BLD-Blower Door Test Results | 8/28/2014 | 8/28/2014 | 8/28/2014 | P | PASS |
Tony Young
|
|
|
4.5
|
BLD-Final | 8/27/2014 | 8/27/2014 | 8/27/2014 | P | PASS |
Tony Young
|
|
|
Reinspect from 8/26 correction notice for final. Thank you. Phone #: ###-#### Inspection requested via web by Heather Echevarria
|
DOC - Permit Finaled | 8/27/2014 | 8/27/2014 | 8/27/2014 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 8/26/2014 | 8/26/2014 | 8/26/2014 | P | FAIL |
Tony Young
|
|
|
Jason Taylor is doing his inspection this morning at 10:30am to bond around part of the grading/drainage. Please call Heather with any questions - ###-#### Phone #: ###-#### Inspection requested via web by Heather Echevarria,,, c/n posted
|
PubWorks Occupancy Approval | 8/26/2014 | 8/26/2014 | 8/26/2014 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Foundation | 8/1/2014 | 8/4/2014 | 8/4/2014 | A | PASS |
Tony Young
|
|
|
Bill; Phone #: ###-####,, retaining wall ok
|
BLD-Footing | 7/29/2014 | 7/30/2014 | 7/30/2014 | A | PASS |
Tony Young
|
|
|
Bill Phone #: ###-####
|
PubWorks Subgrade Approval | 7/30/2014 | 7/30/2014 | 7/30/2014 | | DONE |
Jason C. Taylor
|
|
|
Retaining wall subgrade is apprved by the geotechnical enginner. Ok to pur foundations. Jason Taylor ###-####.
|
BLD-Footing | 7/29/2014 | 7/29/2014 | 7/29/2014 | P | NR |
Tony Young
|
|
|
Bill-###-####, retaining wall footing
|
BLD-Footing | 7/28/2014 | 7/29/2014 | 7/29/2014 | A | NR |
Tony Young
|
|
|
Bill-###-####, retaining wall,, needs soil report 1st
|
BLD-Footing | 7/28/2014 | 7/28/2014 | 7/29/2014 | P | NR |
Tony Young
|
|
|
Bill-###-####
|
CHANGE STATUS TO (ISS) | | | 7/28/2014 | | DONE |
Christina Prado
|
|
|
Per Carl Madsen - no additional fees due for retaining wall plan mod. Changed status to issue as no fees due and approved plans have been returned to applicant
|
Plan assigned to (CDM) | 7/18/2014 | 7/18/2014 | 7/25/2014 | | PASS |
Carl D Madsen
|
|
|
res plan mod, cantilevered retaining wall
|
Routing PW Grading-Hillside | 7/25/2014 | | 7/25/2014 | | PASS |
Jason C. Taylor
|
|
|
AS built drawings will be provided prior to occupancy as per discussed with Heather E. on 7/24/2014. Jason Taylor ###-####
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2014 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 7/23/2014 | | 7/23/2014 | | FAIL |
Jason C. Taylor
|
|
|
Need as built or updated drawings. Jason Taylor ###-####
|
Routing - PLAN CHECK | 7/18/2014 | | 7/23/2014 | | PASS |
Carl D Madsen
|
|
|
plan mod, 3 pages of structural calc and spec. Reference structural calculations.
|
Plan Modification Accepted | | | 7/18/2014 | | DONE |
Tisha Gallop
|
|
|
structural revision on cantilevered retaining wall
|
BLD-Energy code compliance | 6/18/2014 | 6/18/2014 | 6/18/2014 | P | PASS |
Tony Young
|
|
|
Heather Phone #: ###-####
|
BLD-Framing/Rough-in | 6/16/2014 | 6/16/2014 | 6/16/2014 | P | PASS |
Tony Young
|
|
|
Rec''d staple equivalent from engineer - it will be insight 6/16 PM for reinspect on 6/17 AM. Insulators starting 6/17AM per voice mail from Tony. Phone #: ###-#### >> Inspection requested via web by Heather Echevarria
|
BLD-Framing/Rough-in | 6/16/2014 | 6/16/2014 | 6/16/2014 | P | CANC |
Tony Young
|
|
|
Please call Heather for location of plans, truss layout, and engineering Phone #: ###-#### >> Inspection requested via web by Heather Echevarria Inspection cancelled from web by: Heather Echevarria
|
BLD-Framing/Rough-in | 6/13/2014 | 6/16/2014 | 6/16/2014 | A | PEND |
Tony Young
|
|
|
Please call Heather for location of plans, truss layout, and engineering Phone #: ###-#### >> Inspection requested via web by Heather Echevarria
|
BLD-Framing/Rough-in | 6/12/2014 | 6/13/2014 | 6/13/2014 | A | FAIL |
Tony Young
|
|
|
Please call Heather for location of plans, truss layout, and engineering Phone #: ###-#### >> Inspection requested via web by Heather Echevarria,, met framer,, went over list,, ok to insulate if needed
|
BLD-Framing/Rough-in | 6/11/2014 | 6/12/2014 | 6/12/2014 | P | FAIL |
Tony Young
|
|
|
Please call Heather for location of plans, truss layout, and engineering Phone #: ###-#### >> Inspection requested via web by Heather Echevarria,, need trades,, c/n on permit card
|
BLD-Wall Bracing | 6/11/2014 | 6/12/2014 | 6/12/2014 | A | FAIL |
Tony Young
|
|
|
Please call Heather for location of plans, truss layout, and engineering Phone #: ###-#### >> Inspection requested via web by Heather Echevarria,, need to do as the plan shows or get engineer eqvt
|
BLD-Framing/Rough-in | 6/10/2014 | 6/11/2014 | 6/11/2014 | P | NR |
Tony Young
|
|
|
Please call Heather for location of plans, truss layout, and engineering Phone #: ###-#### >> Inspection requested via web by Heather Echevarria,, need trades 1st,, walk through only,, see notes on back of permit card
|
BLD-Foundation | 4/2/2014 | 4/3/2014 | 4/3/2014 | A | PART |
Tony Young
|
|
|
Bill Phone #: ###-####
|
BLD-Foundation | 4/1/2014 | 4/2/2014 | 4/2/2014 | A | DEFR |
Tony Young
|
|
|
Bill Phone #: ###-####,, rain
|
BLD-Foundation | 4/1/2014 | 4/1/2014 | 4/1/2014 | P | PART |
Tony Young
|
|
|
Bill Phone #: ###-####, wip,, too much rain
|
BLD-Footing | 3/21/2014 | 3/24/2014 | 3/24/2014 | P | PART |
Tony Young
|
|
|
request 2pm // Bill Phone #: ###-####,, work in progress,, ok to pour when ready
|
PubWorks Subgrade Approval | 3/20/2014 | 3/20/2014 | 3/20/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 2/25/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/25/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 2/25/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 1/22/2014 | 1/22/2014 | 2/13/2014 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - MECHANICAL | 2/13/2014 | | 2/13/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 2/13/2014 | | 2/13/2014 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/13/2014 | | DONE |
|
|
|
|
Routing - MECHANICAL | 2/10/2014 | | 2/10/2014 | | FAIL |
Troy James
|
|
|
eplan
|
1st review completed | | | 1/31/2014 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 1/22/2014 | | 1/31/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Grading-Hillside | 1/22/2014 | | 1/28/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - FIRE | 1/22/2014 | 1/22/2014 | 1/27/2014 | | PASS |
Scott Arellano
|
|
|
Approved.
|
Route to Impact Fee Review | 1/22/2014 | 1/25/2014 | 1/24/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Sewer Rating | 1/24/2014 | | 1/24/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - MECHANICAL | 1/24/2014 | | 1/24/2014 | | FAIL |
Troy James
|
|
|
eplan
|
Routing - PLANNING | 1/22/2014 | | 1/23/2014 | | PASS |
David Moser
|
|
|
|
Routing - Addressing | 1/22/2014 | | 1/23/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 1/22/2014 | | 1/23/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - Erosion and Sediment | 1/22/2014 | | 1/23/2014 | | PASS |
Evan Jenkins
|
|
|
Site Prep Inspection Approval Required Prior to Earth Disturbance
|
Intake Approval | | | 1/22/2014 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/22/2014 | | DONE |
|
|
|
|
Intake Approval | | | 1/16/2014 | | FAIL |
Christina Prado
|
|
|
Still needs structural calcs and stamping area on 3 sheets
|
Intake Approval | | | 1/14/2014 | | FAIL |
Tisha Gallop
|
|
|
separate plan sheets, naming conventions, stamp area on pages 1,2,3, mark temp window locations on plans, foundation needs eng. stamp, need all structural engineering for foundation, retaining walls, shear.
|
Application received | | | 11/5/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 5 2013 10:17AM
|