Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberBLD13-03369
StatusFinaled
Name BENITON CONSTRUCTION
Site Address 8055 W GODDARD RD
Project NameCAPITAL HIGH SCHOOL
Customer Number 
ePlanReviewNo
Description
(CAPITAL HIGH SCHOOL – Locker Room Remodel – Sprinkler / Lighting / Seismic Upgrade) Permit is to remodel the boys and girls locker rooms to be fully accessible, upgrade the lighting and add sprinklers to all first floor classrooms, seismically upgrade the classroom walls, and upgrade one home economics kitchen to be accessible. This building is partially fire sprinklered there is an informal upgrade agreement outline attached to this permit to show the intent to have the building fully spinklered in phases over the next 5 years. Approval contingent upon adhering to the approved plans on file. Work to include: demolition of non-combustible full height partition walls, and installation of new non-combustible full height partition walls, new lighting / switching, new accessible doors / hardware, installation of new plumbing fixtures, installation of new seismic bracing, installation of new mechanical units, construction of structural bracing to transfer new mechanical units to lower roof deck, and finishes in compliance with chapter 8 of the 2009 IBC. This building is partial Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  12/29/2015 DONE
BLD-Final8/21/20148/22/20148/22/2014APASS
DetailsJim Sly
Ed Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection8/22/20148/22/20148/22/2014PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection8/21/20148/21/20148/21/2014PFAIL
DetailsTroy Cobbley
Need the project related fire alarm permit addressed and the exit signs and emergency lights added as per the Review Comments.
BLD-Ceiling Grid Inspection7/31/20148/1/20148/1/2014APART
DetailsJim Sly
Ed Phone #: ###-####
B hall OK.
BLD-Ceiling Grid Inspection7/23/20147/23/20147/23/2014PPART
DetailsJim Sly
Ed Cuttlers Phone #: ###-####
Select ceilings
FIRE-Conference7/22/20147/22/20147/23/2014PDONE
DetailsTroy Cobbley
Matt Forester Phone #: ###-####

Per discussion with Tim Frost and Romeo Gervais the "end gap" of the new ceiling assemble at the windows will be allowed without a requirement to "box-in" the ends.

Per conversation with Romeo Gervais the limited existing ceiling tile, installed above the conduit and wire mold, will be allowed to remain.
BLD-Framing/Rough-in7/21/20147/21/20147/21/2014PPASS
DetailsMike Jordan
Above ceiling inspection please Phone #: ###-####. Girls east shower and boys shower, girls west ADA shower ok.
BLD-Conference7/9/20147/10/20147/10/2014ADONE
DetailsJim Sly
Ed Phone #: ###-####
Walk thru done.
Issue PAID IN FULL permit  2/11/2014 DONE
OVERRIDE  1/14/2014  
Print Occupancy Form  1/14/2014 DONE
DetailsBarbara Stitt
Telephone call  1/14/2014 DONE
DetailsChristina Prado
Called Scott to advise permit is ready pending GC and gave fees due
Permit Ready to Issue  1/14/2014 DONE
DetailsChristina Prado
Routing - FIRE1/10/2014 1/13/2014 PASS
DetailsCraig D. Hanson
Please see Final Fire Plan Report
Routing - PLAN CHECK1/13/2014 1/13/2014 PASS
DetailsTim L. Woodard
Routing - Erosion and Sediment1/13/2014 1/13/2014 PASS
DetailsAndy J. Long
ESC plan waivers submitted and approved.
PLANS/APPL TAKEN TO FRONT DESK  1/13/2014 DONE
DetailsTim L. Woodard
Case Summary (BLD)  1/13/2014 DONE
DetailsTim L. Woodard
Plan assigned to (TLW)12/5/2013 1/13/2014 PASS
DetailsTim L. Woodard
Routing - MECHANICAL1/9/2014 1/10/2014 PASS
DetailsTroy James
Routing - PLAN CHECK12/23/2013 1/9/2014 PASS
DetailsTim L. Woodard
Resubs approved. TLW
Plan resubmittals received  1/7/2014  
1-7-14 received 1 transmittal letter, 1 esc letter,1 fire response,1 mechanical response,1 bld response & 2 copies of sheets A0.1,A0.2,A2.0,A2.1,A5.0,M3.2 inserted by Shawn Mcclure and taken back to Tim W.
1st review completed  12/23/2013 FAIL
Failed, Errosion Control, Mechanical, Fire.
Routing - FIRE12/20/2013 12/23/2013 FAIL
DetailsCraig D. Hanson
Please see Fire Plan Report
Routing - ELECTRICAL12/20/2013 12/23/2013 PASS
DetailsDoug A Poedy
Took plans from Fire to Doug. He reviewed them then redelivered to Fire for Fire Review to be completed. Doug indicated on the sign-off that he has approved the plans. TLW
Routing - MECHANICAL12/19/2013 12/20/2013 FAIL
DetailsTroy James
emailed corrections to architect.
Routing - PLAN CHECK12/19/2013 12/19/2013 FAIL
DetailsTim L. Woodard
Intercepted plans from Electrical to complete my review. TLW
Routing - PLUMBING12/9/2013 12/9/2013 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing PW Sewer Rating12/6/2013 12/9/2013 PASS
DetailsConnie Baumgartner
Routing - PUBLIC WORKS12/6/2013 12/9/2013 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment12/6/2013 12/9/2013 FAIL
DetailsAndy J. Long
Scope of interior demolition/renovation as described makes this project moderate risk. Need to provide ESC plan waiver and ESC permit application with designated Responsible Person
Routing - Addressing12/5/2013 12/6/2013 PASS
DetailsJason C. Taylor
Application received 12/5/201312/5/2013 DONE
DetailsDarla L Downs
Plans ACCEPTED BY PLAN TECH  12/5/2013 DONE
DetailsChristina Prado
Intake Approval  12/5/2013 PASS
DetailsTim L. Woodard
Recd Pcfee & Taken To Pln CK  12/5/2013 DONE
DetailsChristina Prado