BLD-Conference | 4/8/2015 | 4/9/2015 | 4/9/2015 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Beck,, final ok
|
DOC - Permit Finaled | 4/9/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Conference | 4/7/2015 | 4/8/2015 | 4/8/2015 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Beck,, cross training with staff,, 5 others
|
BLD-Final | 4/6/2015 | 4/7/2015 | 4/7/2015 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Beck
|
PubWorks Occupancy Approval | 4/7/2015 | 4/7/2015 | 4/7/2015 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Wall cover | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Beck
|
BLD-Energy code compliance | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Beck
|
BLD-Framing/Rough-in | 10/2/2014 | 10/2/2014 | 10/2/2014 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Beck,, ok to insulate
|
Plan Modification Accepted | | | 8/27/2014 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 8/27/2014 | | 8/27/2014 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
BLD-Other | 8/12/2014 | 8/13/2014 | 8/13/2014 | A | PART |
Tony Young
|
|
|
fire ratiing // Gordon Phone #: ###-####,, light boxes ok,,work in progress on soffits,, ok
|
BLD-Wall Bracing | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | PASS |
Jim Storey
|
|
|
Request for shear wall inspection and wall cover inspection for feature wall. Please call 30 min prior to arrival. Thanks. Phone #: ###-#### Inspection requested via web by Gary Beck exteior ok to cover
|
BLD-Framing/Rough-in | 8/7/2014 | 8/7/2014 | 8/7/2014 | P | DEFR |
Jim Storey
|
|
|
Request for shear wall inspection and wall cover inspection for feature wall. Please call 30 min prior to arrival. Thanks. Phone #: ###-#### Inspection requested via web by Gary Beck out of time
|
BLD-Wall cover | 8/4/2014 | 8/4/2014 | 8/4/2014 | P | PART |
Tony Young
|
|
|
Gary ,, call 1st, soffits; Phone #: ###-####,, work in progress
|
BLD-Foundation | 3/14/2014 | 3/17/2014 | 3/17/2014 | A | PASS |
Tony Young
|
|
|
ben Phone #: ###-####
|
BLD-Foundation | 3/14/2014 | 3/14/2014 | 3/14/2014 | P | PART |
Tony Young
|
|
|
ben Phone #: ###-####,, wip.. ok
|
BLD-Footing | 3/12/2014 | 3/12/2014 | 3/12/2014 | P | PART |
Tony Young
|
|
|
Ben Phone #: ###-####
|
PubWorks Subgrade Approval | 3/11/2014 | 3/11/2014 | 3/11/2014 | | DONE |
Jason C. Taylor
|
|
|
*All MAIN LEVEL FOUNDATIONS* A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 2/21/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 12/12/2013 | | |
|
|
|
|
Telephone call | | | 12/12/2013 | | DONE |
Christina Prado
|
|
|
called Catherine to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 12/12/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 11/27/2013 | 11/27/2013 | 12/11/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 12/03 L2
|
Routing - PLAN CHECK | 12/11/2013 | | 12/11/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PUBLIC WORKS GRADING | 12/11/2013 | | 12/11/2013 | | PASS |
Jim Wyllie
|
|
|
|
Case Summary (BLD) | | | 12/11/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/11/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 12/10/2013 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheet TF-2.1; taken to Adele
|
Case Summary (BLD) | | | 12/10/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 12/9/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
called and left message with Catherine, the plan set she took and brought back is missing a sheet T2.1. I need 2 stamped copies to issue the permit. 12/9/13
|
Routing - PLAN CHECK | 12/4/2013 | | 12/4/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see 2nd plan review letter in documents. emailed Cathrine 12/4/13 ajs
|
Plan Reviewer's activity | | | 12/4/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Gave copy of plans to Suzan for Cathrine to pick up to make copies per the 2nd plan review letter.
|
1st review completed | | | 12/2/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
emailed comments 12/2
|
Routing - PLAN CHECK | 11/22/2013 | | 12/2/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see plan review letter in documents
|
Routing - PLANNING | 11/19/2013 | | 12/2/2013 | | PASS |
Colleen T Carroll
|
|
|
|
Plan assigned to (JG) | 11/14/2013 | 11/14/2013 | 11/27/2013 | | DEFR |
Javier Guzman
|
|
|
Due 12/03 L2
|
Routing - MECHANICAL | 11/22/2013 | | 11/22/2013 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 11/21/2013 | | 11/22/2013 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - Erosion and Sediment | 11/20/2013 | | 11/21/2013 | | PASS |
Andy J. Long
|
|
|
ESC plan submitted is complete and approved; RP and PD certified.
|
Routing - MECHANICAL | | | 11/20/2013 | | FAIL |
Troy James
|
|
|
emailed correction to A1 heating
|
Routing - Addressing | 11/15/2013 | | 11/18/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 11/18/2013 | | 11/18/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | 11/15/2013 | | 11/18/2013 | | FAIL |
Jason C. Taylor
|
|
|
Geotechnical report needs revised to include building setbacks from top of slope. Jason Taylor ###-####
|
Route to Impact Fee Review | 11/8/2013 | 11/14/2013 | 11/15/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Application received | | 11/8/2013 | 11/15/2013 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/14/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/14/2013 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 11/8/2013 | | FAIL |
|
|
|
Need app, cfh, foundation calcs, floor insul values, spray foam report, geo tech, man j
|