FIRE-Conference | 6/24/2014 | 6/25/2014 | 6/25/2014 | P | DONE |
Forrest France
|
|
|
Tom Phone #: ###-#### *Completed by C. Hanson*
|
BLD-Other | 4/28/2014 | 4/29/2014 | 4/29/2014 | A | PASS |
Jim Storey
|
|
|
Fire caulking - Tony Phone #: ###-#### fire stopping in progess/ wall ok
|
BLD-Energy code compliance | 4/23/2014 | 4/24/2014 | 4/24/2014 | A | NR |
Jim Storey
|
|
|
Tony Phone #: ###-#### fiberglas insulation instaled not menrial wool. pending arch change or replace fiberglass.
|
BLD-Framing/Rough-in | 4/21/2014 | 4/22/2014 | 4/22/2014 | A | PART |
Jim Storey
|
|
|
Tony Phone #: ###-#### need to extend head of wall to collum supports.
|
Permit Ready to Issue | | | 4/21/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 4/21/2014 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 4/21/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CJW) | 1/2/2014 | 1/2/2014 | 2/12/2014 | | PASS |
Carl Westfall
|
|
|
CUMMINS BOISE CNG/LNG SHOP - ePlanReview - Level 3 TI - (20 days - Jan 29)
|
Routing - PLAN CHECK | 2/5/2014 | | 2/12/2014 | | PASS |
Carl Westfall
|
|
|
Not all revised sheets were uploaded. Please upload all sheets that were revised.
Multiple sheets were uploaded into 2 files. Extracted the drawings and uploaded them into ePlan properly.
(2-6-14) Waiting for revised structural calculations so that they can be uploaded.
(2-12-14) Revised structural calculations were uploaded.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/12/2014 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/5/2014 | | DONE |
|
|
|
|
Routing - FIRE | 2/3/2014 | | 2/3/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Final review report 02-03-14
|
Routing - PLAN CHECK | 1/31/2014 | | 2/3/2014 | | PASS |
Carl Westfall
|
|
|
Routing completed. Sent back to the applicant so that he could upload owner revisions for review.
|
Plan resubmittals requested | | | 2/3/2014 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/31/2014 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/16/2014 | | DONE |
|
|
|
|
1st review completed | | | 1/16/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/2/2014 | | 1/16/2014 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines".
|
Routing - FIRE | 1/2/2014 | 1/2/2014 | 1/7/2014 | | FAIL |
Craig D. Hanson
|
|
|
Please see Fire Plan Report 01-07-14
|
Routing - MECHANICAL | 1/2/2014 | | 1/7/2014 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 1/2/2014 | | 1/6/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - Design Review | 1/2/2014 | | 1/6/2014 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - New exterior doors shown Approved new doors through the building permit.
|
Routing - PUBLIC WORKS | 1/2/2014 | | 1/3/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLUMBING | 1/2/2014 | | 1/3/2014 | | PASS |
Bill VanDegrift
|
|
|
No review required.
|
Routing PW Sewer Rating | 1/3/2014 | | 1/3/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 1/3/2014 | | 1/3/2014 | | PASS |
Walt Baumgartner
|
|
|
|
Intake Approval | | | 1/2/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved on 12/9/13. Plan Review Fees paid on 1/2/14.
|
Pending Assignment by JCB | 1/2/2014 | | 1/2/2014 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 11/22/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 22 2013 2:54PM
|