Second Notice | | 10/16/2014 | 10/24/2014 | | DONE |
Christina Prado
|
|
|
completed 10-24-14
|
First Notice | 9/29/2014 | 9/29/2014 | 10/6/2014 | | DONE |
Mike Jordan
|
|
|
mailed 10-7-14
|
FIRE-Final Inspection | 9/29/2014 | 9/30/2014 | 9/30/2014 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 9/29/2014 | 9/29/2014 | 9/29/2014 | P | PASS |
Mike Jordan
|
|
|
Please call 30min prior for access - Steve Phone #: ###-####
|
DOC - Permit Finaled | 9/29/2014 | 9/29/2014 | 9/29/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 9/26/2014 | 9/29/2014 | 9/29/2014 | A | NR |
Mike Jordan
|
|
|
Please call 30min prior to meet on site - Steve Phone #: ###-####. Needs zoning final.
|
Zoning Approval | 9/29/2014 | 9/29/2014 | 9/29/2014 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Conference | 6/26/2014 | 6/26/2014 | 6/26/2014 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Center popout ok.
|
Plan Reviewer's activity | | | 6/25/2014 | | PASS |
|
|
|
Reviewed deferred submittal for awnings.
|
BLD-Framing/Rough-in | 6/19/2014 | 6/20/2014 | 6/20/2014 | P | PASS |
Mike Jordan
|
|
|
Steve-would like a partial inspection and would like at 3:00 Phone #: ###-####. east popuot ok to sheet.
|
BLD-Framing/Rough-in | 6/17/2014 | 6/18/2014 | 6/18/2014 | A | PASS |
Mike Jordan
|
|
|
Steve Durell Phone #: ###-####. West pop out and middle pop out ok. Will also have engineering scanned in project on minor changes approved by engineer.
|
Issue PAID IN FULL permit | | | 5/21/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 5/21/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 5/16/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 5/16/2014 | | DONE |
Barbara Stitt
|
|
|
|
Expiration Notice | 5/12/2014 | 6/3/2014 | 5/12/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 12/9/2013 | 12/9/2013 | 4/4/2014 | | PASS |
Carl Westfall
|
|
|
ALBERTSONS EXTERIOR WALL FINISH UPGRADE - ePlanReview - Level 3 TI - (20 days - Jan 2)
|
Routing Off Site - STRUCTURAL | 4/2/2014 | | 4/4/2014 | | PASS |
|
|
|
(4-2-14) Routed to AHJ for the consultant review.
(4-4-14) Review completed late on a Friday.
|
Routing - PLAN CHECK | 4/2/2014 | | 4/4/2014 | | PASS |
Carl Westfall
|
|
|
(4-2-14) Routed to AHJ for the consultant review.
(4-4-14 Drawings approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2014 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/2/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/7/2014 | | 3/20/2014 | | FAIL |
Carl Westfall
|
|
|
Revised drawings submitted late on Friday. Drawings routed on the following Monday.
(3-20-14) 4th structural review completed but not approved.
|
Routing Off Site - STRUCTURAL | 3/10/2014 | | 3/20/2014 | | FAIL |
Carl Westfall
|
|
|
Craig Brasher
|
Plan resubmittals requested | | | 3/20/2014 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/7/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/21/2014 | | 2/26/2014 | | FAIL |
Carl Westfall
|
|
|
(2-24-14) Drawings submitted late on a Friday. Routing started on the following Monday.
(2-26-14) Now that a lateral analysis has been provided, further design is required so that code compliance is demonstrated. 3rd structural review failed.
|
Routing Off Site - STRUCTURAL | 2/24/2014 | | 2/26/2014 | | FAIL |
Carl Westfall
|
|
|
(2-24-14) Routed to the Consultant Structural Engineer.
(2-26-14) Now that a lateral analysis has been provided, further design is required so that code compliance is demonstrated.
|
Plan resubmittals requested | | | 2/26/2014 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/21/2014 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/31/2014 | | DONE |
|
|
|
Structural concerns not adequately addressed.
|
Routing - PLAN CHECK | 1/24/2014 | | 1/31/2014 | | FAIL |
Carl Westfall
|
|
|
Waiting for the structural consultant to finish his 2nd review.
2nd review failed
|
Routing Off Site - STRUCTURAL | 1/27/2014 | | 1/30/2014 | | FAIL |
|
|
|
Items not addressed
|
Plan resubmittals received | | | 1/24/2014 | | DONE |
|
|
|
|
1st review completed | | | 12/18/2013 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 12/18/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/9/2013 | | 12/18/2013 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required.
|
Routing Off Site - STRUCTURAL | 12/9/2013 | | 12/16/2013 | | FAIL |
|
|
|
Craig Brasher
|
Routing - FIRE | 12/9/2013 | 12/9/2013 | 12/12/2013 | | PASS |
Scott Arellano
|
|
|
|
Routing PW Drainage | 12/9/2013 | | 12/10/2013 | | PASS |
Brian Murphy
|
|
|
|
Pending Assignment by JCB | 12/9/2013 | | 12/9/2013 | | DONE |
Jason Blais
|
|
|
|
Routing - PUBLIC WORKS | 12/9/2013 | | 12/9/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 12/9/2013 | | 12/9/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - Erosion and Sediment | 12/9/2013 | | 12/9/2013 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver submitted and approved. Applicant needs to designate RP for ESC permit to be issued.
|
Routing - Design Review | 12/9/2013 | | 12/9/2013 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH13-00358
|
Application received | | | 12/6/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 6 2013 10:28AM
|
CHANGE STATUS TO (PND) | | | 12/6/2013 | | DONE |
|
|
|
Accidentally voided
|
Intake Approval | | | 12/6/2013 | | PASS |
Jason Blais
|
|
|
Prescreen passed by Tim Woodard and plan review fees paid.
|