First Notice | | 11/17/2014 | 11/7/2014 | | DONE |
|
|
|
This permit finaled on the web by Blair Oram
|
Permanent Occupancy | | | 11/7/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 11/4/2014 | 11/6/2014 | 11/6/2014 | A | PASS |
Phil Shearer
|
|
|
request early as poss // Chris Phone #: ###-####
|
BLD-Final | 10/31/2014 | 11/3/2014 | 11/3/2014 | A | NR |
Phil Shearer
|
|
|
Blair// please call before- needs an hour notice Phone #: ###-####
|
FIRE-Final Inspection | 10/31/2014 | 10/31/2014 | 10/31/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Zoning Approval | 9/9/2014 | 9/9/2014 | 9/9/2014 | | PASS |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 9/5/2014 | 9/8/2014 | 9/8/2014 | A | FAIL |
Troy Cobbley
|
|
|
All emergency lights and exit signs repaired. Life safety ok to final when the project related fire alarm system has corrections made
|
BLD-Final | 9/5/2014 | 9/8/2014 | 9/8/2014 | A | NR |
Dave Hannah
|
|
|
Before 11:30 - Blair Phone #: ###-####
|
FIRE-Final Inspection | 9/2/2014 | 9/3/2014 | 9/3/2014 | P | FAIL |
Troy Cobbley
|
|
|
Need all exit signs and emergency lighting repaired. Need the project related fire alarm permit addressed.
|
BLD-Energy code compliance | 6/20/2014 | 6/23/2014 | 6/23/2014 | A | PASS |
Tom Arcoraci
|
|
|
marvin Phone #: ###-####
|
BLD-Framing/Rough-in | 6/19/2014 | 6/20/2014 | 6/20/2014 | P | PART |
Tony Young
|
|
|
marvin Phone #: ###-####,, front entry,, needs fireblocks at the ceiling lines,, ok to insulate
|
BLD-Ceiling Grid Inspection | 6/2/2014 | 6/2/2014 | 6/2/2014 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 5/22/2014 | 5/22/2014 | 5/22/2014 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 5/21/2014 | 5/22/2014 | 5/22/2014 | A | PASS |
Tom Arcoraci
|
|
|
Marvin-late PM if possible Phone #: ###-####
|
BLD-Framing/Rough-in | 5/21/2014 | 5/22/2014 | 5/22/2014 | A | PASS |
Tom Arcoraci
|
|
|
marvin Phone #: ###-#### wip ok
|
BLD-Ceiling Grid Inspection | 5/7/2014 | 5/7/2014 | 5/7/2014 | P | PASS |
Tom Arcoraci
|
|
|
Marvin Phone #: ###-####
|
BLD-Framing/Rough-in | 5/1/2014 | 5/2/2014 | 5/2/2014 | A | PASS |
Tom Arcoraci
|
|
|
Marvin-Mid am please Phone #: ###-#### wip ok roof para
|
BLD-Framing/Rough-in | 4/16/2014 | 4/17/2014 | 4/17/2014 | A | PASS |
Tom Arcoraci
|
|
|
Marvin Phone #: ###-#### wip ok south rough framing ok 408
|
BLD-Framing/Rough-in | 4/7/2014 | 4/8/2014 | 4/8/2014 | P | PART |
Tom Arcoraci
|
|
|
Early afternoon - Marvin Phone #: ###-#### HDs ok
|
OVERRIDE | | | 3/26/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/26/2014 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 3/26/2014 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 3/26/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 3/25/2014 | | 3/25/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2014 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 1/23/2014 | | 3/25/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 2/19 -Outback
|
Routing - Design Review | 3/17/2014 | | 3/21/2014 | | PASS |
Josh Wilson
|
|
|
REdlines sheet L1.0 existing parking lot trees to remain.
|
Routing - PLAN CHECK | 3/17/2014 | | 3/21/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
email sent 3/21/14
Mike, I have completed the building plan review and there are still a few outstanding items from the previous review that have not been addressed.
-The main door hardware is required to be panic as to occupant load for the building is over 300. ON sheet A2.2 you list the hardware group as Set #1. In this group it list, deadbolt, and signage over the door. Neither are allowed per code for this project.
-The request for the com check for the vestibule envelope have not yet been submitted. Please submit.
If you would like to have to contractor arrange a meeting on Monday we can issue an “Early Start Permit” This will allow the contractor to begin work up to a point in construction of allowing items to be covered. There is a fee for the early start of $46.31.
Please contact Tim Woodard at ###-#### to set up meeting.
As soon as I receive the plans with the corrected information I will be able to issue the building permit.
Thank you
Adele Schaffeld-Griffin
Plans Examiner II
City of Boise PDS
###-####
|
Routing - PUBLIC WORKS | 3/17/2014 | | 3/20/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
routed to Connie. fees are not based on bathroom fixtures so the approval and fees will not change due to bathroom being removed recieved via email
|
Routing - FIRE | 3/7/2014 | 3/7/2014 | 3/10/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Report Rev 2 03-10-14
|
Routing - FIRE | 2/27/2014 | 2/27/2014 | 3/7/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan report 03-07-14
|
Routing Off Site - STRUCTURAL | 3/7/2014 | | 3/7/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
singed off in e plan
|
Routing - PLAN CHECK | 2/27/2014 | | 3/7/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Erosion and Sediment | 2/27/2014 | | 3/4/2014 | | PASS |
Evan Jenkins
|
|
|
Revisions to Resubmitted Plan Approved
|
Routing - Design Review | 2/27/2014 | | 2/27/2014 | | FAIL |
Josh Wilson
|
|
|
Upload revised landscape plan as approved by DRH13-00405. Trees in parking lot must remain.
|
Routing - FIRE | 1/23/2014 | 1/23/2014 | 2/19/2014 | | FAIL |
Scott Arellano
|
|
|
See Attached report
|
1st review completed | | | 2/19/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing Off Site - STRUCTURAL | 1/23/2014 | | 2/18/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Failed off site structural see change marks in e plan
|
Routing - PLAN CHECK | 1/23/2014 | | 2/18/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see e plan changemarks
|
Routing - Design Review | 1/23/2014 | | 2/5/2014 | | FAIL |
Josh Wilson
|
|
|
DR Appeal period expired, however incorrect landscape plan uploaded. Please upload revised landscape plan showing trees within parking lot to remain. JGW 2-5-14
|
Routing - PLUMBING | 1/23/2014 | | 1/24/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing PW Sewer Rating | 1/23/2014 | | 1/24/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 1/23/2014 | | 1/23/2014 | | PASS |
Walt Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 1/23/2014 | | 1/23/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 1/23/2014 | | 1/23/2014 | | FAIL |
Evan Jenkins
|
|
|
No BMP's shown on Site Map: This is a requirement. Made redlines in the Erosion Control plan in ePlan Review on in the ESC Plan
|
Plan Reviewer's activity | | | 1/21/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
DR will be approved today. Got okay from Josh Wilson to approve the pre screen.
|
Intake Approval | | | 1/21/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 12/10/2013 | | FAIL |
|
|
|
1. This project requires planning and zoning approval prior to acceptance. Contact Sarah Schafer at ###-####
2. Please provide a room finish schedule.
3. In reviewing online documents there is a property line passing through the building. Per building code the lot line is not allowed to pass through the structure. Please contact Dave Abo at ###-#### or Todd Tucker at ###-#### to discuss a lot consolidation to remove the lot line.
4. Please provide Central District Health plan review and approval per the checklist.
5. While this item is not part of the prescreen the banquet room does not have any exit signs or exit discharge lighting indicated on the plans. As a department we take the room square footage of a dinning area and divide by 15 which makes the occupant load greater than 49 thus requiring 2 exits which in turn requires exit signs, exit discharge lighting and emergency power.
6. Form 304 Registered design professional indicated is not the Idaho Licensed Architect. Please resubmit the form with the Idaho licensed architect as the registered design professional.
|
Application received | | | 12/6/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 6 2013 10:12AM
|
Pending Assignment by JCM | 1/23/2014 | | | | |
John Menard
|
|
|
|