Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD13-03477
StatusFinaled
Name DAUBY CONSTRUCTION MGMT
Site Address 408 E PARKCENTER BLVD Unit: 210
Project NameIvie and Associates TI
Customer Number 
ePlanReviewYes
Description
(Ivie and Associates TI) (Suite 210)Plan Modification 2/27/14 to add a 100 sq foot office in the open office area. Permit to construct office partition walls for the existing vanilla finish space. Vanilla finish was under BLD11-00308. Scope of work to include nonbearing noncombustible walls to create 5 offices, 2 conference rooms, 1 copy room, 1 break room and open office space. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 5/5/20145/11/2014 DONE
This permit finaled on the web by Justin Dauby
First Notice 4/17/20144/25/2014 DONE
DetailsChristina Prado
Permanent Occupancy  4/7/2014 DONE
DetailsTisha Gallop
BLD-Final4/3/20144/4/20144/4/2014PPASS
DetailsJim Storey
Ben Phone #: ###-####
FIRE-Final Inspection4/3/20144/4/20144/4/2014APASS
DetailsForrest France
Fire life safety inspection completed satisfactory.
BLD-Framing/Rough-in3/10/20143/11/20143/11/2014PPASS
DetailsJim Storey
Ben Phone #: ###-#### ok pending ele aproval.
CHANGE STATUS TO (ISS)  3/4/2014 DONE
DetailsChristina Prado
(F) Reprint permit  3/4/2014 DONE
DetailsChristina Prado
Print Occupancy Form  3/4/2014 DONE
DetailsChristina Prado
CHANGE STATUS TO (ISS)  3/4/2014 DONE
DetailsChristina Prado
Plan assigned to (AJS)2/26/20142/26/20142/27/2014 PASS
DetailsAdele J Schaffeld-Griffin
plan mod
Routing - PLAN CHECK2/27/2014 2/27/2014 PASS
DetailsAdele J Schaffeld-Griffin
revisions submitted 2/26/14
CHANGE STATUS TO (ISS)  2/26/2014 DONE
started plan mod before co was issued
BLD-Final2/25/20142/25/20142/25/2014PPASS
DetailsDave Hannah
Ben Phone #: ###-####
Plan Modification Accepted  2/25/2014 DONE
mod started - adding space
Permanent Occupancy  2/25/2014 DONE
DetailsChristina Prado
FIRE-Final Inspection2/21/20142/21/20142/21/2014PPASS
DetailsForrest France
Fire life safety passed.
BLD-Final2/21/20142/21/20142/21/2014PPART
DetailsJim Storey
ben Phone #: ###-#### temp ok// final occ ok pending ele final.
Temporary Occupancy2/21/20145/22/20142/21/2014 DONE
DetailsChristina Prado
BLD-Ceiling Grid Inspection2/5/20142/5/20142/5/2014PPASS
DetailsJim Storey
Ben-PLease call prior to insepctrion Phone #: ###-####
BLD-Framing/Rough-in1/17/20141/21/20141/21/2014APASS
DetailsJim Storey
ben Phone #: ###-####
Permit Ready to Issue  1/13/2014  
Print Occupancy Form  1/13/2014 DONE
Issue PAID IN FULL permit  1/13/2014 DONE
Plan assigned to (AJS)12/30/201312/30/20131/10/2014 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Due 1/3 Live and Associates
PLANS/APPL TAKEN TO FRONT DESK  1/10/2014 DONE
Routing - Addressing1/3/2014 1/6/2014 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS12/30/2013 1/3/2014 PASS
DetailsAdele J Schaffeld-Griffin
signed off in e plan
Routing PW Sewer Rating1/3/2014 1/3/2014 PASS
DetailsAdele J Schaffeld-Griffin
signed off in e plan
1st review completed  1/3/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK12/30/2013 1/3/2014 PASS
DetailsAdele J Schaffeld-Griffin
Routing - Addressing12/30/2013 12/30/2013 FAIL
DetailsEmily Dixon
Needs suite number.
Intake Approval  12/30/2013 PASS
DetailsAdele J Schaffeld-Griffin
Application received  12/18/2013 DONE
Application submitted via PDS Online on Dec 18 2013 2:42PM