Case Summary (BLD) | | | 11/6/2015 | | DONE |
|
|
|
|
Second Notice | | 3/10/2014 | 4/1/2014 | | DONE |
|
|
|
Faxed 4-1-14
|
First Notice | | 2/10/2014 | 2/28/2014 | | DONE |
Christina Prado
|
|
|
mailed 2/28
|
Permanent Occupancy | | | 1/31/2014 | | DONE |
|
|
|
|
BLD-Final | 1/29/2014 | 1/30/2014 | 1/30/2014 | P | PASS |
Dave Hannah
|
|
|
Call prior to going Phone #: 8415809 >> Inspection requested via mobile web by Mike
|
FIRE-Final Inspection | 1/29/2014 | 1/30/2014 | 1/30/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
BLD-Framing/Rough-in | 1/21/2014 | 1/22/2014 | 1/22/2014 | A | PASS |
Dave Hannah
|
|
|
Call prior to going Phone #: 8415809 >> Inspection requested via mobile web by Mike
|
Print Occupancy Form | | | 1/7/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/7/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/7/2014 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 12/31/2013 | 12/31/2013 | 1/6/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 1/6 Hall Suite
|
Routing - Addressing | 12/31/2013 | | 1/6/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
signed off in e plan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/6/2014 | | DONE |
|
|
|
|
Routing PW Sewer Rating | 12/31/2013 | | 1/3/2014 | | PASS |
Connie Baumgartner
|
|
|
|
1st review completed | | | 1/3/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 12/31/2013 | | 1/3/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 12/31/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PUBLIC WORKS | 12/31/2013 | | 12/31/2013 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 12/30/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 30 2013 4:24PM
|