Permit Information
Permit NumberBLD13-03195
StatusFinaled
Name BROWN BUILDING CO LLC
Site Address 513 E ORION CT
Project Name 
Customer Number 
ePlanReviewNo
Description
WUI ZONE A, Inspector to verify truss loading includes the 12psf of additional dead load for tile roofing. The truss details and layout are uploaded in documents that were used for plan review. Under side of eves 1x6 fire retardant treated cedar. Permit for the construction of a new 4748 sq. ft., two story (below grade 1308 sq. ft., grade level 3440 sq. ft.) single family dwelling with 5 bedrooms, 4.5 bathrooms, approximately 1,058 sq. ft. of covered patio/porch and a 1592 sq. ft. attached garage per the approved plans, plan review report, res check, structural engineering, Evaluation report for spay insulation and any notations. A-1 zoning and setbacks per planning. Inspector may request the designer and or engineer on site during the construction for issues as he determines. AJS A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/10/201412/11/201412/11/2014APASS
DetailsTony Young
Matt Phone #: ###-####// c of o issued
DOC - Permit Finaled12/11/201412/11/201412/11/2014PPASS
DetailsTony Young
PubWorks Occupancy Approval12/11/201412/11/201412/11/2014 DONE
DetailsJason C. Taylor
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
BLD-Final12/10/201412/10/201412/10/2014PNR
DetailsTony Young
Matt Phone #: ###-####,, conf walk through
Plan Modification Accepted  7/29/2014 DONE
new manual j report
Routing - MECHANICAL7/29/2014 7/29/2014 PASS
DetailsTroy James
resubmitted manual j report
BLD-Wall cover7/17/20147/18/20147/18/2014APART
DetailsTony Young
matt Phone #: ###-####,, soffit,, work in progress
BLD-Energy code compliance7/17/20147/17/20147/17/2014PPASS
DetailsTony Young
matt Phone #: ###-####
BLD-Energy code compliance7/16/20147/17/20147/17/2014ANR
DetailsTony Young
matt Phone #: ###-####
BLD-Framing/Rough-in7/9/20147/10/20147/10/2014PPART
DetailsTony Young
Matt Phone #: ###-####,, ok to insulate
BLD-Framing/Rough-in7/3/20147/7/20147/7/2014PCANC
DetailsTony Young
Will Phone #: ###-#### // cancelled per Matt Brown, will call back to reschedule 7/7/14 @ 10:35 .. leg
BLD-Other5/28/20145/29/20145/29/2014APASS
DetailsTom Arcoraci
matt - shear inspection Phone #: ###-#### ok to cover wains coat areas and colums
BLD-Foundation3/26/20143/26/20143/26/2014PPART
DetailsTony Young
Heron Phone #: ###-####.. work in progress,, ok
BLD-Footing3/18/20143/19/20143/19/2014APASS
DetailsTom Arcoraci
Juron Phone #: ###-####
PubWorks Subgrade Approval3/18/20143/18/20143/18/2014 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Issue PAID IN FULL permit  2/28/2014 DONE
DetailsChristina Prado
Permit Ready to Issue  12/18/2013  
Telephone call  12/18/2013  
12-18-13 called Trey permit ready and fee given ///dld
Plan assigned to (AJS) 11/13/201312/17/2013 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Hillside
Telephone call  12/17/2013 DONE
DetailsAdele J Schaffeld-Griffin
called Franklin Buildng Supply, spoke with Jerrod the truss information submitted did not include the loading for the tile roof. He will email me the new layour and details.

Called and relayed the same informaiton to owner

12/17/13 ajs
Plan Reviewer's activity  12/17/2013 DONE
DetailsAdele J Schaffeld-Griffin
email sent to Trey, Matt and Jim, 12/17/13

Trey, the truss information was submitted Thursday afternoon. I finished the project I was working on and started reviewing the information submitted. The truss loading did not include the tile roofing. I spoke with the designer at Franklin and he confirmed that they did not include the added dead load in the design. He was going to add the 12 psf noted from the structural engineering I have from Wolf Engineering and email me the revised information.

Once I receive the revised girder truss loading I will get it reviewed. Below is a time line for this project for your records.

Plans submitted to City of Boise 11/13/13.

Hillside homes have up to a 14 business day turnaround time.

This plan review was completed and comments sent out on 11/29/13, 12 business days not including Thanksgiving.

I received revised plans on 12/2 and again on 12/5 and the truss information on 12/11.


If you have any questions please let me know.

Thank you



Adele Schaffeld-Griffin
Plans Examiner II
City of Boise PDS
###-####

Routing - PLAN CHECK12/17/2013 12/17/2013 PASS
DetailsAdele J Schaffeld-Griffin
Case Summary (BLD)  12/17/2013 DONE
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  12/17/2013 DONE
Inspection Record Card- Bld  12/17/2013 DONE
DetailsChristina Prado
Plan resubmittals received  12/11/2013  
12-11-13 received 1 calc sent to Adele
Plan resubmittals received  12/5/2013 DONE
DetailsChristina Prado
received two sets of revised plan sheets marked A2.0 & A2.1;Taken to Adele for additional review
Routing - PLAN CHECK12/4/2013 12/4/2013 FAIL
DetailsAdele J Schaffeld-Griffin
emailed 2nd comments 12/4/13 see documetns
Plan resubmittals received  12/2/2013  
12-2-13 received 2 copies of sheets A2.2,A4.2, & E1.1 sent to Adele.
Routing - PLAN CHECK11/25/2013 11/29/2013 FAIL
DetailsAdele J Schaffeld-Griffin
emailed comments to Trey 11/29/13 ajs
1st review completed  11/29/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE11/22/201311/13/201311/25/2013 PASS
DetailsScott Arellano
This residence requires an automatic fire sprinkler system as per an agreement with the Boise City Fire Dept, dated 7/10/06 signed by Chief Ren Ross. This requirement is specific to lots on East Orion Court to #26, #27, #28, #29 & #30. See attached plat documents in small documents folder.
Routing - Erosion and Sediment11/21/2013 11/22/2013 PASS
DetailsAndy J. Long
ESC plan and narrative are approved. RP and PD are currently certified.
Routing - MECHANICAL11/15/2013 11/21/2013 PASS
DetailsTroy James
Route to Impact Fee Review11/13/201311/18/201311/15/2013 PASS
DetailsCindy M. Gould
Route to Impact Fee Review11/13/201311/16/201311/15/2013 PASS
DetailsCindy M. Gould
Routing - PLANNING11/15/2013 11/15/2013 PASS
DetailsSusan Riggs
Routing - PUBLIC WORKS11/14/2013 11/15/2013 PASS
DetailsConnie Baumgartner
Routing PW Grading-Hillside  11/14/2013 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Routing - Addressing11/13/2013 11/14/2013 PASS
DetailsJason C. Taylor
Plans ACCEPTED BY PLAN TECH  11/13/2013 DONE
DetailsChristina Prado
Intake Approval  11/13/2013 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  11/13/2013 DONE
DetailsChristina Prado
Application received 11/13/2013