Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD13-03419
StatusFinaled
Name MEDINA GRACIELA H
Site Address 7203 W NORTHVIEW CIR
Project Name 
Customer Number 
ePlanReviewNo
Description
***1-7-2014 THIS PERMIT IS MODIFIED TO REFLECT THE 2ND PHASE OF THIS PERMIT FOR THE REMOVAL OF THE EXISTING EXTERIOR WALL IN ORDER TO OPEN UP THE NEW ADDED LIVING SPACE TO THE EXISTING. NEW BEAM SIZES ARE ATTACHE TO THE DOCUMENT SECTION OF THIS PERMIT. $501.00 added value to this permit.1-8-2014. pep*** This project is for the enclosure of an existing covered front porch area of 132s.f. with foundation to frost depth. There will be a 2nd phase to the project where the existing interior front wall will be removed by installing a girder truss or bean to support the existing main structure roof. The 2nd phase is not included in this permit. Separate electrical and ESC permits are required. All per the approved plans as marked and the plan review notes. pep
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/29/20185/30/20185/30/2018PPASS
DetailsJim Sly
Gracey Phone #: ###-####
DOC - Permit Finaled5/30/20185/30/20185/30/2018PPASS
DetailsJim Sly
BLD-Energy code compliance12/5/201412/5/201412/5/2014PPASS
DetailsJim Sly
Gerald Phone #: ###-####
BLD-Framing/Rough-in7/1/20147/2/20147/2/2014APASS
DetailsMike Jordan
gracie Phone #: ###-####. Needs to complete airseal and insulate.
BLD-Conference1/30/20141/30/20141/30/2014PPASS
DetailsTom Arcoraci
BLD-Framing/Rough-in1/28/20141/29/20141/29/2014APASS
DetailsTom Arcoraci
gracie Phone #: ###-#### ok to insulate ext walls ok to insulate rest when plumbing and electric roughs are complete ok to sheet rock kit cabinet area framing ok
BLD-Framing/Rough-in1/13/20141/13/20141/13/2014PPASS
DetailsJim Sly
Floor framing - Gracie Phone #: ###-####
OVERRIDE  1/8/2014  
Routing Walk-In (BLD)1/8/20141/8/20141/8/2014PPASS
DetailsPerry Paine
Plan assigned to (PEP)1/7/20141/7/20141/8/2014 PASS
DetailsPerry Paine
Routing Walk-In (BLD)1/6/20141/6/20141/8/2014PPASS
DetailsAdele J Schaffeld-Griffin
(taken to Adele) 1-8-2013 permit modified by pep
CHANGE STATUS TO (ISS)  1/8/2014 DONE
DetailsBarbara Stitt
(F) Reprint permit  1/8/2014 DONE
DetailsBarbara Stitt
Case Summary (BLD)  1/8/2014  
Inspection Record Card- Bld  1/8/2014  
CHANGE STATUS TO (REV)  1/8/2014 DONE
BLD-Framing/Rough-in1/3/20141/6/20141/6/2014APART
DetailsJim Sly
gracie Phone #: ###-####
New North wall shear nailing.....OK.
Plan Reviewer's activity  1/6/2014 DONE
DetailsAdele J Schaffeld-Griffin
met with home owner. I need distance from between bearing points and direction of ridge to get trib area in order to size the beam.
BLD-Footing12/20/201312/20/201312/20/2013PPASS
DetailsTom Arcoraci
MONTY PLEASE CALL BEFORE GOING OUT Phone #: ###-####
Routing Walk-In (Zoning)12/12/201312/12/201312/12/2013PPASS
DetailsColleen T Carroll
Routing Walk-In (BLD)12/12/201312/12/201312/12/2013PDONE
DetailsPerry Paine
Plan assigned to (PEP)12/12/201312/12/201312/12/2013 PASS
DetailsPerry Paine
Inspection Record Card- Bld  12/12/2013  
1st review completed  12/12/2013 DONE
PLANS/APPL TAKEN TO FRONT DESK  12/12/2013 DONE
Permit Ready to Issue  12/12/2013  
Issue PAID IN FULL permit  12/12/2013 DONE
Application received 12/12/2013