Permit Information
Permit NumberBLD13-03291
StatusFinaled
Name GUHO CORP
Site Address 3003 W MAIN ST
Project Name30th + Main
Customer NumberREF BLD13-03348
ePlanReviewYes
Description
(30th and Main)(Core and Shell) (MULTIPLE PERMIT NUMBERS) SEE BLD13-03348. No occupancy under this permit. Permit for New 2 story medical office building and site improvements. 1st floor 10,113 sq ft and 2nd floor 11,136 sq ft. 2 existing buildings will be demolitioned under this permit and other site demolition as per approved plans to prepare site for new building. Tenant improvement permits required for 2nd floor and 1st floor suite 100. BLD13-03348 is issued for the tenant in suite130. The work is required to comply with the approved drawings, with the plan review report, with the structural design, and with all applicable codes and ordinances. This building is fully fire sprinklered and has a full fire alarm system compliant with chapter 9 for ambulatory health care. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. The elevator will require a separate permit issued by the State of Idaho elevator division. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (FNL)  9/17/2015 DONE
BLD-Final1/2/20151/5/20151/6/2015PPASS
DetailsDave Hannah
MJ Phone #: ###-####
FIRE-Final Inspection1/2/20151/5/20151/5/2015APASS
DetailsForrest France
Fire life safety finaled. Inspection passed.
Letter of compliance/Occupancy  1/5/2015 DONE
FIRE-Final Inspection12/31/20141/2/20151/2/2015PCANC
DetailsForrest France
Bill ###-####
BLD-Final12/31/20141/2/20151/2/2015PCANC
DetailsDave Hannah
Bill Phone #: ###-####
FIRE-Final Inspection12/30/201412/31/201412/31/2014APART
DetailsForrest France
TCO approved pending trade related fire alarm final.
BLD-Final12/30/201412/31/201412/31/2014PNR
DetailsDave Hannah
MJ Phone #: ###-####
PubWorks Occupancy Approval12/31/201412/31/201412/31/2014 DONE
DetailsTiffany Lowery
Zoning Approval12/31/201412/31/201412/31/2014 DONE
DetailsAndrea Tuning
FIRE-Conference12/22/201412/22/201412/22/2014PDONE
DetailsForrest France
Regarding project related fire alarm and sprinkler permit work.
BLD-Ceiling Grid Inspection10/2/201410/2/201410/2/2014PPART
DetailsDave Hannah
Mark Phone #: ###-#### med gas and elec rooms ok to cover ceilings
BLD-Framing/Rough-in9/30/201410/1/201410/1/2014APEND
DetailsDave Hannah
Mark Phone #: ###-#### 1hr lid med gas and elec rooms
BLD-Framing/Rough-in9/11/20149/12/20149/12/2014APASS
DetailsDave Hannah
BLD-Energy code compliance9/11/20149/11/20149/11/2014PPASS
DetailsDave Hannah
MJ Phone #: ###-####
BLD-Energy code compliance9/5/20149/5/20149/8/2014PPASS
DetailsDave Hannah
Mark-would like as late as possible (after 2) iff possible or can you do Monday AM Phone #: ###-#### ext walls south and west parts of occ on first floor
BLD-Energy code compliance9/3/20149/4/20149/4/2014APART
DetailsDave Hannah
MJ Phone #: ###-#### ok to rock inside of west stair tower
BLD-Framing/Rough-in9/2/20149/3/20149/4/2014APART
DetailsDave Hannah
MJ Phone #: ###-#### ok to insulate framing west stair tower
BLD-Other8/13/20148/14/20148/15/2014PPART
DetailsDave Hannah
Exterior metal stud inspection please Phone #: ###-#### ok to cover ext
BLD-Framing/Rough-in7/29/20147/30/20147/31/2014PPART
DetailsDave Hannah
Partial framing for metal studs - MJ Phone #: ###-#### ok to cover the ne and sw ext high wall
BLD-Foundation3/17/20143/18/20143/18/2014APEND
DetailsDave Hannah
m.j. - partial - rebar Phone #: ###-#### ok after spec inspection sign off . stair tower and elev pit ftgs .
OVERRIDE  2/21/2014  
Issue PAID IN FULL permit  2/21/2014 DONE
DetailsChristina Prado
Print Occupancy Form  2/21/2014 DONE
DetailsChristina Prado
Place hold on job1/30/2014 2/21/2014 DONE
DetailsChristina Prado
Do not issue without BLD13-03348. Both ePlan permits on one set of plans
Permit Ready to Issue  2/21/2014 DONE
DetailsChristina Prado
Routing Off Site - STRUCTURAL1/30/2014 1/30/2014 PASS
DetailsAdele J Schaffeld-Griffin
I reviewed the final items requested from the structural engineer and feel they have adequately addressed the concerns.
PLANS/APPL TAKEN TO FRONT DESK  1/30/2014 DONE
Plan assigned to (AJS)12/3/2013 1/30/2014 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Due 12/31 30th & Main New BLDG
Routing Off Site - STRUCTURAL1/14/2014 1/23/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK1/14/2014 1/17/2014 PASS
DetailsAdele J Schaffeld-Griffin
off stite structural failed
Routing PW Environmental1/14/2014 1/14/2014 PASS
DetailsWalt Baumgartner
Mars Boss Amalgam Separator indicated
1st review completed  1/2/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK12/3/2013 1/2/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL12/3/2013 12/19/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Sewer Design12/3/2013 12/18/2013 PASS
DetailsKyle S. Rosenmeyer
Install 6" PVC WYE (Keynote 23) on private property. Service direction changes and branches not allowed within public R/W.
Routing PW Solid Waste12/3/2013 12/16/2013 PASS
DetailsPeter J. McCullough
signed off in e plan
Routing PW Environmental12/16/2013 12/16/2013 FAIL
DetailsWalt Baumgartner
Routing - FIRE12/12/201312/12/201312/13/2013 PASS
DetailsCraig D. Hanson
Routing - FIRE12/3/201312/3/201312/9/2013 FAIL
DetailsScott Arellano
Please see Fire Plan Report
Routing - PLUMBING12/3/2013 12/9/2013 PASS
DetailsDaryl Spivey
1. Tempered water required at public lavs.
2. Label all non potable water as required by ISPC.
3. Need to install a drain in Lab room to drain hot and cold RPBP's to.
Route to Impact Fee Review12/3/2013 12/6/2013 PASS
DetailsCindy M. Gould
Routing PW Drainage12/3/2013 12/6/2013 PASS
DetailsBrian Murphy
Routing PW Street Lights12/3/2013 12/5/2013 PASS
DetailsMike D Hedge
No street light requirement, contacted engineer to remove the four street ights shown on Main St. and he has removed them as of 12-13-13.
Routing PW Sewer Rating12/3/2013 12/4/2013 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment12/3/2013 12/4/2013 PASS
DetailsEvan Jenkins
Routing - Design Review12/3/2013 12/3/2013 PASS
DetailsAndrea Tuning
Routing - PLANNING Land Div12/3/2013 12/3/2013 PASS
DetailsDave Abo
Parcel with existing structure.
Routing - Addressing12/3/2013 12/3/2013 PASS
DetailsEmily Dixon
Project now on the corner of Whitewater Park Blvd and Main St.
Routing - PUBLIC WORKS12/3/2013 12/3/2013 PASS
DetailsBeverly Mountain
Intake Approval  12/3/2013 PASS
DetailsJohn Menard
Intake Approval  11/26/2013 FAIL
DetailsJohn Menard
1. The intake check list indicated that a soils report had been included; however, it does not appear that the soils report was uploaded. Please upload the required soils report.
2. The ESC narrative did not upload. Please upload the ESC narrative again.
3. Please upload a completed and signed Verification of Legal Lot form.
4. It appears that two building will be demolished and removed from this property. If the demo work is part of this permit, please include that information in the project description portion of the shell application.
5. It appears that this building will have more than one tenant. If that is correct, separate permits will be required. Please submit a permit application for the shell building portion of the project and a major tenant improvement permit application for the proposed tenant space. There should be a separate Certificate of Value for each application.
Intake Approval  11/26/2013 FAIL
DetailsJohn Menard
Because we can not issue a Certificate of Occupancy to a building that is not fully completed, we must issue separate permits to establish a letter of completion for the shell building and a Certificate of Occupancy for each separate tenant space. Please submit the separate permits and certificate of values originally requested.
Application received  11/25/2013 DONE
Application submitted via PDS Online on Nov 25 2013 11:21AM
Pending Assignment by JCM12/3/2013    
DetailsJohn Menard