Third Notice | | 5/10/2014 | 5/13/2014 | | DONE |
|
|
|
This permit finaled on the web by Richard Schultz
|
Third Notice | | 4/6/2014 | 5/5/2014 | | DONE |
|
|
|
mailed
|
Second Notice | | 3/10/2014 | 4/1/2014 | | DONE |
|
|
|
Faxed 4-1-14
|
First Notice | | 2/14/2014 | 2/28/2014 | | DONE |
Christina Prado
|
|
|
mailed 2-28-14
|
Permanent Occupancy | | | 2/4/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 1/31/2014 | 1/31/2014 | 1/31/2014 | P | PASS |
Tom Arcoraci
|
|
|
matt Phone #: ###-####
|
FIRE-Final Inspection | 1/31/2014 | 1/31/2014 | 1/31/2014 | A | PASS |
Forrest France
|
|
|
Noted one directional exit sign at the west side not yet installed per plan review annotations, some office door hardware is not yet installed- Building inspector please verify prior to final. Remainder of fire life safety items passed.
|
BLD-Framing/Rough-in | 12/16/2013 | 12/16/2013 | 12/17/2013 | P | PASS |
Dave Hannah
|
|
|
Thanks Matt Phone #: ###-#### >> Inspection requested via web by Richard Schultz
|
Place hold on job | 11/21/2013 | | 12/12/2013 | | DONE |
Christina Prado
|
|
|
BLD13-03047 must be issued at same time for Vanilla Shell created by demising wall///cdp
|
Permit Ready to Issue | | | 12/12/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 12/12/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 12/12/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 11/15/2013 | 11/15/2013 | 11/21/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 11/21
|
Routing - PLAN CHECK | 11/21/2013 | | 11/21/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/21/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/15/2013 | | 11/20/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 11/20/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan
|
Intake Approval | | | 11/15/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PUBLIC WORKS | 11/15/2013 | | 11/15/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 11/15/2013 | | 11/15/2013 | | PASS |
Emily Dixon
|
|
|
Suite number is 500.
|
Routing PW Sewer Rating | 11/15/2013 | | 11/15/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 10/24/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please complete and upload the 518 check list for the pre screen.
Please let me know what is being done with the space not included in this permit. An additional permit, not plans, may need to be submitted in order to issue a correct certificate of occupancy for the square footage now that is is reduced.
Thank you
Adele
###-####
|
Application received | | | 10/18/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 18 2013 12:05PM
|