BLD-Final | 5/29/2014 | 5/29/2014 | 5/29/2014 | P | PASS |
Mike Jordan
|
|
|
Please call brian prior to inspection Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
DOC - Permit Finaled | 5/29/2014 | 5/29/2014 | 5/29/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 5/29/2014 | 5/29/2014 | 5/29/2014 | P | DONE |
Mike Jordan
|
|
|
5
|
BLD-Wall cover | 5/2/2014 | 5/5/2014 | 5/5/2014 | P | PASS |
Mike Jordan
|
|
|
East eave firewall assembly. Phone #: ###-#### >> Inspection requested via web by Brian Stark. double layer 5/8 type x rock on soffit ok.
|
BLD-Energy code compliance | 4/8/2014 | 4/9/2014 | 4/9/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Framing/Rough-in | 4/4/2014 | 4/7/2014 | 4/7/2014 | A | PART |
Mike Jordan
|
|
|
Needs to sweep all hard surfaces of silts and pick up all construction debries. RP was notied.
|
BLD-Wall Bracing | 2/23/2014 | 2/24/2014 | 2/24/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 2/13/2014 | 2/14/2014 | 2/14/2014 | P | CANC |
Mike Jordan
|
|
|
Upper floor nailing...ready between 1 and 3 pm Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 2/4/2014 | 2/6/2014 | 2/5/2014 | A | CANC |
Mike Jordan
|
|
|
Shear wall fastening on 2nd story walls. Please inspect between 9-10 am Phone #: ###-#### >> Inspection requested via web by Brian Stark Inspection cancelled from web by: Brian Stark
|
BLD-Footing | 1/30/2014 | 1/31/2014 | 1/31/2014 | A | PASS |
Mike Jordan
|
|
|
chad Phone #: ###-####
|
BLD-Energy code compliance | 1/17/2014 | 1/21/2014 | 1/21/2014 | A | PART |
Jim Sly
|
|
|
steve Phone #: ###-#### Foundation
|
BLD-Foundation | 1/13/2014 | 1/13/2014 | 1/13/2014 | P | PASS |
Mike Jordan
|
|
|
Ron Phone #: ###-####
|
BLD-Footing | 1/8/2014 | 1/9/2014 | 1/9/2014 | P | PART |
Mike Jordan
|
|
|
Heron Phone #: ###-####
|
BLD-Footing | 1/8/2014 | 1/9/2014 | 1/9/2014 | A | CANC |
Mike Jordan
|
|
|
Please call Jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
Issue PAID IN FULL permit | | | 12/20/2013 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 12/13/2013 | | |
|
|
|
|
Telephone call | | | 12/13/2013 | | DONE |
Tisha Gallop
|
|
|
called James and told him permit is ready, fee due and RP expires 12/21/13
|
Inspection Record Card- Bld | | | 12/13/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/13/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (JG) | 12/5/2013 | 12/5/2013 | 12/12/2013 | | PASS |
Javier Guzman
|
|
|
Due 12/17 L1
|
Routing - PLAN CHECK | 12/10/2013 | | 12/12/2013 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | | | 12/12/2013 | | PASS |
Connie Baumgartner
|
|
|
|
1st review completed | | | 12/12/2013 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 12/12/2013 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/12/2013 | | DONE |
|
|
|
|
Routing - MECHANICAL | 12/11/2013 | | 12/11/2013 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 12/9/2013 | | 12/10/2013 | | FAIL |
Troy James
|
|
|
emailded corrections to Canfield, dustin mori
|
Routing - PLANNING | 12/9/2013 | | 12/9/2013 | | PASS |
Sue Cummings
|
|
|
|
Route to Impact Fee Review | 12/5/2013 | 12/8/2013 | 12/6/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 12/4/2013 | 12/8/2013 | 12/6/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 12/5/2013 | | 12/6/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Application received | | 12/4/2013 | 12/4/2013 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/4/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/4/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 12/4/2013 | | PASS |
Barbara Stitt
|
|
|
|