DOC - Permit Finaled | | | 12/23/2015 | | DONE |
|
|
|
|
BLD-Final | 2/28/2014 | 3/3/2014 | 3/3/2014 | A | PASS |
Dave Hannah
|
|
|
shawn Phone #: ###-####
|
FIRE-Final Inspection | 2/18/2014 | 2/18/2014 | 2/18/2014 | P | PASS |
Forrest France
|
|
|
Final okay pending egress components per approved plans- to be verified at structural final.
|
BLD-Final | 2/14/2014 | 2/18/2014 | 2/18/2014 | P | NR |
Dave Hannah
|
|
|
Shawn-Please call 30 mins prior to inspection Phone #: ###-####
|
FIRE-Final Inspection | 2/14/2014 | 2/18/2014 | 2/18/2014 | A | NR |
Forrest France
|
|
|
Missing approved plans on site, may need to provide an additional exit sign.
|
BLD-Framing/Rough-in | 1/15/2014 | 1/16/2014 | 1/16/2014 | P | PART |
Jim Sly
|
|
|
Shawn-Please call at least 30 mins prior to insepction Phone #: ###-#### Pony Wall........where glass will be installed above it OK.
|
BLD-Wall Bracing | 1/15/2014 | 1/16/2014 | 1/16/2014 | P | PART |
Jim Sly
|
|
|
Shawn-Please call at least 30 mins prior to insepction Phone #: ###-#### Pony Wall.......Where glass is going to be installed above.....OK
|
Inspection Record Card- Bld | | | 1/13/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 1/13/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 1/13/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (AJS) | 11/14/2013 | 11/14/2013 | 11/25/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 11/20
|
Routing - PLAN CHECK | 11/25/2013 | | 11/25/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/25/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/14/2013 | | 11/18/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks, I spoke with Bruce and he is going to revise the code summary to match to original submittal from 2005 as this permit is not changing occupant load.
|
1st review completed | | | 11/18/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 11/14/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 11/1/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1 Please re upload the drawings in the drawings folder. Drawings do not go in the documents folder.
2 Please remove the drawings that have been replaced
3 Please provide the required stamping area on the plans.Cover sheet leave a 4"x4" space located 3" off right sheet edge. All other plans shall have a 4"x2" space locted 3" off the right sheet edge.
Please see http://pds.cityofboise.org/media/105041/electronicstandards.pdf for the required standards for electronic submittal. If you are having difficulties please contact Alex DeYoung at ###-####
I completed the pre screen, please see 3 items above.
Thank you
|
Intake Approval | | | 10/29/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1 Please re upload the drawings in the drawings folder.
2 Please re upload the drawings to read left to right.
3 Please submit the 304 design professional of record form.
I will begin the pre screen when the items above are corrected.
Thank you
|
Application received | | | 10/23/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 23 2013 11:55AM
|