Case Summary (BLD) | | | 9/12/2014 | | DONE |
|
|
|
|
BLD-Final | 8/1/2014 | 8/4/2014 | 8/4/2014 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Austin Wagner
|
DOC - Permit Finaled | 8/4/2014 | 8/4/2014 | 8/4/2014 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 8/1/2014 | 8/1/2014 | 8/1/2014 | P | CANC |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Austin Wagner
|
BLD-Blower Door Test Results | 8/1/2014 | 8/1/2014 | 8/1/2014 | P | PASS |
Phil Shearer
|
|
|
3.7
|
BLD-Energy code compliance | 5/29/2014 | 5/29/2014 | 5/29/2014 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Austin Wagner
|
BLD-Framing/Rough-in | 5/27/2014 | 5/28/2014 | 5/28/2014 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Austin Wagner
|
BLD-Framing/Rough-in | 5/27/2014 | 5/28/2014 | 5/27/2014 | A | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Austin Wagner Inspection cancelled from web by: Austin Wagner
|
BLD-Framing/Rough-in | 5/21/2014 | 5/22/2014 | 5/22/2014 | P | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Austin Wagner Inspection cancelled from web by: Austin Wagner
|
BLD-Framing/Rough-in | 5/21/2014 | 5/21/2014 | 5/21/2014 | P | FAIL |
Dave Hannah
|
|
|
BLD-COM/RES INSPECTOR
|
BLD-Wall Bracing | 5/7/2014 | 5/7/2014 | 5/7/2014 | P | PASS |
Jim Sly
|
|
|
This lot and block is actually 6-9 Timberside . The address is correct. Phone #: ###-#### >> Inspection requested via web by Austin Wagner
|
BLD-Footing | 4/7/2014 | 4/8/2014 | 4/9/2014 | P | PASS |
Dave Hannah
|
|
|
Heron Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 3/31/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (JG) | 3/25/2014 | 3/25/2014 | 3/28/2014 | | PASS |
Javier Guzman
|
|
|
eplan mod to mirror house
|
Routing - PLAN CHECK | 3/25/2014 | | 3/28/2014 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLANNING | 3/25/2014 | | 3/28/2014 | | PASS |
Leon Letson
|
|
|
Signed off in ePlan review by Leon Letson, plan mod to mirror house
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2014 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 3/25/2014 | | DONE |
Tisha Gallop
|
|
|
started workflow to mirror the house
|
Issue PAID IN FULL permit | | | 2/24/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 2/24/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 1/7/2014 | | |
|
|
|
|
Plan assigned to (JG) | 12/23/2013 | 12/23/2013 | 1/7/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, Pending Mech, Due 1/03 L1 ePlan **
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/7/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - MECHANICAL | 1/6/2014 | | 1/6/2014 | | PASS |
Troy James
|
|
|
approved with notes
|
Routing - PLAN CHECK | 12/30/2013 | | 12/31/2013 | | PASS |
Javier Guzman
|
|
|
PRJ DOX CASE
|
1st review completed | | | 12/31/2013 | | FAIL |
Javier Guzman
|
|
|
Mech
|
Route to Impact Fee Review | 12/23/2013 | 12/27/2013 | 12/30/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 12/23/2013 | 12/26/2013 | 12/30/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 12/23/2013 | | 12/30/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 12/23/2013 | | 12/30/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 12/23/2013 | | 12/27/2013 | | PASS |
Leon Letson
|
|
|
|
Routing - MECHANICAL | 12/23/2013 | | 12/27/2013 | | FAIL |
Troy James
|
|
|
eplan, need to revise orientation to show the front door facing East.
|
Application received | | | 12/13/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 13 2013 2:15PM
|
Intake Approval | | | 12/13/2013 | | PASS |
|
|
|
|