BLD-Final | 1/14/2015 | 1/14/2015 | 1/14/2015 | P | PASS |
Mike Jordan
|
|
|
Please call brian prior. Phone #: ###-#### Inspection requested via web by Brian Stark
|
DOC - Permit Finaled | 1/14/2015 | 1/14/2015 | 1/14/2015 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 9/10/2014 | 9/12/2014 | 9/12/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Framing/Rough-in | 9/10/2014 | 9/10/2014 | 9/10/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 8/13/2014 | 8/14/2014 | 8/14/2014 | P | PASS |
Mike Jordan
|
|
|
3rd floor shear Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Wall cover | 8/13/2014 | 8/14/2014 | 8/14/2014 | A | PASS |
Mike Jordan
|
|
|
Firewall Phone #: ###-#### Inspection requested via web by Brian Stark. 3rd. floor ok.
|
BLD-Wall Bracing | 8/11/2014 | 8/11/2014 | 8/11/2014 | P | PASS |
Mike Jordan
|
|
|
2nd floor shear Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 8/8/2014 | 8/8/2014 | 8/8/2014 | P | PASS |
Mike Jordan
|
|
|
2nd floor shear. Please inspect between 10 and 11 am. Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 8/7/2014 | 8/8/2014 | 8/8/2014 | A | NR |
Mike Jordan
|
|
|
2nd floor shear Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 8/6/2014 | 8/7/2014 | 8/7/2014 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Footing | 6/2/2014 | 6/2/2014 | 6/2/2014 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Energy code compliance | 5/7/2014 | 5/7/2014 | 5/7/2014 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin. Rigid insulation at stemwall, under slab on grade.
|
BLD-Foundation | 5/2/2014 | 5/2/2014 | 5/2/2014 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Footing | 5/1/2014 | 5/1/2014 | 5/1/2014 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
Issue PAID IN FULL permit | | | 2/20/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 1/9/2014 | | |
|
|
|
|
Plan assigned to (AJS) | 1/8/2014 | 1/8/2014 | 1/9/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 1/9/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 1/9/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/9/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 1/9/2014 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 1/9/2014 | | DONE |
Tisha Gallop
|
|
|
called Jim and told him permit is ready and fee due
|
Routing - PLAN CHECK | 1/7/2014 | | 1/9/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (JG) | 12/24/2013 | 12/24/2013 | 1/8/2014 | | DEFR |
Javier Guzman
|
|
|
Due 1/09 L2 ***
|
Routing - MECHANICAL | 12/27/2013 | | 1/7/2014 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 12/24/2013 | 12/27/2013 | 12/30/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 12/26/2013 | | 12/27/2013 | | PASS |
Sue Cummings
|
|
|
Sue Cummings
|
Routing - PUBLIC WORKS | | | 12/26/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 12/24/2013 | | 12/24/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/24/2013 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | 12/23/2013 | 12/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 12/23/2013 | | PASS |
Barbara Stitt
|
|
|
|