DOC - Permit Finaled | | | 12/23/2015 | | DONE |
|
|
|
|
BLD-Final | 9/26/2014 | 9/29/2014 | 9/30/2014 | P | PASS |
Dave Hannah
|
|
|
Nick Phone #: ###-####
|
Zoning Approval | 9/3/2014 | 9/3/2014 | 9/3/2014 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 8/29/2014 | 9/2/2014 | 9/2/2014 | A | NR |
Jim Sly
|
|
|
Nick Phone #: ###-#### Need Zoning and Electr. finals.
|
FIRE-Final Inspection | 8/29/2014 | 8/29/2014 | 8/29/2014 | P | PASS |
Forrest France
|
|
|
Scope of permit work completed. Life safety inspection passed.
|
BLD-Final | 8/28/2014 | 8/29/2014 | 8/29/2014 | A | NR |
Jim Sly
|
|
|
Nick Phone #: ###-#### Need Fire/Life safety final.
|
BLD-Framing/Rough-in | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | PASS |
Tony Young
|
|
|
Drive thru faming only - Nick Phone #: ###-####
|
BLD-Framing/Rough-in | 7/8/2014 | 7/8/2014 | 7/8/2014 | P | PASS |
Dave Hannah
|
|
|
Nick Phone #: ###-####
|
BLD-Conference | 6/12/2014 | 6/12/2014 | 6/12/2014 | P | PASS |
Dave Hannah
|
|
|
Nick Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/15/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 4/15/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 4/14/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 4/14/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 1/2/2014 | | 1/2/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/2/2014 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 12/6/2013 | | 1/2/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 12/19 ICON Credit Union
|
Routing - PLAN CHECK | 12/6/2013 | | 12/16/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan
|
1st review completed | | | 12/16/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Drainage | 12/6/2013 | | 12/10/2013 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 12/6/2013 | | 12/9/2013 | | PASS |
Josh Wilson
|
|
|
|
Routing - PUBLIC WORKS | 12/6/2013 | | 12/6/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 12/6/2013 | | 12/6/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - Erosion and Sediment | 12/6/2013 | | 12/6/2013 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver submitted and approved. Need to identify RP prior to issuance of permit
|
Intake Approval | | | 12/6/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 11/27/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please upload the required planning documents listed on the check list.
|
Application received | | | 11/19/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 19 2013 9:32AM
|