Permit NumberBLD13-03172
StatusFinaled
Name BOISE HOTEL HOLDINGS LLC
Site Address 2970 W ELDER ST
Project NameHoliday Inn - Boise Airport
Customer Number 
ePlanReviewNo
Description
**(HOLIDAY INN – BOISE AIRPORT)** Application for inspection to determine requirements for issuance of a Certificate of Occupancy for a 78,220 sq ft existing hotel building. This building was originally constructed under BLD05-02392. NO NEW WORK IS AUTHORIZED UNDER THIS PERMIT. There will be no change to the occupancy. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/18/201512/18/201512/18/2015PPASS
DetailsJim Storey
Travis Phone #: ###-####
FIRE-Final Inspection12/18/201512/18/201512/18/2015PPASS
DetailsTroy Cobbley
life safety passed
Permanent Occupancy  12/18/2015 DONE
Permanent Occupancy  12/18/2015 DONE
BLD-Final11/17/201511/18/201511/18/2015APASS
DetailsJim Storey
Travis Phone #: ###-#### pending fire
FIRE-Final Inspection11/17/201511/18/201511/18/2015AFAIL
DetailsTroy Cobbley
For final I still need verification of FIR permit for the first floor work,
BLD-Final11/16/201511/17/201511/17/2015PNR
DetailsJim Storey
Travis Phone #: ###-####
FIRE-Final Inspection11/16/201511/17/201511/17/2015AFAIL
DetailsTroy Cobbley
Provide the exit sign in the DIning/Seating area, provide FIR permit for the completed fire alarm work in the first floor corridor
FIRE-Final Inspection4/23/20144/28/20144/29/2014AFAIL
DetailsTroy Cobbley
Repair the exit sign on the fourth floor, provide plan review with a correct floor plan for the first floor, provide notification for the first floor corridor and relocate smoke detector, provide missing exit signs, change door swing on exit door, notify plan review about exiting into patio area for approval.
BLD-Final4/23/20144/28/20144/28/2014PFAIL
DetailsJim Storey
Travis Phone #: ###-#### kitchen door hardware/ pool smoke seal
Issue PAID IN FULL permit  4/23/2014 DONE
DetailsChristina Prado
Plan assigned to (TLW)11/13/2013 11/19/2013 DONE
DetailsTim L. Woodard
Routing - PLAN CHECK11/19/2013 11/19/2013 PASS
DetailsTim L. Woodard
1st review completed  11/19/2013 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  11/19/2013 DONE
DetailsTim L. Woodard
Case Summary (BLD)  11/19/2013 DONE
Print Occupancy Form  11/19/2013 DONE
Permit Ready to Issue  11/19/2013  
Telephone call  11/19/2013  
11-19-13 called Logan permit ready for pick up ///dld
Plans ACCEPTED BY PLAN TECH  11/13/2013  
11-12-13 ok per Tim W to take in
First Notice 12/28/2015   
First Notice 12/28/2015   
Application received 11/12/2013