First Notice | | 5/6/2017 | 4/27/2017 | | DONE |
|
|
|
as per Rita-signing off so no 2nd val gets issued
|
FIRE-Final Inspection | 4/26/2017 | 4/27/2017 | 4/26/2017 | A | DONE |
Jim Page
|
|
|
the building final was done w/o the fire final being done so please do inspection and call Candy. As per Building Official, racking system has been approved. Final life fire safety inspection passed/complete. Bob A.
|
Permanent Occupancy | | | 4/26/2017 | | DONE |
|
|
|
|
Meeting | | | 4/26/2017 | | DONE |
|
|
|
sent Jay Washburn the C of O by mail
|
DOC - Permit Finaled | | | 4/26/2017 | | DONE |
|
|
|
All trades have been approved
|
CHANGE STATUS TO (ISS) | | | 4/26/2017 | | DONE |
|
|
|
no fire final was done so had to changed status so could schedule
|
BLD-Final | 3/22/2017 | 3/22/2017 | 3/22/2017 | P | PASS |
Jim Page
|
|
|
As per Building Official, racking system has been approved. Final life fire safety inspection passed/complete.
|
BLD-Final | 3/20/2017 | 3/20/2017 | 3/20/2017 | P | DONE |
Jim Storey
|
|
|
Building Official has been provided current installation information and has approved current installation and existing conditions.
|
Additional plans submitted | | | 3/17/2017 | | DONE |
Jason Blais
|
|
|
Additional documentation on the steel storage racks delivered to the Building Official by builiding owner.
|
BLD-Aging Inspection | 8/3/2016 | 8/3/2016 | 8/3/2016 | | FAIL |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 8/2/2016 | 8/2/2016 | 8/2/2016 | | DONE |
Jim Storey
|
|
|
Field inspector contacted by Mike Casey (Plan Manager) regarding resolution of the approval of the Steel Storage Racking assembly. Message forwarded to Buidling Official.
|
Telephone call | | | 7/27/2016 | | DONE |
Jim Page
|
|
|
Field inspector contacted by Mike Casey (Plan Manager) regarding resolution of the approval of the Steel Storage Racking assembly. Message forwarded to Buidling Official.
|
Telephone call | | | 7/13/2016 | | DONE |
Jim Page
|
|
|
Contacted Facilities representative (Mike Casey) at Dixon Container to check on the status of resolving the outstanding steel storage racking issue holding up final approval of the buiding permit.
|
FIRE-Final Inspection | 3/14/2016 | 3/21/2016 | 3/21/2016 | A | PART |
Jim Page
|
|
|
Previously noted items addressed/repaired, fire sprinklers are current/compiant with current inspection tags, fire alarm inspection is current, fire extinguishers are in place with current inspection tags, exit signs have been repaired/modified for correct path of egress. Final approval for life fire safety inspection is contingent on the racking permit, tenant is in the process of getting racking issue addressed and completed.
|
FIRE-Final Inspection | 4/22/2014 | 4/22/2014 | 4/22/2014 | A | NR |
Forrest France
|
|
|
Pending remainder of C/N items.
|
FIRE-Conference | 4/4/2014 | 4/4/2014 | 4/4/2014 | P | DONE |
Forrest France
|
|
|
Discussion regarding C/N items, door hardware, exit signage, and FIR permit necessary for fire sprinkler system modifications.
|
FIRE-Final Inspection | 3/27/2014 | 4/3/2014 | 4/3/2014 | A | FAIL |
Forrest France
|
|
|
Noted items include; obstructed sprinkler head at a storage closet below the warehouse managers office, missing coverage at a mezzanine storage room, need to verify fire protection at the accounts storage closet, overspaced coverage at the hall adjacent to the break room, need to provide a letter stating the existing fire sprinkler system is adequate for the protected hazard, revise door hardware at four warehouse exits and the main entry/exit, cover exposed wiring at the storage room light fixture, adjust directional arrows at exit signs. A racking permit will be necessary for storage over 8'. Refer to plan review documents for details.
|
Issue PAID IN FULL permit | | | 3/24/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 3/19/2014 | 3/19/2014 | 3/19/2014 | | PASS |
Tim L. Woodard
|
|
|
Subject to feild inspection. See IFC report 03-19-14
|
Application received | | 11/7/2013 | 3/19/2014 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 11/8/2013 | | 3/19/2014 | | PASS |
Tim L. Woodard
|
|
|
1st Review Completed. TLW
|
Case Summary (BLD) | | | 3/19/2014 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 3/19/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 3/19/2014 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 3/19/2014 | | DONE |
Tisha Gallop
|
|
|
called Jay and told him permit is ready, fee due.
|
Routing - PLAN CHECK | 11/18/2013 | | 3/19/2014 | | PASS |
Tim L. Woodard
|
|
|
Routed to fire.
|
Routing - FIRE | 11/12/2013 | | 11/18/2013 | | FAIL |
Scott Arellano
|
|
|
Need more information. See Fire Report
|
1st review completed | | | 11/18/2013 | | FAIL |
|
|
|
Failled Fire
|
Routing - PLAN CHECK | 11/8/2013 | | 11/12/2013 | | PASS |
Tim L. Woodard
|
|
|
Approved as IIB only. TLW
|
Plans ACCEPTED BY PLAN TECH | | | 11/8/2013 | | |
|
|
|
11-7-13 ok per Tim W to take in
|