BLD-Final | 4/3/2014 | 4/4/2014 | 4/4/2014 | A | PASS |
Jim Sly
|
|
|
call 1/2 hr before for access // Rayder Phone #: ###-####
|
DOC - Permit Finaled | 4/4/2014 | 4/4/2014 | 4/4/2014 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 1/28/2014 | 1/30/2014 | 1/30/2014 | A | PASS |
Tony Young
|
|
|
call 1/2 hr to meet for access // Raider Phone #: ###-####
|
BLD-Energy code compliance | 1/28/2014 | 1/29/2014 | 1/29/2014 | P | PASS |
Tony Young
|
|
|
energy seal // call 1/2 hr to meet for access // Raider Phone #: ###-####
|
BLD-Energy code compliance | 1/27/2014 | 1/28/2014 | 1/28/2014 | A | PART |
Tony Young
|
|
|
energy seal // call 1/2 hr to meet for access // Raider Phone #: ###-####,, seal pack ok,, ok to insulate
|
BLD-Framing/Rough-in | 1/27/2014 | 1/28/2014 | 1/28/2014 | A | PASS |
Tony Young
|
|
|
call 1/2 hr to meet for access // Raider Phone #: ###-####,, will pull mechanical later on,, nothing will be covered,, ok to insulate
|
BLD-Wall Bracing | 12/9/2013 | 12/10/2013 | 12/10/2013 | P | PASS |
Tony Young
|
|
|
Rader Phone #: ###-####
|
BLD-Foundation | 11/26/2013 | 11/27/2013 | 11/27/2013 | A | DONE |
Tony Young
|
|
|
Dan Phone #: ###-####
|
BLD-Footing | 11/21/2013 | 11/22/2013 | 11/22/2013 | A | PART |
Tony Young
|
|
|
Dan-Please call with results of insepction Phone #: ###-####,, may change point load areas,, pending engineering,, ok to pour when ready
|
PubWorks Subgrade Approval | 11/19/2013 | 11/19/2013 | 11/19/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Routing Walk-In (BLD) | 11/15/2013 | 11/15/2013 | 11/15/2013 | A | DONE |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 11/7/2013 | 11/7/2013 | 11/15/2013 | | PASS |
Perry Paine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/15/2013 | | |
|
|
|
|
Permit Ready to Issue | | | 11/15/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/15/2013 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 11/7/2013 | 11/7/2013 | 11/7/2013 | A | FAIL |
Perry Paine
|
|
|
|
1st review completed | | | 11/7/2013 | | FAIL |
|
|
|
need foundation engineering
|
Routing Walk-In (Erosion) | 11/5/2013 | 11/5/2013 | 11/6/2013 | P | PASS |
Evan Jenkins
|
|
|
|
Application received | | 11/5/2013 | 11/6/2013 | | DONE |
|
|
|
|
Routing Walk-In (PW Hillside) | 11/5/2013 | 11/5/2013 | 11/5/2013 | A | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing Walk-In (Zoning) | 11/5/2013 | 11/5/2013 | 11/5/2013 | A | PASS |
Leon Letson
|
|
|
|