First Notice | | 12/29/2013 | 12/27/2013 | | DONE |
|
|
|
|
BLD-Final | 12/16/2013 | 12/19/2013 | 12/19/2013 | A | PASS |
Tom Arcoraci
|
|
|
roy Phone #: ###-####
|
Permanent Occupancy | | | 12/19/2013 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 12/16/2013 | 12/18/2013 | 12/18/2013 | P | PASS |
Forrest France
|
|
|
Life safety inspection completed satisfactory.
|
BLD-Ceiling Grid Inspection | 12/10/2013 | 12/13/2013 | 12/13/2013 | A | PART |
Jim Storey
|
|
|
Roy Phone #: ###-#### ok pending others
|
BLD-Energy code compliance | 11/22/2013 | 11/26/2013 | 11/26/2013 | A | PASS |
Jim Storey
|
|
|
Roy Phone #: ###-####
|
BLD-Framing/Rough-in | 11/21/2013 | 11/25/2013 | 11/25/2013 | A | PART |
Jim Storey
|
|
|
Roy Phone #: ###-#### framing ok pending others
|
Print Occupancy Form | | | 11/21/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 11/18/2013 | | |
|
|
|
|
Plan assigned to (AJS) | 11/5/2013 | 11/5/2013 | 11/18/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 11/15 level 2
|
Issue PAID IN FULL permit | | | 11/18/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 11/18/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 11/18/2013 | | 11/18/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/2013 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 11/18/2013 | | 11/18/2013 | | PASS |
Beverly Mountain
|
|
|
|
Permit Ready to Issue | | | 11/18/2013 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 11/15/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 11/5/2013 | | 11/14/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Erosion and Sediment | 11/5/2013 | | 11/6/2013 | | PASS |
Evan Jenkins
|
|
|
|
Routing - Addressing | 11/5/2013 | | 11/5/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing PW Sewer Rating | 11/5/2013 | | 11/5/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 11/5/2013 | | 11/5/2013 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 11/5/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Payment Received | | | 11/4/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 10/30/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please provide the 304 design professional form
Please provide the ESC waiver letter.
Thank you
|
Application received | | | 10/29/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 29 2013 1:50PM
|