BLD-Final | 9/8/2014 | 9/8/2014 | 9/8/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
DOC - Permit Finaled | 9/8/2014 | 9/8/2014 | 9/8/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 9/8/2014 | 9/8/2014 | 9/8/2014 | P | DONE |
Mike Jordan
|
|
|
5
|
BLD-Energy code compliance | 7/23/2014 | 7/24/2014 | 7/24/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Framing/Rough-in | 7/22/2014 | 7/22/2014 | 7/22/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Framing/Rough-in | 7/21/2014 | 7/22/2014 | 7/22/2014 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark. Needs to complete airseal pack.
|
BLD-Wall cover | 6/16/2014 | 6/16/2014 | 6/16/2014 | P | PASS |
Mike Jordan
|
|
|
Firewall completion in roof areas and exterior walls. Same inspection for lots 184-191. Please call Jim at ###-#### 30 minutes prior to inspection. Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Wall cover | 4/24/2014 | 4/24/2014 | 4/24/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark. 3rd floor firewall ok.
|
BLD-Wall Bracing | 4/23/2014 | 4/23/2014 | 4/23/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark. 3rd floor wall bracing ok.
|
BLD-Wall cover | 4/18/2014 | 4/18/2014 | 4/18/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark. 2nd floor 2hr.wall ok.
|
BLD-Energy code compliance | 4/18/2014 | 4/18/2014 | 4/18/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 4/17/2014 | 4/17/2014 | 4/17/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark. 2nd. floor shear nailing ok.
|
BLD-Wall cover | 4/15/2014 | 4/15/2014 | 4/15/2014 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 4/14/2014 | 4/15/2014 | 4/15/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark
|
BLD-Wall cover | 4/15/2014 | 4/15/2014 | 4/15/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark. 1st. floor firewall ok.
|
BLD-Wall cover | 4/14/2014 | 4/14/2014 | 4/14/2014 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Stark Inspection cancelled from web by: Brian Stark
|
BLD-Footing | 3/31/2014 | 3/31/2014 | 3/31/2014 | A | PASS |
Mike Jordan
|
|
|
Flatwork Phone #: ###-#### >> Inspection requested via web by James Larkin. Interior footing ok.
|
BLD-Energy code compliance | 3/21/2014 | 3/24/2014 | 3/24/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Energy code compliance | 3/21/2014 | 3/21/2014 | 3/21/2014 | P | PASS |
Mike Jordan
|
|
|
rigid insulation at exterior foundation under slab on grade.
|
BLD-Foundation | 3/17/2014 | 3/18/2014 | 3/18/2014 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Footing | 3/17/2014 | 3/17/2014 | 3/17/2014 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
Issue PAID IN FULL permit | | | 2/20/2014 | | DONE |
|
|
|
|
OVERRIDE | | | 1/9/2014 | | |
|
|
|
|
Plan assigned to (AJS) | 1/8/2014 | 1/8/2014 | 1/9/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 1/9/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2014 | | DONE |
|
|
|
|
1st review completed | | | 1/9/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Inspection Record Card- Bld | | | 1/9/2014 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 1/9/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 1/6/2014 | | 1/9/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (JG) | 12/24/2013 | 12/24/2013 | 1/8/2014 | | DEFR |
Javier Guzman
|
|
|
Due 1/09 L2 ***
|
Routing - MECHANICAL | 12/27/2013 | | 1/3/2014 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 12/24/2013 | 12/27/2013 | 12/30/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 12/26/2013 | | 12/27/2013 | | PASS |
Sue Cummings
|
|
|
Sue Cummings
|
Routing - PUBLIC WORKS | | | 12/26/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 12/24/2013 | | 12/24/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/24/2013 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | 12/23/2013 | 12/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 12/23/2013 | | PASS |
Barbara Stitt
|
|
|
|