First Notice | | 7/17/2014 | 7/23/2014 | | DONE |
|
|
|
This permit finaled on the web by derek cooper
|
Permanent Occupancy | | | 7/7/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 5/29/2014 | 5/29/2014 | 5/29/2014 | P | PASS |
Dave Hannah
|
|
|
Derrick Phone #: ###-####
|
BLD-Final | 5/28/2014 | 5/28/2014 | 5/29/2014 | P | PEND |
Dave Hannah
|
|
|
late today after Dixie does her final on the chiller on the roof
|
Temporary Occupancy | 5/22/2014 | 8/20/2014 | 5/22/2014 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 5/19/2014 | 5/20/2014 | 5/21/2014 | A | PART |
Dave Hannah
|
|
|
Derrik-Please call at least 30 mins prior so he can meet ya there Phone #: ###-#### ok for temp cc
|
FIRE-Final Inspection | 5/20/2014 | 5/21/2014 | 5/20/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory. Plan modification and project related FIR permits finaled. *NOTE- inspection finished on 5/20.
|
Plan assigned to (SRZ) | 5/16/2014 | 5/16/2014 | 5/20/2014 | | PASS |
Sam Zahorka
|
|
|
plan mod for chillers on roof
|
Routing - PLAN CHECK | 5/16/2014 | | 5/20/2014 | | PASS |
Sam Zahorka
|
|
|
Plan Modification
|
Case Summary (BLD) | | | 5/20/2014 | | DONE |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 5/20/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2014 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 5/20/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 5/20/2014 | | DONE |
Tisha Gallop
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/20/2014 | | DONE |
Candy A. Nichols
|
|
|
|
FIRE-Final Inspection | 5/16/2014 | 5/19/2014 | 5/19/2014 | A | PEND |
Forrest France
|
|
|
Pending plan modification and permit related FIR trade work.
|
Plan Modification Accepted | | | 5/16/2014 | | DONE |
Tisha Gallop
|
|
|
Plan modification accepted for structural engineering for chillers on roof; routed to Sam Zahorka
|
Zoning Approval | 4/30/2014 | 4/30/2014 | 4/30/2014 | | PASS |
Josh Wilson
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/18/2014 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 3/18/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (SRZ) | 3/5/2014 | 3/5/2014 | 3/14/2014 | | PASS |
Sam Zahorka
|
|
|
Bogus Plan Mod. - Pending Fire to PASS
|
Routing - PLAN CHECK | 3/14/2014 | | 3/14/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2014 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 3/14/2014 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 3/14/2014 | | DONE |
|
|
|
called Steve Trout and left mssg plan mod is ready and fee due.
|
Permit Ready to Issue | | | 3/14/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 3/13/2014 | | 3/14/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 3 Mod 03-14-14
|
Case Summary (BLD) | | | 3/13/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/5/2014 | | 3/13/2014 | | PASS |
Sam Zahorka
|
|
|
Plan Modification PASSED.
|
Plan resubmittals received | | | 3/12/2014 | | DONE |
Christina Prado
|
|
|
Received two sets of revised cover sheets as well as one transmittal; Taken to Sam for further review
|
Issue PAID IN FULL permit | | | 3/5/2014 | | DONE |
Christina Prado
|
|
|
|
Plan Modification Accepted | | | 3/5/2014 | | DONE |
Christina Prado
|
|
|
Plan modification accepted to reflect revisions and alterations of mezzaninie as well as add a fire suppression system;Plans taken to Sam Zahorka for further review
|
Plan assigned to (SRZ) | 12/10/2013 | 12/10/2013 | 2/7/2014 | | PASS |
Sam Zahorka
|
|
|
2nd Review Completed. Level 3 TI - Bogus Brewing Inc
|
Routing - Design Review | 2/6/2014 | | 2/7/2014 | | PASS |
Josh Wilson
|
|
|
OK per CZC14-00004
|
Routing - PLAN CHECK | 2/7/2014 | | 2/7/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2014 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 2/7/2014 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 2/7/2014 | | DONE |
Tisha Gallop
|
|
|
called Steve Trout and left message that permit is ready, fee due and need ACHD and GC form.
|
Permit Ready to Issue | | | 2/7/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 2/5/2014 | 2/5/2014 | 2/6/2014 | | PASS |
Craig D. Hanson
|
|
|
See Attached Fire Report 02-06-14
|
Routing - PLAN CHECK | 2/6/2014 | | 2/6/2014 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 1/17/2014 | | 2/5/2014 | | PASS |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 2/5/2014 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plan sheets marked A2.3, A6.0, A10.1, A10.2, A11.0 & A13.0; Plans taken to Sam Zahorka for further review
|
Case Summary (BLD) | | | 2/5/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - MECHANICAL | 1/16/2014 | | 1/17/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 1/14/2014 | | 1/16/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Plan resubmittals requested | | | 1/15/2014 | | DONE |
Tisha Gallop
|
|
|
received two copies of response and three copies of plan sheet A2.1; taken to Sam Zahorka
|
Routing - FIRE | 1/10/2014 | 1/10/2014 | 1/14/2014 | | FAIL |
Craig D. Hanson
|
|
|
Please see Fire Report (Rev 1) 01-14-14
|
Routing - PLAN CHECK | 1/7/2014 | | 1/13/2014 | | FAIL |
Sam Zahorka
|
|
|
2nd Review in progress
|
Plan resubmittals received | | | 1/9/2014 | | DONE |
Christina Prado
|
|
|
Recieved two sets of bld & fire review comments as well as two sets of plans marked Cover, A2.0, A2.1, A3.0, A10.0, A10.1, A11.0, A13.0 & E2.0L; Taken to Sam for further review
|
Routing - MECHANICAL | 1/6/2014 | | 1/7/2014 | | FAIL |
Troy James
|
|
|
Talked to Bob Tikker Mechanical Engineer
|
Routing - PLAN CHECK | 12/31/2013 | | 1/6/2014 | | FAIL |
Sam Zahorka
|
|
|
Routed to Mechanical for Review.
|
Routing - FIRE | 12/26/2013 | | 12/31/2013 | | FAIL |
Craig D. Hanson
|
|
|
Please see Fire Plan 1st Review
|
1st review completed | | | 12/31/2013 | | FAIL |
|
|
|
Failed Plan Check, Design Review, Fire
|
Routing - PLAN CHECK | 12/19/2013 | | 12/26/2013 | | FAIL |
Sam Zahorka
|
|
|
Routed to Fire
|
Routing - Design Review | 12/18/2013 | | 12/19/2013 | | FAIL |
Sarah Schafer
|
|
|
Sarah Schafer - Very minor exterior changes
Zoning Certificate needed for the storefront changes along Broad. I have contacted Steve Trout, he will submit the information through a zoning certificate and we will call the plans back upon completion. SMS
|
Routing - PLUMBING | 12/12/2013 | | 12/18/2013 | | PASS |
Bill VanDegrift
|
|
|
If P-7 services a hose real a PVB will be required.
|
Routing PW Sewer Rating | 12/12/2013 | | 12/12/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Solid Waste | 12/12/2013 | | 12/12/2013 | | PASS |
Peter J. McCullough
|
|
|
Alley service only
|
Routing PW Environmental | 12/12/2013 | | 12/12/2013 | | PASS |
Walt Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | | | 12/12/2013 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 12/12/2013 | | 12/12/2013 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver request submitted and approved
|
Routing - Addressing | 12/10/2013 | | 12/11/2013 | | PASS |
Emily Dixon
|
|
|
|
Pending Assignment by JCB | 12/10/2013 | | 12/10/2013 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 12/10/2013 | | DONE |
Jason Blais
|
|
|
Emailed architect to contact ACHD to determine if any additional impact fees are due. Written verification needs to be provided to our Permit Counter prior to the building permit being issued.
|
Intake Approval | | | 12/9/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/9/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/9/2013 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | | 12/6/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 6 2013 10:32AM
|