 10/24/2013 | 10/24/2013 | P | CANC |
Troy Cobbley
|
|
|
Overbooked but Chris and I discussed general life safety requirements on the phone. Per Chris the phone lines for the fire alarm system are being re-installed. I told him that I would need "certification" that the monitoring had been set up and the system tested prior to a final inspection.
|
Issue PAID IN FULL permit | | | 10/24/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/23/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/23/2013 | | DONE |
Tisha Gallop
|
|
|
Per Jason Blais waived requirements for GC on this permit per no work being done.
|
Telephone call | | | 10/23/2013 | | DONE |
Christina Prado
|
|
|
Called Chris to give fees due
|
Plan assigned to (AJS) | 10/17/2013 | 10/17/2013 | 10/22/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Due 10/22
|
Routing - PLAN CHECK | 10/21/2013 | | 10/22/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
application stated sales but there was not sales area indicated on the plans
|
1st review completed | | | 10/22/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 10/22/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2013 | | DONE |
|
|
|
|
Routing - FIRE | 10/21/2013 | 10/21/2013 | 10/21/2013 | | PASS |
Craig D. Hanson
|
|
|
|
Plan resubmittals received | | | 10/21/2013 | | DONE |
Christina Prado
|
|
|
Received twosets of plan review comments and two sets revised plan sheets marked S1, A1, A2, A3, A4, FA-1 & FA-2;Plans taken to Adele for further review
|
Telephone call | | | 10/18/2013 | | DONE |
|
|
|
Spoke with architect on 10/18. he said he would resubmit plans in a larger scale so that I could re-valuate.
|
Routing - FIRE | 10/17/2013 | 10/17/2013 | 10/17/2013 | | FAIL |
Craig D. Hanson
|
|
|
Need more information.
|
Plan assigned to (CDM) | 10/16/2013 | 10/16/2013 | 10/17/2013 | | DEFR |
Carl D Madsen
|
|
|
|
Issue PAID IN FULL permit | | | 10/16/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | 10/16/2013 | 10/16/2013 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/16/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/16/2013 | | DONE |
Tisha Gallop
|
|
|
|