Third Notice | | 6/16/2014 | 7/9/2014 | | DONE |
|
|
|
mailed to Mark Lockwood
|
Second Notice | | 5/5/2014 | 6/11/2014 | | DONE |
Barbara Stitt
|
|
|
bad address and phone #; send to tenant/applican Mark Lockwood
Mailed 6-11-14
|
First Notice | | 4/10/2014 | 4/25/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 3/31/2014 | 3/31/2014 | 3/31/2014 | P | PASS |
Mike Jordan
|
|
|
Between 2-4 if possible please--Stacy Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 3/31/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 3/27/2014 | 3/28/2014 | 3/28/2014 | P | NR |
Mike Jordan
|
|
|
stacy Phone #: ###-####. Needs mech. final first.
|
FIRE-Final Inspection | 3/28/2014 | 3/28/2014 | 3/28/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 3/27/2014 | 3/28/2014 | 3/28/2014 | A | FAIL |
Troy Cobbley
|
|
|
Repair the FACP, tag and mount the fire extinguisher and provide emergency lighting at the rear exit.
|
Zoning Approval | 3/28/2014 | 3/28/2014 | 3/28/2014 | | DONE |
Sarah Schafer
|
|
|
|
BLD-Framing/Rough-in | 3/7/2014 | 3/7/2014 | 3/7/2014 | P | PASS |
Mike Jordan
|
|
|
Stacy Between 2-3 if possible please Phone #: ###-####
|
Print Occupancy Form | | | 1/31/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 1/31/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 1/29/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 12/31/2013 | 12/31/2013 | 1/27/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 1/13 San Francisco Sourdough eatery
|
Routing - MECHANICAL | 1/27/2014 | | 1/27/2014 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/2014 | | DONE |
|
|
|
|
Routing - MECHANICAL | 1/23/2014 | | 1/23/2014 | | FAIL |
Troy James
|
|
|
notes on eplan
|
Routing - PLAN CHECK | 1/16/2014 | | 1/17/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
need plumbing review and mechanical corrections
|
Routing - MECHANICAL | 1/16/2014 | | 1/17/2014 | | FAIL |
Troy James
|
|
|
eplan, need type 2 hood over convection oven
|
Routing - PLUMBING | 1/16/2014 | | 1/17/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Plan Reviewer's activity | | | 1/17/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
emailed Mark 1/17/14
Mark,
I received the revised plans for BLD13-03495 yesterday 1/16/14 and routed them to;
The PW Environmental reviewer and Walt has approved the permit.
The plumbing review will have to be completed prior to issuing the permit and as of now it has not been completed.
The mechanical review has been completed and the review failed. A type 2 hood is required by the mechanical plan reviewer over the free standing convection oven.
The building plan review has been completed with no additional comments. I will not be able issue the permit until all departments have approved the permit.
Plumbing and mechanical did not review the original submittal as the required plans were not submitted with the package for this food handling establishment.
If you have any questions please feel free to contact me.
Thank you
Adele Schaffeld-Griffin
Plans Examiner II
City of Boise PDS
###-####
|
Routing PW Environmental | 1/16/2014 | | 1/16/2014 | | PASS |
Walt Baumgartner
|
|
|
Applicant has indicated TI will connect to existing on site grease interceptor installed w/ original shell & core project in 2000.
Plans approved
|
Routing PW Solid Waste | 12/31/2013 | | 1/9/2014 | | PASS |
Peter J. McCullough
|
|
|
signed off in eplan
|
1st review completed | | | 1/9/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 12/31/2013 | | 1/9/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan
|
Routing PW Sewer Rating | 12/31/2013 | | 1/9/2014 | | PASS |
Connie Baumgartner
|
|
|
signed off in e plan
|
Routing PW Environmental | 12/31/2013 | | 1/3/2014 | | FAIL |
Walt Baumgartner
|
|
|
|
Routing - Addressing | 12/31/2013 | | 12/31/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 12/31/2013 | | 12/31/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Design Review | 12/31/2013 | | 12/31/2013 | | PASS |
Sarah Schafer
|
|
|
Approved per CZC13-00282 issued 12-31-13.
|
Intake Approval | | | 12/31/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
ok to take in by Sara Schafer
|
Intake Approval | | | 12/26/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
A Zoning Certificate is required for the changes being made to the exterior of the building. Please contact Sara Schafer at ###-#### if you have any questions. Once you have the zoning certificate please upload it into the documents folder and resubmit the pre screen.
Thank you
|
Application received | | | 12/19/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 19 2013 3:46PM
|