Permanent Occupancy | | | 1/3/2014 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 12/31/2013 | 1/2/2014 | 1/2/2014 | P | PEND |
Mike Jordan
|
|
|
Hal Zimmerman Phone #: ###-####. Will be ok for perm occ. once mech. has finaled.
|
FIRE-Final Inspection | 12/31/2013 | 1/2/2014 | 1/2/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per Mary with Taylor Brothers the hood suppression sytem is fine as is with the new equipment. Also per Tim Woodard the key locking hardware on the main exit is ok as well. (plans show panic)
|
FIRE-Final Inspection | 12/6/2013 | 12/30/2013 | 12/30/2013 | A | FAIL |
Troy Cobbley
|
|
|
Mount the fire extinguishers, provide re-certificaiton for the hood suppression system due to new equipment, repair the emergency light at the restrooms, provide occupant load sign, provide panic hardware at the south exit per the approved plans.
|
Telephone call | | | 12/6/2013 | | DONE |
Christina Prado
|
|
|
Called Justin to advise permit is ready for pick up
|
Permit Ready to Issue | | | 12/6/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 12/6/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 12/6/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 12/5/2013 | | 12/5/2013 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 12/5/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 11/26/2013 | | 12/5/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 12/2/2013 | | 12/3/2013 | | FAIL |
Tim L. Woodard
|
|
|
Waiting on CDH approval. TLW
|
1st review completed | | | 12/3/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 11/26/2013 | | 11/29/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 11/29/2013 | | 11/29/2013 | | PASS |
Walt Baumgartner
|
|
|
existing grease interceptor on site
|
Routing PW Sewer Rating | 11/29/2013 | | 11/29/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 11/27/2013 | | 11/27/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Application received | | 11/26/2013 | 11/26/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/26/2013 | | DONE |
Barbara Stitt
|
|
|
|
Receive PAYMENT IN FULL | | | 11/26/2013 | | DONE |
Barbara Stitt
|
|
|
|
First Notice | | 1/13/2014 | | | |
|
|
|
|