BLD-Final | 8/19/2014 | 8/19/2014 | 8/19/2014 | P | PASS |
Mike Jordan
|
|
|
Please call Brian prior Phone #: ###-#### Inspection requested via web by Brian Stark
|
DOC - Permit Finaled | 8/19/2014 | 8/19/2014 | 8/19/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 7/16/2014 | 7/16/2014 | 7/16/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 7/16/2014 | 7/16/2014 | 7/16/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Framing/Rough-in | 7/10/2014 | 7/11/2014 | 7/11/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Framing/Rough-in | 7/8/2014 | 7/9/2014 | 7/9/2014 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark. Provide additional studs on either side of 2plyin garage to providebearing at end of wall, Also repair bottom plate at this location. Complete all fireblocking Provide 2 layers of 5/8 type x rock at soffits. Install baffels and rulers in attic. Steps in garge are non code compliant.
|
BLD-Wall Bracing | 7/9/2014 | 7/9/2014 | 7/9/2014 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark. Several areas were sheating is not attached. Correction notice posted.
|
BLD-Wall cover | 5/19/2014 | 5/20/2014 | 5/20/2014 | A | PASS |
Mike Jordan
|
|
|
Firewall assembly Phone #: ###-#### >> Inspection requested via web by Brian Stark. 3rd story ok.
|
BLD-Wall cover | 5/14/2014 | 5/15/2014 | 5/15/2014 | A | PASS |
Mike Jordan
|
|
|
Second story firewall Phone #: ###-#### >> Inspection requested via web by Brian Stark. 2nd story 2hr. firewall ok.
|
BLD-Energy code compliance | 3/14/2014 | 3/14/2014 | 3/14/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 3/11/2014 | 3/11/2014 | 3/11/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 3/10/2014 | 3/11/2014 | 3/11/2014 | A | NR |
Mike Jordan
|
|
|
Juron Phone #: ###-####. Moved to pm.
|
BLD-Footing | 3/10/2014 | 3/10/2014 | 3/10/2014 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin. Will reschedule.
|
Issue PAID IN FULL permit | | | 2/20/2014 | | DONE |
|
|
|
|
OVERRIDE | | | 1/8/2014 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/8/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 1/8/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (JG) | 12/24/2013 | 12/24/2013 | 1/6/2014 | | PASS |
Javier Guzman
|
|
|
Due 1/10 L2 ***
|
1st review completed | | | 1/6/2014 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 1/6/2014 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/6/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | | | 1/6/2014 | | PASS |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 12/24/2013 | 12/27/2013 | 12/30/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 12/23/2013 | 12/27/2013 | 12/30/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - MECHANICAL | 12/27/2013 | | 12/30/2013 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 12/24/2013 | | 12/30/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | | | 12/30/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 12/30/2013 | | 12/27/2013 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/24/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/24/2013 | | PASS |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/24/2013 | | DONE |
Christina Prado
|
|
|
|
Application received | | 12/23/2013 | | | |
|
|
|
|