BLD-Final | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
DOC - Permit Finaled | 7/25/2014 | 7/25/2014 | 7/25/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 7/25/2014 | 7/25/2014 | 7/25/2014 | P | DONE |
Mike Jordan
|
|
|
4
|
BLD-Wall cover | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Wall cover | 6/2/2014 | 6/3/2014 | 6/3/2014 | P | FAIL |
Mike Jordan
|
|
|
Fire and sheetrock shear fastening Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Energy code compliance | 5/20/2014 | 5/22/2014 | 5/22/2014 | P | PASS |
Mike Jordan
|
|
|
BLD-COM/RES INSPECTOR
|
BLD-Framing/Rough-in | 5/22/2014 | 5/22/2014 | 5/22/2014 | P | PASS |
Mike Jordan
|
|
|
BLD-COM/RES INSPECTOR
|
BLD-Framing/Rough-in | 5/19/2014 | 5/20/2014 | 5/20/2014 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark. Nail off top chord of 3ply truss in garage as per engineering. Box out electrical ground at 1hr. firewall with 5/8 type x rock.
|
BLD-Wall Bracing | 4/14/2014 | 4/14/2014 | 4/14/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Footing | 3/20/2014 | 3/21/2014 | 3/21/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin. interior thickend footings.
|
BLD-Energy code compliance | 2/13/2014 | 2/13/2014 | 2/13/2014 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Foundation | 2/6/2014 | 2/6/2014 | 2/6/2014 | P | PASS |
Mike Jordan
|
|
|
Heron Phone #: ###-####
|
BLD-Footing | 2/3/2014 | 2/3/2014 | 2/3/2014 | P | PASS |
Mike Jordan
|
|
|
Heron Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/20/2013 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 12/16/2013 | | |
|
|
|
|
Plan assigned to (JG) | 12/5/2013 | 12/5/2013 | 12/16/2013 | | PASS |
Javier Guzman
|
|
|
Due 12/17 L1
|
Routing - PLAN CHECK | 12/12/2013 | | 12/16/2013 | | PASS |
Javier Guzman
|
|
|
Javier Guzman
|
1st review completed | | | 12/16/2013 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 12/16/2013 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/16/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/16/2013 | | DONE |
|
|
|
|
Telephone call | | | 12/16/2013 | | DONE |
Christina Prado
|
|
|
called Jim to advise permit is ready and gave fees due. ALso advised of upcoming RP expiration
|
Permit Ready to Issue | | | 12/16/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - MECHANICAL | 12/9/2013 | | 12/12/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/9/2013 | | 12/9/2013 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | 12/9/2013 | | 12/9/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Route to Impact Fee Review | 12/5/2013 | 12/8/2013 | 12/6/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 12/4/2013 | 12/8/2013 | 12/6/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 12/5/2013 | | 12/6/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Application received | | 12/4/2013 | 12/4/2013 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/4/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/4/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 12/4/2013 | | PASS |
Barbara Stitt
|
|
|
|