**(DIXON CONTAINER COMPANY)** Application for inspection to determine requirements for issuance of a Certificate of Occupancy for a 42,530 sq ft existing office / warehouse / manufacturing building. This space was previously occupied by "Whitman Industries" while in Ada County’s jurisdiction. This building was annexed into the City of Boise in 2006. NO NEW WORK IS AUTHORIZED UNDER THIS PERMIT. There will be no change to the occupancy. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 5/6/20174/27/2017 DONE
as per Rita-signing off so no 2nd val gets issued
FIRE-Final Inspection4/26/20174/27/20174/26/2017ADONE
DetailsJim Page
the building final was done w/o the fire final being done so please do inspection and call Candy. As per Building Official, racking system has been approved. Final life fire safety inspection passed/complete. Bob A.
Permanent Occupancy  4/26/2017 DONE
Meeting  4/26/2017 DONE
sent Jay Washburn the C of O by mail
DOC - Permit Finaled  4/26/2017 DONE
All trades have been approved
CHANGE STATUS TO (ISS)  4/26/2017 DONE
no fire final was done so had to changed status so could schedule
BLD-Final3/22/20173/22/20173/22/2017PPASS
DetailsJim Page
As per Building Official, racking system has been approved. Final life fire safety inspection passed/complete.
BLD-Final3/20/20173/20/20173/20/2017PDONE
DetailsJim Storey
Building Official has been provided current installation information and has approved current installation and existing conditions.
Additional plans submitted  3/17/2017 DONE
DetailsJason Blais
Additional documentation on the steel storage racks delivered to the Building Official by builiding owner.
BLD-Aging Inspection8/3/20168/3/20168/3/2016 FAIL
DetailsJim Storey
BLD-Aging Inspection8/2/20168/2/20168/2/2016 DONE
DetailsJim Storey
Field inspector contacted by Mike Casey (Plan Manager) regarding resolution of the approval of the Steel Storage Racking assembly. Message forwarded to Buidling Official.
Telephone call  7/27/2016 DONE
DetailsJim Page
Field inspector contacted by Mike Casey (Plan Manager) regarding resolution of the approval of the Steel Storage Racking assembly. Message forwarded to Buidling Official.
Telephone call  7/13/2016 DONE
DetailsJim Page
Contacted Facilities representative (Mike Casey) at Dixon Container to check on the status of resolving the outstanding steel storage racking issue holding up final approval of the buiding permit.
FIRE-Final Inspection3/14/20163/21/20163/21/2016APART
DetailsJim Page
Previously noted items addressed/repaired, fire sprinklers are current/compiant with current inspection tags, fire alarm inspection is current, fire extinguishers are in place with current inspection tags, exit signs have been repaired/modified for correct path of egress. Final approval for life fire safety inspection is contingent on the racking permit, tenant is in the process of getting racking issue addressed and completed.
FIRE-Final Inspection4/22/20144/22/20144/22/2014ANR
DetailsForrest France
Pending remainder of C/N items.
FIRE-Conference4/4/20144/4/20144/4/2014PDONE
DetailsForrest France
Discussion regarding C/N items, door hardware, exit signage, and FIR permit necessary for fire sprinkler system modifications.
FIRE-Final Inspection3/27/20144/3/20144/3/2014AFAIL
DetailsForrest France
Noted items include; obstructed sprinkler head at a storage closet below the warehouse managers office, missing coverage at a mezzanine storage room, need to verify fire protection at the accounts storage closet, overspaced coverage at the hall adjacent to the break room, need to provide a letter stating the existing fire sprinkler system is adequate for the protected hazard, revise door hardware at four warehouse exits and the main entry/exit, cover exposed wiring at the storage room light fixture, adjust directional arrows at exit signs. A racking permit will be necessary for storage over 8'. Refer to plan review documents for details.
Issue PAID IN FULL permit  3/24/2014 DONE
DetailsTisha Gallop
Routing - FIRE3/19/20143/19/20143/19/2014 PASS
DetailsTim L. Woodard
Subject to feild inspection. See IFC report 03-19-14
Application received 11/7/20133/19/2014 DONE
Plan assigned to (TLW)11/8/2013 3/19/2014 PASS
DetailsTim L. Woodard
1st Review Completed. TLW
Case Summary (BLD)  3/19/2014 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  3/19/2014 DONE
DetailsTim L. Woodard
Print Occupancy Form  3/19/2014 DONE
DetailsTisha Gallop
Permit Ready to Issue  3/19/2014 DONE
DetailsTisha Gallop
Telephone call  3/19/2014 DONE
DetailsTisha Gallop
called Jay and told him permit is ready, fee due.
Routing - PLAN CHECK11/18/2013 3/19/2014 PASS
DetailsTim L. Woodard
Routed to fire.
Routing - FIRE11/12/2013 11/18/2013 FAIL
DetailsScott Arellano
Need more information. See Fire Report
1st review completed  11/18/2013 FAIL
Failled Fire
Routing - PLAN CHECK11/8/2013 11/12/2013 PASS
DetailsTim L. Woodard
Approved as IIB only. TLW
Plans ACCEPTED BY PLAN TECH  11/8/2013  
11-7-13 ok per Tim W to take in