Permit NumberBLD13-02949
StatusFinaled
Name KOUBA HOMES
Site Address 6401 S EISENMAN RD Unit: 105
Project NameQuarry Business Complex Ste# 1
Customer Number 
ePlanReviewYes
Description
(DANBAY LLC. – Quarry Business Complex Ste# 105) Permit is to build out a 4,774 metal milling and office tenant (4,247 sq. ft. 1st floor / 527 sq. ft. 2nd floor)in an existing 20,268 square foot shell and core building (BLD07-00349). This building if fire sprinklered for non-separated uses and area increase. Approval contingent upon adhering to the approved plans on file. Work to include: [construction of interior non-bearing walls to create a private office, two open office areas, two unisex accessible restrooms, and a manufacturing area], installation of new load bearing walls / floor to create a new second floor, installation of new electrical, installation of new accessible bathroom fixtures, installation of mop sink, new kitchenette with sink, construction of a new interior open stairway, and finishes in compliance with chapter 8 of the 2006 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 9/3/201410/6/2014 DONE
follow up // company on hold 10/6/14
Third Notice 7/14/20148/29/2014 DONE
mailed with letter to Kouba Homes
Third Notice 6/14/20147/9/2014 DONE
mailed to Kouba
Third Notice 5/12/20146/9/2014 DONE
mailed to Kouba Homes
Second Notice 4/10/20145/7/2014 DONE
DetailsBarbara Stitt
Mailed 5-7-14
First Notice 3/21/20143/31/2014 DONE
DetailsChristina Prado
mailed 4-1-14
BLD-Final3/10/20143/11/20143/11/2014APASS
DetailsJim Storey
vince Phone #: ###-#### final ok no card on site
Print Occupancy Form  3/11/2014 DONE
DetailsChristina Prado
Permanent Occupancy  3/11/2014 DONE
DetailsChristina Prado
FIRE-Final Inspection3/7/20143/10/20143/10/2014APASS
DetailsForrest France
Verified C/N items are finished with the exception of door hardware at one pair of main entry/exit doors. This item to be completed prior to structural final as agreed.
FIRE-Final Inspection3/7/20143/7/20143/7/2014PFAIL
DetailsTroy Cobbley
Provide fire extinguisher on the mezzanine, repair/install all exit signs/emergency lights and provide single action hardware on one set of the double store front doors.
BLD-Energy code compliance2/6/20142/7/20142/7/2014APASS
DetailsJim Storey
vince Phone #: ###-####
BLD-Framing/Rough-in2/5/20142/5/20142/5/2014PPASS
DetailsJim Storey
Vince Phone #: ###-####
BLD-Other12/30/201312/30/201312/30/2013PPASS
DetailsJim Storey
vince - fire wall Phone #: ###-####
Permit Ready to Issue  12/12/2013 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  12/12/2013 DONE
DetailsChristina Prado
Print Occupancy Form  12/12/2013 DONE
DetailsChristina Prado
PLANS/APPL TAKEN TO FRONT DESK  11/21/2013 DONE
DetailsTim L. Woodard
Plan assigned to (TLW)10/25/2013 11/21/2013 PASS
DetailsTim L. Woodard
Level 3 TI - ePlanReview - Moser Metal Milling
Routing - PLAN CHECK11/19/2013 11/21/2013 PASS
DetailsTim L. Woodard
Routing - PLUMBING11/19/2013 11/20/2013 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - FIRE11/19/2013 11/20/2013 PASS
DetailsCraig D. Hanson
See Fire Report Rveision 1
Plan resubmittals received  11/19/2013 DONE
DetailsTim L. Woodard
E plan. TLW
Routing - FIRE10/25/201310/25/201311/18/2013 FAIL
DetailsCraig D. Hanson
See Fire Plan Report
1st review completed  11/18/2013 DONE
DetailsTim L. Woodard
Routing PW Solid Waste10/25/2013 11/18/2013 PASS
DetailsPeter J. McCullough
Approved per E-Plan Review. TLW
Routing - ELECTRICAL10/25/2013 11/14/2013 PASS
DetailsDoug A Poedy
All equipment must be listed. TLW
Routing - PLAN CHECK10/25/2013 11/14/2013 FAIL
DetailsTim L. Woodard
Refer to change marks on the drawings. TLW
Routing - PLUMBING10/25/2013 10/30/2013 FAIL
DetailsBill VanDegrift
Need to seperate hosebibs in shop from potable supply. Install a RPBP for evaporative cooler and hosebibs in shop.
Routing - Erosion and Sediment10/25/2013 10/28/2013 PASS
DetailsEvan Jenkins
No Review Needed
Routing - Addressing10/25/2013 10/28/2013 PASS
DetailsEmily Dixon
Routing PW Sewer Rating10/25/2013 10/28/2013 PASS
DetailsBeverly Mountain
Routing PW Environmental10/25/2013 10/28/2013 PASS
DetailsWalt Baumgartner
OK, spoke to owner Rob Moser w/ regard to wastewater disposal, etc.
Pending Assignment by JCB10/25/2013 10/25/2013 DONE
DetailsJason Blais
Routing - PUBLIC WORKS10/25/2013 10/25/2013 PASS
DetailsBeverly Mountain
Intake Approval  10/24/2013 PASS
DetailsJason Blais
Prescreen approved by Sam Zahorka and plan review fees paid.
Application received  10/22/2013 DONE