Second Notice | | 3/13/2014 | 3/6/2014 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
First Notice | | 2/14/2014 | 3/3/2014 | | DONE |
Christina Prado
|
|
|
mailed 3/4/14
|
Permanent Occupancy | | | 2/5/2014 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/4/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 1/31/2014 | 2/3/2014 | 2/3/2014 | P | PASS |
Mike Jordan
|
|
|
Please Call Brian McCoy for Access Phone #: ###-#### >> Inspection requested via web by Brian McCoy. Ok for perm occ.
|
FIRE-Final Inspection | 1/31/2014 | 2/3/2014 | 2/3/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. No product was being stored on site at the time of the inspection.
|
FIRE-Final Inspection | 1/27/2014 | 1/27/2014 | 1/27/2014 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for corrections and their locations which include door hardware, fire extinguisher on mezzanine level and signage at the main exit door and the gas storage rooms.
|
BLD-Ceiling Grid Inspection | 1/20/2014 | 1/21/2014 | 1/21/2014 | A | PASS |
Jim Sly
|
|
|
Call Shawn for Access ###-#### Phone #: ###-#### >> Inspection requested via web by Brian McCoy
|
BLD-Energy code compliance | 1/2/2014 | 1/3/2014 | 1/3/2014 | A | PASS |
Mike Jordan
|
|
|
Shawn Phone #: ###-####
|
BLD-Framing/Rough-in | 12/30/2013 | 12/30/2013 | 12/30/2013 | P | PASS |
Jim Storey
|
|
|
Please contact Shawn for access ###-#### Phone #: ###-#### >> Inspection requested via web by Brian McCoy
|
Issue PAID IN FULL permit | | | 12/13/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 12/12/2013 | | DONE |
Tisha Gallop
|
|
|
spoke to Glen Walker and told him permit is ready, fee due and need GC.
|
Permit Ready to Issue | | | 12/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 11/25/2013 | 11/25/2013 | 12/11/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 12/9/2013 | | 12/11/2013 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 12/11/2013 | | DONE |
|
|
|
|
Routing - PLANNING | 12/11/2013 | | 12/11/2013 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 12/11/2013 | | 12/11/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/11/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 12/9/2013 | 12/9/2013 | 12/9/2013 | | PASS |
Craig D. Hanson
|
|
|
See Fire Report Revision 1
|
Plan resubmittals received | | | 12/6/2013 | | DONE |
Tisha Gallop
|
|
|
received response, United Water flow sheet, memo from Rotech Healthcare, two copies of plan sheets G-001, A-111, A-141; taken to Carl Madsen.
|
Routing - FIRE | 12/2/2013 | 12/2/2013 | 12/3/2013 | | FAIL |
Craig D. Hanson
|
|
|
Please see Fire Plan Review
|
1st review completed | | | 12/3/2013 | | FAIL |
|
|
|
Failed Plan Check, Fire
|
Routing - PLAN CHECK | 11/25/2013 | | 12/2/2013 | | FAIL |
Carl D Madsen
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/25/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 11/25/2013 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/25/2013 | | DONE |
Christina Prado
|
|
|
|