Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD13-03348
StatusFinaled
Name GUHO CORP
Site Address 3003 W MAIN ST Unit: 130
Project Name30th + Main
Customer NumberREF BLD13-03291
ePlanReviewNo
Description
(Whitewater Oral Surgery)(Suite 130)(Core and shell permit BLD13-03291) Permit for Ambulatory Health Care occupancy. Tenant space will be 7,205 sq ft. Core and shell permit BLD13-03291. Scope of work will include nonbearing walls to create-waiting area, reception, admin work area, break room, work room, janitors closet, 2 ADA restrooms for staff with ADA compliant showers, utility room, pre-op, recovery, 5 procedure rooms, med gas room, 1 office, 6 exam rooms, 1 x-ray room, 1 conference room. 2 ADA restrooms for general use as shown on approved plans. The fire alarm and fire sprinkler systems shall meet IBC 422.5 and 422.6. The size of the occupancy does not require smoke barriers. Suspended ceilings and hard lids as per approved plans. Interior finish shall meet the requirements of chapter 8, IBC. Med gas room is separated with 1 hour rated construction as shown on approved plans. Plumbing, mechanical and electrical as per approved plans. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 7/18/20158/5/2015 DONE
This permit finaled on the web by Lisa Owen
Third Notice 6/14/20157/13/2015 DONE
Third Notice 5/10/20156/9/2015 DONE
Third Notice 3/8/20155/5/2015 DONE
Second Notice 2/12/20153/3/2015 DONE
mailed 3-3-15
First Notice 1/16/20152/2/2015 DONE
DetailsCandy A. Nichols
put in mail 2/2/15
BLD-Final1/2/20151/5/20151/6/2015PPASS
DetailsDave Hannah
MJ Phone #: ###-####
Permanent Occupancy  1/6/2015 DONE
FIRE-Final Inspection1/2/20151/5/20151/5/2015APASS
DetailsForrest France
Fire life safety inspection completed and passed.
FIRE-Final Inspection12/31/20141/2/20151/2/2015PCANC
DetailsForrest France
Bill ###-####
BLD-Final12/31/20141/2/20151/2/2015PCANC
DetailsDave Hannah
Bill ###-####
FIRE-Final Inspection12/30/201412/31/201412/31/2014APART
DetailsForrest France
TCO approved pending trade related fire alarm permit work.
BLD-Final12/30/201412/31/201412/31/2014PPART
DetailsDave Hannah
MJ Phone #: ###-#### ok for temp occ
FIRE-Final Inspection12/29/201412/30/201412/30/2014ANR
DetailsForrest France
Pending trade related FIR permit work.
BLD-Final12/29/201412/30/201412/30/2014PCANC
DetailsDave Hannah
MJ Phone #: ###-####
FIRE-Final Inspection12/23/201412/23/201412/26/2014PNR
DetailsForrest France
Bill Phone #: ###-####
BLD-Ceiling Grid Inspection11/12/201411/12/201411/12/2014PPART
DetailsDave Hannah
Bill Phone #: ###-#### west side ok
Place hold on job1/30/2014 2/21/2014 DONE
DetailsChristina Prado
Do not issue without BLD13-03291. Both ePlan permits on one set of plans
Permit Ready to Issue  2/21/2014 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  2/21/2014 DONE
DetailsChristina Prado
Print Occupancy Form  2/21/2014 DONE
DetailsChristina Prado
Plan assigned to (AJS)12/3/2013 1/30/2014 PASS
DetailsAdele J Schaffeld-Griffin
1ST REVIEW COMPLETEDDue 12/31 L-3 Whitewater Oral Surgery
PLANS/APPL TAKEN TO FRONT DESK  1/30/2014 DONE
Routing - PLAN CHECK1/14/2014 1/17/2014 PASS
DetailsAdele J Schaffeld-Griffin
Routing PW Environmental1/15/2014 1/15/2014 PASS
DetailsWalt Baumgartner
Application received 12/3/20131/14/2014 DONE
Routing - FIRE12/3/201312/3/20131/3/2014 PASS
DetailsCraig D. Hanson
Please refer to Fire Plan Report
Routing - PLAN CHECK12/3/2013 1/3/2014 FAIL
DetailsAdele J Schaffeld-Griffin
see change marks in e plan
1st review completed  1/2/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Sewer Design12/16/2013 12/18/2013 PASS
DetailsKyle S. Rosenmeyer
Routing PW Solid Waste12/16/2013 12/16/2013 PASS
DetailsPeter J. McCullough
Routing PW Environmental12/16/2013 12/16/2013 FAIL
DetailsWalt Baumgartner
See plan sheet 5.11 med gas plumb plan - Amalgam separator meeting ISO certification prior to vacuum system
Routing PW Sewer Rating12/16/2013 12/16/2013 PASS
DetailsConnie Baumgartner
Routing PW Drainage12/16/2013 12/16/2013 PASS
DetailsBrian Murphy
Routing PW Street Lights12/16/2013 12/16/2013 PASS
Details
No street light requirement
Routing - PLUMBING12/3/2013 12/9/2013 PASS
DetailsDaryl Spivey
1. Tempered water required at public lavs.
2. Label all non potable water as required bym ISPC.
3. Install a drain in Lab room to drain hot and cold RPBP's to.
Route to Impact Fee Review12/3/2013 12/6/2013 PASS
DetailsCindy M. Gould
Tenant improvement no impact fees
Routing - Addressing12/4/2013 12/4/2013 PASS
DetailsEmily Dixon
Suite number is 130.
Pending Assignment by JCM12/3/2013    
DetailsJohn Menard