Permit Information
Permit NumberBLD13-03318
StatusFinaled
Name PRESTIGE HOMES INC
Site Address 699 N MITCHELL ST
Project NameHORIZON PARK APARTMENTS
Customer Number 
ePlanReviewNo
Description
Horizon Park - Eight Unit Apartment Building (First floor apt. #s 101,102,103,104, Second floor #s 201,202,203,204). Permit for the construction of a new 2 story, 8 unit apartment building per the approved plans. The building has 4,800 sq. ft. per story including common areas with 4 apartments on each story. This building is fully fire sprinklered per residential occupancy requirements and shall comply with NFPA13 as regulated by the Fire Department. CDM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  7/20/2015 DONE
BLD-Final7/13/20157/14/20157/14/2015PPASS
DetailsMike Jordan
Please call in advance of arrival. Thanks! Phone #: ###-#### Inspection requested via web by Scott Zierler. ok for perm occ.
BLD-Final7/13/20157/14/20157/13/2015ACANC
DetailsMike Jordan
Please call when heading over. Thanks! Phone #: ###-#### >> Inspection requested via web by Scott Zierler Inspection cancelled from web by: Scott Zierler
FIRE-Final Inspection6/29/20156/30/20156/30/2015APASS
DetailsTroy Cobbley
Life safety passed. Knox box is on site but not installed. Contractor is waiting for the fire dept to locate
Zoning Approval6/30/20156/30/20156/30/2015 PASS
DetailsJosh Wilson
FIRE-Conference6/10/20156/11/20156/11/2015PDONE
DetailsTroy Cobbley
I met with Scott regarding what is required for the fire final. Items include alarm bell, fire alarm system, address...ect
BLD-Conference6/4/20156/5/20156/5/2015PDONE
DetailsMike Jordan
Need to review items from previous inspection. 10 minutes max, Thanks
Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Final5/12/20155/13/20155/13/2015ANR
DetailsMike Jordan
Call when on your way. Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Other10/29/201410/30/201410/30/2014PPASS
DetailsJim Sly
Inspection of RC1 Hat Channel on ceiling of main floor. Thanks! Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Framing/Rough-in10/22/201410/22/201410/22/2014PPASS
DetailsMike Jordan
Thanks! Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Energy code compliance10/22/201410/22/201410/22/2014PPASS
DetailsMike Jordan
Thanks! Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Conference10/10/201410/13/201410/13/2014APASS
DetailsMike Jordan
Check penetrations. Phone #: ###-#### Inspection requested via web by Scott Zierler. Ok to insulate exterior walls only.
BLD-Conference10/8/201410/9/201410/9/2014ANR
DetailsMike Jordan
Review fire collars, fire pillows, etc. Need to see about getting approval to insulate exterior walls. Waiting on fire rough-in inspection tomorrow, but need to get walls insulated so stucco guys can continue. Thanks
Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Conference10/1/201410/1/201410/1/2014PDONE
DetailsMike Jordan
Review of riser room and questions about fire rating. Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Conference9/25/20149/25/20149/25/2014PDONE
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Framing/Rough-in9/18/20149/22/20149/22/2014PCANC
DetailsMike Jordan
Please call when on your way. Thanks. Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Conference9/22/20149/22/20149/22/2014PDONE
DetailsMike Jordan
Please call when on your way. Thanks. Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Wall Bracing8/21/20148/21/20148/21/2014PPASS
DetailsPhil Shearer
Thanks! Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Wall Bracing8/13/20148/13/20148/13/2014PPART
DetailsMike Jordan
Plans are in the green box across the parking lot outside the building. Thx. Phone #: ###-#### Inspection requested via web by Scott Zierler. Provide staple conversion, install floor to floor straps.
BLD-Conference8/13/20148/13/20148/13/2014PPASS
DetailsMike Jordan
Upstairs common wall insulation inspection. Phone #: ###-#### Inspection requested via web by Scott Zierler
BLD-Conference7/16/20147/16/20147/16/2014PPASS
DetailsMike Jordan
Thanks. Phone #: ###-#### Inspection requested via web by Scott Zierler. Party walls, 1st. floor ok.
BLD-Conference7/10/20147/11/20147/11/2014PDONE
DetailsMike Jordan
Will call if not ready. Phone #: ###-#### Inspection requested via web by Scott Zierler. Interior fire partions still not continous at jogs. Contractor to repair.
BLD-Conference7/9/20147/10/20147/10/2014APART
DetailsMike Jordan
Insulation inspection. Please call. Phone #: ###-#### Inspection requested via web by Scott Zierler. Party wall rating is incomplete. Cintractor to repair and recall for inspection.
BLD-Footing5/29/20145/30/20145/30/2014APASS
DetailsMike Jordan
Juron Phone #: ###-####
BLD-Conference5/20/20145/22/20145/22/2014ACANC
DetailsMike Jordan
Pre-Excavation Site inspection Phone #: ###-#### >> Inspection requested via web by Scott Zierler Inspection cancelled from web by: Scott Zierler
OVERRIDE  5/12/2014  
Telephone call  5/12/2014 DONE
DetailsBarbara Stitt
Called Scott and told him that permit is ready, fees due and need GC info on 5-12-14 @ 8:45am
Issue PAID IN FULL permit  5/12/2014 DONE
DetailsBarbara Stitt
Permit Ready to Issue  5/12/2014 DONE
DetailsBarbara Stitt
Route to Impact Fee Review5/7/20145/7/20145/9/2014 PASS
DetailsCindy M. Gould
PLANS/APPL TAKEN TO FRONT DESK  5/7/2014 DONE
Print Occupancy Form  5/7/2014 DONE
DetailsTisha Gallop
Routing - MECHANICAL4/25/2014 5/7/2014 PASS
DetailsTroy James
Plan assigned to (CDM)12/3/2013 5/7/2014 PASS
DetailsCarl D Madsen
First review completed
Routing - Addressing5/6/2014 5/6/2014 PASS
DetailsJason C. Taylor
Routing - PLAN CHECK4/23/2014 5/6/2014 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL4/25/2014 5/6/2014 PASS
DetailsCarl D Madsen
Received letter from consulting engineer.
Routing - PLANNING5/5/2014 5/5/2014 PASS
DetailsJosh Wilson
Plan resubmittals received  4/30/2014 DONE
rec'd 3 copies of sheets A-4; A-5; A-6; A-7; A-8 - taken to CDM
Routing - PLUMBING4/25/2014 4/30/2014 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - FIRE4/25/20144/25/20144/25/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review 04-25-14
Telephone call  4/25/2014 DONE
DetailsChristina Prado
Called Action Couriers for pick up
Plan resubmittals received  4/25/2014  
Received 3 copies of structure calcs from Wolfe Engineering, 6 copies of sheet A-4, A-7, A-8 and 3 copies of sheet A-6, then taken to Carl Madsen's desk
Routing PW Sewer Design4/22/2014 4/23/2014 PASS
DetailsKyle S. Rosenmeyer
Routing - PUBLIC WORKS4/21/2014 4/23/2014 PASS
DetailsConnie Baumgartner
Routing Off Site - STRUCTURAL4/11/2014 4/22/2014 FAIL
DetailsCarl D Madsen
Received comments and forwarded to Scott and Lynn.
Routing PW Drainage4/21/2014 4/22/2014 PASS
DetailsBrian Murphy
Telephone call  4/11/2014 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Plan resubmittals received  4/10/2014 DONE
DetailsChristina Prado
Received one set of revised plan sheets marked A-4, A-5, A-6 & A-7 as well as one set of revised structual calcs;Taken to Carl Madesn for further review
Plan resubmittals received  4/8/2014 DONE
rec. 2 copies of full sets of plans, 2 copies of eng calcs and drawings, 5 copies of civil-taken to cdm
Meeting  4/4/2014 DONE
Meet with Scott (builder) looked at the street access and other items on my fire plan report of 01-13-14. Street access and turning radius issues resolved. hammer head issue also resolved. area is existing since 1999. he will put on site plan fire sprinkler feed lines when he resubmits.CDH 04-04-14
Routing - PUBLIC WORKS2/14/2014 2/21/2014 FAIL
DetailsConnie Baumgartner
Failed by Brian Murphy and Kyle Rosenmeyer
Routing PW Drainage2/18/2014 2/20/2014 FAIL
DetailsBrian Murphy
NEED MORE INFO FROM ARCHITECT LEFT MESSAGE
Routing PW Sewer Design2/14/2014 2/18/2014 FAIL
DetailsKyle S. Rosenmeyer
Point of connection to city sewer not shown/not clear. Contacted architect 2/18.
Routing - FIRE2/13/20142/13/20142/13/2014 FAIL
DetailsCraig D. Hanson
See Fire Plans Review Rev 1 02-13-14
Routing - PLAN CHECK1/13/2014 2/13/2014 FAIL
DetailsCarl D Madsen
Plan resubmittals received  2/3/2014 DONE
DetailsChristina Prado
received one response letter, two revised sets of manual Js, two sets of structural calcs as well as two full sets of plans marked C-1, C-2, C-3, A-1. L-1, A-2, A-3, A-4, A-5, A-6, A-7, A-8, A-9, A-10, E-1, E-2, P-1, P-2, P-3, S-1, S-2 & S-3; Taken to Carl Madsen for further review
Routing - FIRE12/3/201312/3/20131/13/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 01-13-14
1st review completed  1/13/2014 FAIL
Failed: Fire, PW, Plan Check, Mechanical, Plumbing, Sewer, Addressing
Routing - PLAN CHECK12/26/2013 1/10/2014 FAIL
DetailsCarl D Madsen
Carl Madsen
Plan resubmittals received  12/27/2013  
Received 5 copies of sheet C2 of 2 and taken to add into plans on Carl's desk
Routing - PLANNING12/24/2013 12/26/2013 PASS
DetailsJosh Wilson
DRH13-00331-Josh Wilson
Routing - MECHANICAL12/23/2013 12/24/2013 FAIL
DetailsTroy James
emailed correction to Prestige homes
Routing - PLUMBING12/18/2013 12/23/2013 FAIL
DetailsDaryl Spivey
1. Provide complete plumbing plan with water sizing and waste and vent piping sized and plumbed as required by ISPC.
2. Provide DCVA on water service on each address.
Routing - Erosion and Sediment12/16/2013 12/18/2013 PASS
DetailsAndy J. Long
ESC plan waiver submitted and approved. Valid RP provided.
Routing - PUBLIC WORKS12/3/2013 12/16/2013 FAIL
DetailsConnie Baumgartner
see bld13-03319 for comments
Routing PW Solid Waste12/9/2013 12/9/2013 PASS
DetailsPeter J. McCullough
Existing enclosure, service level will need to be increased.
Routing PW Sewer Design12/4/2013 12/9/2013 FAIL
DetailsKyle S. Rosenmeyer
Need to show point of connection to Boise City Sewer.
Routing - Addressing12/4/2013 12/4/2013 FAIL
DetailsJason C. Taylor
Apartment numbers need to be assigned. Called applicant - messagees not returned. Jason Taylor ###-####
Routing PW Sewer Rating12/4/2013 12/4/2013 PASS
DetailsConnie Baumgartner
Plan resubmittals received  12/4/2013  
Received 3 sets of structural cals and 6 copies of sheet A-4 and taken to add to routing permit
Routing - PLANNING Land Div12/3/2013 12/3/2013 PASS
DetailsDave Abo
Lot 3, Block 1, McMonigle Subdivision
Application received 12/2/201312/2/2013 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  12/2/2013 DONE
DetailsBarbara Stitt
Recd Pcfee & Taken To Pln CK  12/2/2013 DONE
DetailsBarbara Stitt
Intake Approval  12/2/2013 PASS
DetailsTim L. Woodard
First Notice 7/30/2015   
Pending Assignment by JCB12/2/2013    
DetailsJohn Menard
Routing PW Drainage12/9/2013   FAIL
DetailsBrian Murphy
NEED SAND WINDOW IN SWALE OTHER PREVIOUSLY APPROVED DETAILS